Resolved
Resolved that Executive Committee note the progress to date.
Executive Committee noted this item on Tuesday 23 January 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that Executive Committee note the progress to date.
EXECUTIVE COMMITTEE January 2024
UK Shared Prosperity and Rural England Prosperity Fund Updates Relevant wards: All wards Portfolio holder: Cllr Beverley Nielsen Head of Service: Simon Smith Contact officer: Elspeth McQueen If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 To update on the progress of the delivery of the UK Shared Prosperity Fund (UKSPF) Programme.
1.2To update on the progress of the delivery of the Rural England Prosperity Fund (REPF) Programme.
2. Recommendations 2.1 The Committee note the progress to date.
3. Background 3.1 The UKSPF was announced in late Spring 2022 and is a central pillar of the UK Government’s Levelling Up agenda. It supports local investments across the themes of;
i) Community and Place;
ii) Supporting Local Business; and
iii) People and Skills. 3.2 Malvern’s Investment Plan was submitted August 2022 and formally approved in January 2023. Delivery is eligible from April 2022 to March 2025.
3.3The REPF was announced in September 2022 and supports the aims of the government’s Levelling Up White Paper and Future Farming Programme. It funds capital projects for small businesses and community infrastructure in rural areas.
3.4Malvern’s Investment Plan addendum for REPF was submitted November 2022 and formally approved in April 2023. Delivery is eligible from April 2023 to March 2025.
3.5Overall programme budget:
i) UKSPF budget: £2,420,526
ii) REPF budget: £500,624
iii) Total budget: £2,938,926
3.6A progress report for April – September 2023 was submitted to DLUHC at the beginning of January 2024. A total spend of £249,259 was reported for this period against a profiled target for the year of £929,706. A further £189,594 of spend was achieved just outside the reporting period bringing the total spend to £438,853 (47% of the total profiled budget for 2023/24).
3.7All UKSPF and REPF funding (£2,938,926) is now allocated to projects through the approved governance processes including discussion at the appropriate Panel followed by final approval at Executive Committee.
3.8The table at Appendix 1 details the UKSPF projects approved to date.
3.9The REPF funding is being delivered as a funding opportunity for rural businesses (the Malvern Hills Rural Fund). To date 23 Expressions of Interest have been submitted with 14 projects going through to Full Application. 8 projects worth a total of £825k have been approved; £136k of which is REPF funding and the rest is made up of private match funding.
3.10Confirmation has been received from DLUHC that unspent funding for 2023/24 can be rolled over into 2024/25. Underspend of more than 20% will result in funding being paid on a percentage basis until spend is evidenced; Malvern Hills’ programme is currently on track to achieve at least 80% spend in 2023/24.
4. Implications and impact 4.1 What are the financial/resource implications? 4.2 A management and administration budget is built into the UKSPF Programme. A UKSPF team has been appointed to manage and administer the funding. 4.3 What are the risks? 4.4 An underspend of greater than 20% in 2023/24 could occur. All funding is now allocated to projects which decreases the risk of underspend and Malvern Hills’ programme is currently on track to achieve at least 80% spend in 2023/24. The projects at higher risk of underspend are being monitored and managed closely to ensure the greatest level of spend achievable occurs in 2023/24. Should an underspend greater than 20% occur the funding would not be automatically lost to Malvern Hills and steps would be taken to ensure that the whole budget allocation was used before 31st March 2025.
4.5DLUHC recently published revised outputs and outcomes definitions. There was a risk that some of the outputs and outcomes profiled in the Investment Plan would not be achieved as a result of the revised definitions. A revised achievable outputs and outcomes profile was submitted as part of the recent performance report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UKSPF Approved ProjectsAppendix 1 | 4 pages | Download |
PDF |
UK Shared Prosperity Fund UpdateReport | 4 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.