Malvern Hills District Council
Executive Committee, Tuesday 24 January 2023 at 5.00pm

Tenbury Community Pool Rising Cost Pressures

Approved Executive 1 paper

Executive Committee approved this item on Tuesday 24 January 2023. Below is the council's own wording, with the papers it was decided on.

Item54

Resolved

that i ) A grant of up to £115,000 for Tenbury Community Pool Limited be approved and funded from the priorities earmarked reserve. ii) That delegated authority be given to the Deputy Chief Executive and Director of Communities and Housing in consultation with the Portfolio Holder for Resources, to finalise the level of capital grant award in line with the outcome of other external grant fund bids by Tenbury Community Pool and the associated terms and conditions.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 6 pages

EXECUTIVE COMMITTEE 24 JANUARY 2023

TENBURY COMMUNITY POOL RISING COST PRESSURES Relevant wards: All Portfolio holder: Cllr Tom Wells, leader of the Council and Portfolio Holder for Community Services

Director: Jen Taylor, Director for Communities and Housing

Contact officer: Mark Hammond, Community Infrastructure and Development Manager If you have any questions about this report, please contact the portfolio holder or the contact officer.

1. Purpose and summary 1.1 To report on the rising energy costs and the impact on Tenbury Community Pool (TCP).

1.2To set out actions taken to date and planned by Freedom Leisure, Tenbury Community Pool Ltd and the Council to respond to the challenge, including proposals for additional capital works.

1.3Provide TCP with a grant of up to £115,000 to help ensure the facility is fit for purpose and financially viable for years to come and thus minimise the level of additional revenue grant support that is required from the Council.

2. Recommendations i) That a grant of up to £115,000 to Tenbury Community Pool Limited (TCP) be approved and be funded from the priorities earmarked reserve.

ii) That delegated authority be given to the Deputy Chief Executive and Director of Communities and Housing in consultation with the Portfolio Holder responsible for Resources, to finalise the level of capital grant award in line with the outcome of other external grant fund bids by TCP and the associated terms and conditions.

3. Background 3.1 Tenbury Pool is owned and operated by Tenbury Community Pool Ltd (TCP), a Charitable Company Limited by Guarantee in 2014. MHDC supported TCP with the tendering of a new operator in 2014, as part of the Council’s tendering process for its own leisure stock. TCP awarded a 10-year contract to Freedom Leisure (FL) to operate the pool, commencing April 2015.

3.2The pool plays a critical role within the rural north of the district, delivering on the Council’s priority to “promote health, fitness and wellbeing through community outreach programmes and support for leisure centres, with 1.5mn visits in the plan period”, and in tackling health inequalities and levelling up communities. A recent DCN report, “Fit for the Future: The Health Value of Wellbeing and Leisure Services”, shows that engagement with every 1 million inactive people in England could lead to £314Mn saving to the NHS.

3.3Under the contract TCP are responsible for funding FL’s management fee, building insurance, and major capital enhancement and replacement works to the fabric of the building and static components above £10,000. TCP has no direct source of regular income and is wholly reliant on an annual Council grant, other external grants secured from time to time and fundraising initiatives.

3.4The Council has paid an annual fixed rate grant of £68,476 to TCP since the commencement of the contract in 2015. This grant covers the operational losses at TCP, and without this subsidy the facility would not be economically viable. TCP has a long-term aim to provide a financially sustainable leisure centre that is less reliant on Council grant support.

3.5In 2020, TCP completed a £450,000 refurbishment and extension project funded through a Section 106 grant of £200,000 from the Council, a Sport England grant of £50,000, and £200,000 from other funding sources.

3.6The refurbishment enabled FL to drive up the levels of participation in swimming and fitness-based activities by 64% and drive down electricity usage by 22% and gas usage by 67%, compared to pre-covid levels.

3.7FL and TCP had made positive steps towards financial sustainability as illustrated in Chart 1, and prior to the energy and cost of living crisis were forecast to make an operating profit for the first time in 2022/23. Chart 1. Overall profit/loss profile

60000 * £51,135 40000

0 2015/16 2016/17 2017/18 2018/19 2019/20 2021/22 2022/23 -20000 -£2,748

-40000 -£31,106 -£43,840 -60000 -£49,314 -£47,935

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tenbury Community Pool Rising Cost PressuresReport 6 pages DownloadRead as text

At this meeting

Whole meeting

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies