M/24/01660/FUL - Land At (Os 6325 6956), Knighton On Teme
ApprovedPlanning2 papers
AI summaryMalvern Hills planners approve 60MW battery storage scheme near Knighton on Teme, subject to Historic England and legal sign-off, despite heritage officer's refusal call.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to Historic England, legal agreement and conditions
MoneyBNG monitoring fee via legal agreementNo figure quoted in the papers
What happens nextLegal agreement and advertisement periodNo objection from Historic England by February 2026
Who it affectsKnighton on Teme parish, Lindridge ward5.5ha open countryside site near Grade I church
What was decided
The committee resolved to grant full planning permission for a 60MW Battery Energy Storage System on 5.5ha of open countryside, delegating the final decision to the Director of Planning and Infrastructure. Report P9, P12
Approval is conditional on no objection from Historic England by February 2026, expiry of the press and site notice advertisement period, completion of a legal agreement for Biodiversity Net Gain monitoring, and the conditions in the report (with a small change to construction vehicle movement hours from 0900 to 0915).
The committee accepted the officer recommendation to approve despite the council's Historic Conservation officer recommending refusal on heritage grounds. Report P66, P82, P9
Why
Officers treated the scheme as a low carbon energy project under SWDP 27, giving significant weight to its role in storing renewable energy and supporting national net zero targets. Report P172, P175, P178
The landscape, ecology, highway and drainage consultees raised concerns, but conditions and a Construction Traffic Management Plan were judged sufficient to make the development acceptable. Report P38, P39, P58, P100, P113
Natural England and the council's ecologist confirmed no adverse effect on the River Clun SAC or River Teme SSSI, with BNG of 19.03% in area habitats and 16.43% in hedgerows proposed on site. Report P41, P49, P54
What happens next
Officers will consider any Historic England response and minor amendments in consultation with the NAPC chairman, and complete the legal agreement before issuing the decision notice.
Conditions require a Construction Traffic Management Plan, Biodiversity Gain Plan, archaeological investigation, landscape and ecology mitigation, a post-completion noise test and a decommissioning scheme after the 40 year operational life. Report P47, P53, P86, P109, P113, P115
The applicant must keep public rights of way KT-657 and KT-663 open during construction where possible, applying for temporary closure at least 8 weeks in advance if needed. Report P130, P131
The money
301 HGV trips over the 12-month construction period Total forecast HGV movements during construction Report P105
no more than 7 HGV trips generated a week (14 two-way movements) Maximum weekly HGV cap Report P105
an average of 2 two-way HGV trips per day Average daily HGV movement rate Report P105
0.13ha Increase in post-developed impermeable area Report P40
157.14m3 Preliminary storage capacity in crushed stone pore spaces Report P40
19.03% in area habitats and 16.43% in hedgerow habitats Proposed on site Biodiversity Net Gain Report P54
Chosen: Approve with conditions and legal agreement (officer recommendation). Scheme seen as low carbon energy project with benefits for net zero and limited harm once mitigated Report P9, P178
Rejected: Refuse on heritage grounds (MHDC Historic Conservation recommendation). Committee accepted officer planning balance giving weight to renewable energy benefits over less than substantial harm Report P66, P82
Rejected: Relocate compound 15m further from the northern boundary (Knighton on Teme Parish Council request). Not adopted as a change at committee; minor amendments left to officers Report P37
Implications
Equalities: Approval allows industrial use of open countryside within sight of heritage assets that residents value for its rural character, against 86 objections and 10 letters of support. Report P136, P138, P143
Legal: A section 106 legal agreement is required to secure the Biodiversity Net Gain monitoring fee and long term habitat management. Report P56
Legal: Sections 16 and 66 of the Planning (Listed Building and Conservation Areas) Act 1990 apply because the site is in the setting of a Grade I listed church. Report P20, P10
Risk: Fire and Rescue Service flags high water demand and vapour cloud risks for lithium ion BESS fires, with the developer offering 5m unit spacing instead of the NFCC's preferred 6m, justified by engineered fire suppression. Report P121, P125, P127, P155, P158
Risk: Construction phase requires a full Construction Traffic Management Plan, banksmen, temporary traffic signals on the A456 and verge widening on the constrained C2095 lane. Report P108, P113
Environment and climate: Scheme is treated as a low carbon project supporting national net zero targets by storing surplus renewable energy for the grid. Report P175, P178
Environment and climate: Natural England confirmed no adverse effect on the River Clun SAC and River Teme SSSI subject to mitigation; site is in flood zone 1 with surface water drained via soakaways. Report P38, P49
Other: The development is temporary, with decommissioning and return to agricultural land required after 40 years, balanced against 30 year Biodiversity Net Gain retention duties. Report P47, P48
Who and where
Knighton on Teme Parish Council, in favour subject to changes to siting, colour, screening, sound testing and lighting Report P35, P37
MHDC Trees and Landscape Officer, objecting to hedgerow loss and industrial use of farmland Report P57, P58, P60
Ramblers Association (Worcestershire) and CPRE Worcestershire, objecting on public rights of way and landscape grounds Report P132, P133
Hereford and Worcester Fire and Rescue Service, setting out access, spacing, water and signage expectations Report P117, P120, P121, P123, P124
86 objectors and 10 supporters who wrote to the council Report P136, P138
Residents near Hucklebatch Farm, Hillside Farm, the local Church and Wyrebrook named in parish sound testing request Report P37
Timeline
5 March 2025: Original application expiry date Report P7
28 May 2025: Worcestershire Lead Local Flood Authority confirms no objection to the flood risk assessment design Report P39
23 July 2025: MHDC adopts the Shadow Habitats Regulations Assessment as the final HRA Report P50
29 July 2025: Natural England raises no objection to the application subject to mitigation Report P50
3 September 2025: MHDC Ecology sets out revised BNG, bat and protected species information Report P43
5 December 2025: County Highways recommends approval with conditions Report P87
14 January 2026: Northern Area Planning Committee resolves to approve subject to conditions and legal agreement Report P1
20 January 2026: Agreed extension of time expiry for the application Report P7
February 2026: Deadline for Historic England to raise no objection before delegation takes effect
Plain English for the jargon
BESS: Battery Energy Storage System, a facility that stores electricity and releases it to the grid to balance supply and demand.
