Executive Committee, Tuesday 24 January 2023 at 5.00pm

Replacement of Curtain Walling at Malvern Splash

Approved Executive 1 paper

Executive Committee approved this item on Tuesday 24 January 2023. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

that capital expenditure of up to £420,000 to replace the curtain walling on the park side elevation of Malvern Splash, be approved.
Word for word from the decision Malvern Hills published for this meeting. Source: moderngov.malvernhills.gov.uk

Follow this further

Built from Malvern Hills's papers

What the report saysPro

Report to Executive Committee, 3 pages

EXECUTIVE COMMITTE 23 January 2023

REPLACEMENT OF CURTAIN WALLING AT MALVERN SPALSH Relevant wards: Priory

Portfolio holder: Cllr Peter Whatley, Portfolio Holder for Resources

Director: Andy Baldwin, Deputy Chief Executive Contact officer: Sandra Hudson, Head of Property and Customer Services If you have any questions about this report, please contact the portfolio holder or the contact officer.

1. Purpose and summary 1.1 To seek the Committee’s approval for capital expenditure of up to £420,000 to replace the curtain walling on the park side elevation of Malvern Splash

2. Recommendations i) That capital expenditure of up to £420,000 to replace the curtain walling on the park side elevation of Malvern Splash, be approved.

3. Background 3.1 The existing curtain walling is over 30 years old and we are finding that we have to rescure/replace and increasing number of the glazed units.

3.2An application for planning permission for the phased replacement of the curtain walling at Malvern Splash was approved on 27 October 2020.

3.3Phase I was undertaken as part of the pool refurbishment in 2020/21 with phase II programmed for 2022/23. There is an existing allocation of £350,000 in the Capital Programme for these works which was calculated with reference to the cost of replacing the curtain walling on the Priory Road elevation.

3.4The project has now been tendered but due to the escalating cost of materials and labour, the lowest tender price exceeded the capital programme allocation. To try to bring the project within budget, we looked at a value engineering solution where, instead of replacing the whole wall, the glazed units would still be replaced with more energy efficient ones and the remainder of the walling sprayed to match the colour of the Priory Road elevation.

3.5All but one of the tenderers declined to price for the variation as they would be unable to provide a guarantee for the work. The one contractor who did quote gave a saving on their original tender price but this was still in excess of the lowest tender price for full replacement.

3.6The lowest price received for full replacement of the curtain walling is £404,000 but authority for a spend of up to £420,000 is being sought to accommodate material cost inflation which may occur between the tender return date and placement of the order.

3.7Full replacement of the curtain walling will be guaranteed for 10 years and the upgrading of the glazing from the double glazed units we currently have to modern tripled glazed ones could save around 30,000kWh of energy and 6tCO2e per year. This figure represents an energy saving of 14.3% for the floor area directly impacted by the curtain walling on this elevation.

4. Implications and impact 4.1 What are the financial/resource implications? A capital spend £70,000 in excess of the funding allocated in the Capital Programme

4.2What are the risks? Reputational in failing to meet our 5 year plan objectives of:

• reducing our greenhouse gas emissions • becoming carbon neutral and delivering Destination Zero • investing in our community facilities

5. Outcomes of the impact assessment 5.1 Privacy Not applicable 5.2 Council priorities Reducing greenhouse gas emissions, becoming carbon neutral and delivering Destination Zero, investing in our community facilities.

5.3Equalities None

Appendices • None

Background papers • Planning application number 20/01107/FUL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Replacement of Curtain Walling at Malvern SplashReport 3 pages DownloadRead as text

At this meeting

Whole meeting

More from Malvern Hills Executive Committee

All decisions
MeetingDecisionOutcome
15 Sep 2026 Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... Decided Open
15 Sep 2026 Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... Noted Open
15 Sep 2026 Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... Noted Open
15 Sep 2026 Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... Agreed Open
15 Sep 2026 Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies