EXECUTIVE COMMITTEE 18 June 2024
UK Shared Prosperity and Rural England Prosperity Fund Updates Relevant wards: All wards
Portfolio holder: Cllr Julie Wood, Portfolio holder for Strategic Planning, Economic Development and Tourism Head of Service: Ian Edwards, Director of Economy and Environment
Contact officer: Simon Smith, Head of Economic Development If you have any questions about this report, please contact the portfolio holder or the contact officer.
1. Purpose and summary 1.1 To update on the progress of the delivery of the UK Shared Prosperity Fund (UKSPF) Programme.
1.2To update on the progress of the delivery of the Rural England Prosperity Fund (REPF) Programme.
2. Recommendations 2.1 The Committee note the progress to date.
3. Background 3.1 The UKSPF was announced in late Spring 2022 and is a central pillar of the UK Government’s Levelling Up agenda. It supports local investments across the themes of;
i) Community and Place;
ii) Supporting Local Business; and iii) People and Skills.
3.2Malvern’s Investment Plan was submitted August 2022 and formally approved in January 2023. Delivery is eligible from April 2022 to March 2025.
3.3The REPF was announced in September 2022 and supports the aims of the government’s Levelling Up White Paper and Future Farming Programme. It funds capital projects for small businesses and community infrastructure in rural areas.
3.4Malvern’s Investment Plan addendum for REPF was submitted November 2022 and formally approved in April 2023. Delivery is eligible from April 2023 to March 2025.
3.5Overall programme budget:
i) UKSPF budget: £2,420,526
ii) REPF budget: £500,624
iii) Total budget: £2,938,926
3.6An end of year report for April 2023 – March 2024 was successfully submitted to DLUHC at the beginning of May 2024.
3.7A total spend of £800,422 UKSPF was reported for 2023/24 against a profiled target for the year of £803,706. The underspend will be carried forward into 2024/25.
3.8A total spend of £21,753 REPF was reported for 2023/24 against a profiled target for the year of £125,000. The underspend will be carried forward into 2024/25.
3.9The REPF funding is being delivered as a funding opportunity for rural businesses (the Malvern Hills Rural Fund), which opened in July 2023. To date 73 Expressions of Interest have been submitted with 34 projects going through to Full Application. 15 projects worth a total of £743,357 have been approved; £287,086 of which is REPF funding and the rest is made up of private match funding.
3.10All UKSPF and REPF funding (£2,938,926) is now allocated to projects through the approved governance process including discussions at the appropriate Panel followed by final approval at Executive Committee.
3.11The table at Appendix A details the live and completed UKSPF and REPF projects to date. 4. Implications and impact 4.1 What are the financial/resource implications? 4.2 A management and administration budget is built into the UKSPF Programme. A UKSPF team has been appointed to manage and administer the funding.
4.3What are the risks? 4.4 An underspend could occur in 2024/45. All funding is now allocated to projects which decreases the risk of underspend and Malvern Hills’ programme is currently on track, reporting nearly 100% spend in 2023/24. The projects at higher risk of underspend are being monitored and managed closely to ensure that all funding will be spend by end of March 2025.
4.5The targeted outputs and outcomes will not be delivered. A revised achievable outputs and outcomes profile was submitted as part of a previous performance report and the figures achieved to date demonstrate that the programme is on target to deliver. Outputs and outcomes will continue to be monitored closely to ensure delivery.
4.6There is a risk that monies will not be used effectively or misused by delivery partners. This will be mitigated by the Council’s procurement strategy, which is governed by the Council’s Contract Procurement Rules, requiring compliance with public sector procurement requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UKSPF and Malvern Hills Rural Fund Approved ProjectsAppendix A | 4 pages | Download |
PDF |
UK Shared Prosperity Fund (UKSPF) and Rural England Prosperity Fund (REPF) Programmes UpdateReport | 4 pages | DownloadRead as text |
Follow Executive Committee at Malvern Hills and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Confirmation of MinutesRESOLVED that the minutes of the meeting of the Executive Committee, held on 16 June 2026, be confirmed as a correct ... | Decided | Open |
| 15 Sep 2026 | Revenue and Capital MonitoringRESOLVED that i ) the report be noted; ii) £500,000 is transferred to the priorities earmarked reserve from the proje... | Noted | Open |
| 15 Sep 2026 | Quarterly Performance Report 2026/27 - Quarter 1RESOLVED that i ) the achievements and improvements in performance be noted; ii) the strategic issues raised in secti... | Noted | Open |
| 15 Sep 2026 | Maximising the Delivery of Affordable HousingIt was agreed that members’ concerns regarding tenure, accessibility, local connection and allocation information wou... | Agreed | Open |
| 15 Sep 2026 | Street Naming and Numbering PolicyRESOLVED that the revised ‘Street Naming and Numbering Policy’, as presented in Appendix 1, be adopted. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.