BNG: Biodiversity Net Gain, a statutory requirement for developments to leave habitats in a measurably better state than before, monitored for at least 30 years.
SWDP: South Worcestershire Development Plan, the local plan covering Malvern Hills, Worcester City and Wychavon.
SAC: Special Area of Conservation, a European protected site whose integrity must be protected through Habitats Regulations Assessment.
NDHA: Non-designated heritage asset, a building or site of local heritage interest that is not statutorily listed but is a material planning consideration.
CTMP: Construction Traffic Management Plan, a document setting out how construction vehicles will move to and from a site safely.
PRoW: Public Right of Way, a legally protected path such as a footpath that the public may use.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item140
Resolved
RESOLVED that the decision to APPROVE the application and Grant Full Planning Permission be delegated to the Director of Planning and Infrastructure, subject to the following: a) No objection being received from Historic England by 4 th February 2026. b) Officer consideration of any minor amendments to the proposal in Consultation with the Chairman of NAPC arising as a consequence of representations from Historic England. c) The expiry of the requisite advertisement period (by Site notice and press) on the basis that the proposal affects the setting of a Grade I listed building. d) The satisfactory completion of a Legal Agreement to secure: i ) a monitoring fee related to Biodiversity Net Gain (BNG) to fulfil the statutory duty to monitor and report on BNG delivery. e) The imposition of conditions set out in the report, following a review of their final wording and order by your officers [including an amendment of the timings of construction vehicle movements to and from the site are precluded to change 0900 to 0915 in condition 13(g)]. f) The consideration of any further representations received between the resolution of committee to grant full planning permission and the issuing of the decision notice by your officers. 2. In the absence of the satisfactory completion ... view the full minutes text for item 140.
Word for word from the decision Malvern Hills published for this meeting.Source: moderngov.malvernhills.gov.uk
Site Address Land At (Os 6325 6956), Knighton On Teme
Description of Development Proposed Battery Energy Storage System (BESS) and associated infrastructure
Case Officer Lee Walton Applicant INTEGRUM SPV 22298 LIMITED
Parish Knighton on Teme CP Agent [name removed] Member(s) Cllr Douglas Godwin
Reason for Referral Major application Expiry Date 5 March 2025 to Committee EoT 20 January 2026
Key Issues - Principle of development - Landscape character and visual impact - Neighbour Amenity and Noise Nuisance - Heritage Assets and their Setting - Highway Safety - Drainage and Flooding - Biodiversity - Climate Emergency - Planning obligation - Other Issues - Heritage Balance - Overall Planning balance
Recommendation Approval 1. SITE DESCRIPTION AND DETAILS OF PROPOSAL
The application site is located in the open countryside within land that slopes towards the south where the land drops beyond the site’s northern and eastern boundaries. The site is approximately 5.5ha in area. The grade I listed Church of St Michael is located approximately 260m north of the site, alongside which is a grade II listed Church Farmhouse and the grade II listed remains of the Churchyard Cross approximately 255m distant.
A public right of way footpath (KT-657 C) runs partly along the northern boundary of the site and enters the site aligned with the church. There are other footpath within the immediate area. To the north and the east these are located within lower ground.
The proposal seeks provision of a 60MW Battery Energy Storage System (BESS) and associated infrastructure to provide energy balancing services to the national grid.
Two access points are proposed. The compound surface would comprise primarily of permeable gravel surface, with the above equipment sitting on raised reinforced concrete foundations. Internal access tracks within the compound will comprise of crushed stone. The compound would be surrounded by a fence. An underground cable would connect the proposed substation to the point of connection, an existing electricity pylon to the northwest of the BESS compound.
The following equipment would be found within a fenced compound:
• 64 no. BESS Battery Unit, maximum height of 2.8m • 8 no. Transformers, maximum height of 2.9m • 1 no. 132kv Substation Area with Transformer, maximum height of 6.77m • 1 no. Project Control Room, maximum height of 2.75m • 1 no. Spare Parts Container, maximum height of 2.75m • 1 no. DNO Control Room, maximum height of 2.75m • 1 no. water tank, maximum height of 2.2m • Perimeter fence, maximum height of 2.4m
The submission is supported among others by the following:
• Planning Statement, including Design and Access Statement • Statement of Community Involvement • Arboricultural Implications Assessment • Arboricultural Method Statement • Agricultural Land Classification Report • Flood Risk Assessment • Historic Environment Desk-Based Assessment • Archaeological Evaluation • Preliminary Ecological Appraisal • Biodiversity Net Gain Assessment • Statutory Biodiversity Metric • Noise Impact Assessment • Transport Statement • Construction Traffic Management Plan • Geophysical Survey Report • Landscape and Visual Impact Appraisal • Temporary Traffic Management Method Statement • Bat Impact Assessment • Biodiversity Net Gain assessment • Preliminary Ecological Appraisal • Heritage rebuttal statement 2. PLANNING POLICY AND LEGISLATIVE FRAMEWORK
2.1The Development Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.