Resolved

Decision The Committee notes:- (1) the progress that has been made to date; (2) the delegations agreed at the Executive meeting of 21 March 2018 (3) the remaining actions required to enable contract closure and construction and operation to commence as agreed and delegated at the Executive of 21 March 2018; and (4) that the actions are targeted for completion in November with the aim of entering into contract with Vital Energi in December.
Word for word from the decision Manchester published for this meeting. Source: democracy.manchester.gov.uk

Follow this further

Built from Manchester's papers

What the report saysPro

Report to Resources and Governance Scrutiny Committee

Summary

The purpose of this report is to provide an update on the progress of the Manchester Civic Quarter Heat Network project (the “CQHN”) and the actions required to enable contract closure and commencement of the construction phase.

The Council’s Climate Change Action Plan and the Climate Change Strategy documents include the intention to develop and deliver a heat network in the Civic Quarter as a key project to contribute to the decarbonisation of energy provision in the Civic Quarter.

The Civic Quarter Heat Network Project comprises the creation of a new and architecturally acclaimed low carbon energy centre at the Manchester Central Convention Complex. The energy centre will supply low carbon heat and electricity to Council owned buildings – the Town Hall, the Town Hall Extension and Library, Manchester Central Convention Centre, Manchester Art Gallery, the Bridgewater Hall and Heron House. Refer to Appendix 1 for further information

The project has been designed to allow for expansion to supply low carbon energy to other commercial buildings/developments in the Civic Quarter. Subject to contract the project will be designed, built, operated and maintained on behalf of the Council by Vital Energi of Blackburn (Vital). Vital were selected via an OJEU compliant procurement process and will be subject to a performance related contract for both construction and operational phases.

On the 21 March 2018 the Executive:

1 Approved the establishment of a Special Purpose Vehicle (SPV), wholly owned by the Council, to promote the delivery of the Project as described in the report to Executive of the same date

2 Delegated authority to the Strategic Director Development, the City Treasurer and the City Solicitor, in consultation with the Leader, Executive Member for the Environment and the Executive Member for Finance and Human Resources, to approve the Business Plan and corporate documentation to establish the SPV and to negotiate and finalise the terms of the contractual and property arrangements as set out in the Executive report of 21 March 2018 3 Delegated authority to the City Solicitor to enter into and complete all documents or agreements necessary to give effect to the recommendations of the report to Executive of 21 March 2018

Recommendations

The Committee is recommended to:-

1. Note the progress that has been made;

2. Note the delegations agreed at the Executive meeting of 21 March 2018;

3. Note the remaining actions required to enable contract closure and construction and operation to commence as agreed and delegated at the Executive of 21st March 2018 viz:-

a. Complete the Business Plan (the Capital Approval Process Business Case) b. Finalise the Project Agreement with Vital Energi c. Finalise the lease agreement facilitating the construction of the Energy Centre d. Finalise the agreement for the power connection

4. Note that the actions above are targeted for completion in November with the aim of entering into contract with Vital Energi in December.

Wards Affected: Deansgate

Alignment to the Our Manchester Strategy Outcomes (if applicable)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Network Route and the Energy CentreAppendix 1 424 KB Download
PDF
Civic Quarter Heat Network: updateReport 252 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 18 attended
SR
Councillor Sarah RussellChair, present
AA
Councillor Ahmed AliCommittee Member, present
PA
Councillor Paul AndrewsCommittee Member, present
HB
Councillor Hugh BarrettCommittee Member, present
BC
Councillor Ben ClayCommittee Member, present
JD
Councillor Joan DaviesCommittee Member, present
SL
Councillor Shelley LanchburyCommittee Member, present
RK
Councillor Richard KilpatrickCommittee Member, present
RM
Councillor Rebecca MooreCommittee Member, present
BP
Councillor Bernard PriestCommittee Member, present
ER
Councillor Emily RowlesCommittee Member, apologies
AS
Councillor Andrew SimcockCommittee Member, present

All 18 on the meeting page

More from Manchester Resources and Governance Scrutiny Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 MinutesTo approve the minutes of the Resources and Governance Scrutiny Committee meeting held on 23 July 2026. Approved Open
10 Sep 2026 Housing Repairs Insourcing and Recommissioning (Part A)To note the report. Noted Open
10 Sep 2026 Overview ReportTo note the report and agree the work programme. Noted Open
10 Sep 2026 Exclusion of Press and PublicTo exclude the press and public during consideration of the following item which involved consideration of exempt inf... Decided Open
23 Jul 2026 MinutesTo approve the minutes of the Resources and Governance Scrutiny Committee meeting held on 2 July 2026. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies