Housing Repairs Insourcing and Recommissioning (Part A)

Noted Scrutiny 1 paper

AI summaryManchester scrutiny committee notes proposals to end the Equans housing repairs contract and bring the service in-house from 1 April 2027, with a forecasted £4.8m annual cost reduction over five years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedResources and Governance Scrutiny Committee, 10 September 2026
Money£4.8m annual saving forecastedOver first five years of in-house operation
What happens nextExecutive to consider approvalDetailed financial case set out in Part B of report
Who it affectsCouncil housing tenants city-wideRepair, maintenance and compliance services

What was decided

The committee noted the report setting out a combined insourcing and recommissioning model for housing repairs and maintenance to take effect from 1 April 2027. Report P4, P6

Officers are recommended to proceed with developing the Internal Property Service to deliver the principal repairs work directly, while specialist functions would be re-tendered. Report 1.3, 1.4, 2.5, P48, P49, P50, P51, P52

The HRA is running at an annual deficit of £22.758m and the business plan forecasts responsive repairs costs falling from £13.1m in 2027/28 to £8.3m by year five. Report P16

Why

The Equans contract for repairs, maintenance and compliance to directly managed council housing expires on 31 March 2027 with no further extension options. Report P1, 1.1, 2.1

Officers found the current contract cost unsustainable, responsive repair volumes 16% higher than in 2021/22 and a higher share classified as emergency or same-day than comparable social landlords. Report 2.14, 2.16

Insourcing is judged to give the council greater control over prioritisation, productivity, workforce development and compliance with landlord duties under the Social Housing (Regulation) Act and Consumer Standards. Report 2.22, P63

What happens next

Heads of Terms for a new depot lease to be agreed, with signing intended in October 2026 subject to Executive approval. Report 2.11

Officers to finalise scope of in-house and externally commissioned services, undertake workforce transition, procure a new ICT system, lease vehicles and commission specialist managed services. Report 1.4, 2.12, 3.1, 3.6, 3.7

An Equality Impact Assessment is to inform the project plan before implementation. Report P8

The money

  • £22.758m Current annual HRA operating deficit Report P16
  • £4.8m Forecast reduction in annual operating costs over first five years under proposed model Report P16
  • £13.1m Forecast responsive repairs cost in 2027/28 under proposed model Report P16
  • £8.3m Forecast responsive repairs cost by Year 5 under proposed model Report P16

Options considered

  • Rejected: Re-tender with Equans or an alternative external contractor for the whole service. Would not give the council sufficient control over prioritisation, resources or productivity improvements Report P40
  • Rejected: Full insourcing of all repair and maintenance activity. Intermittent specialist work such as scaffolding, and functions requiring specialist accreditation such as fire safety, are better delivered by external contractors Report P41
  • Chosen: Hybrid model: in-house principal service plus re-commissioned specialist functions. Provides greater council control over the main service while retaining access to specialist expertise and value for money Report P42, P43, P44

Implications

  • Financial: In-sourced model is part of the HRA Sustainability Plan but is not expected on its own to resolve the £22.758m deficit. Report P16, P17, 2.24
  • Financial: Mobilisation requires capital investment in ICT, depot facilities and operational infrastructure, and possible future capital for building, fire and compliance works; additional borrowing could increase capital financing and interest costs. Report P19, P20
  • Financial: Long-term leases meeting recognition criteria will appear on the HRA balance sheet as right-of-use assets and lease liabilities, with ongoing depreciation and financing charges. Report P21
  • Legal: Legal Services will advise on workforce transfer, depot leasing, procurement, contractual transition and information governance to meet statutory and regulatory duties. Report 3.3, 3.8
  • Equalities: An Equality Impact Assessment will be carried out on tenants, employees and other affected groups to meet the Public Sector Equality Duty and respond to a diverse tenant base. Report P8
  • Risk: Officers are engaging Equans on contingency arrangements to maintain service continuity during transition. Report 1.1
  • Staffing: A reduction in responsive repair volumes and improved productivity are expected to reduce reliance on agency staff and subcontractors over time. Report P16

Who and where

  • Tenants of directly managed council homes across affected wards Report P7, 1.1, 2.7
  • Council housing staff and Equans employees potentially subject to workforce transfer Report 1.4, 3.3
  • Specialist contractors in fire safety, lifts, drainage, asbestos, structural and other regulated works Report P50, P51, P52
  • Manchester Housing Revenue Account Report P16, 2.24

Timeline

  • February 2026: Executive gave in-principle approval to develop the combined model Report P1, 1.2, 2.3
  • October 2026 (intended): Depot Heads of Terms to be signed, subject to Executive approval Report 2.11
  • 31 March 2027: Equans contract expires with no further extension options Report P1, 1.1, 2.1
  • 1 April 2027: Target commencement date for the new in-house and re-commissioned delivery model Report P2, 1.4, 3.1

Plain English for the jargon

  • Equans: Current external contractor providing repairs, maintenance and compliance services to directly managed council housing
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and expenditure
  • Internal Property Service: Proposed in-house council team to deliver the principal operational elements of the repairs and maintenance service
  • Ark Consultancy: External consultancy engaged to develop the business plan for the proposed delivery model
  • Major Contracts Board: Council body which in December 2023 considered proposals to in-source the high-volume components of the repairs service
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47

Resolved

To note the report.
Word for word from the decision Manchester published for this meeting. Source: democracy.manchester.gov.uk

Follow this further

Built from Manchester's papers

What the report saysPro

Report to Resources and Governance Scrutiny Committee

Summary

The Council’s contract with Equans for repairs, maintenance and compliance services to directly managed council housing expires on 31 March 2027. In February 2026, Executive gave in-principle approval to develop a combined model under which the principal operational elements of the service would be brought into direct Council management, with specialist functions recommissioned through externally procured arrangements.

This report sets out the proposed model, supporting business plan, mobilisation arrangements, financial implications and key risks, and seeks approval to proceed with the insourcing of the principal operational elements of the service and the recommissioning of specialist managed services from 1 April 2027.

Recommendations

The Committee is recommended to:

1. Note and comment on the contents of the report.

Executive is recommended to:

1. Note the proposal for the Council to establish a combined insourcing and recommissioning model for delivery of the housing repairs and maintenance service, further details of which are set out in Part B.

Wards Affected: Ancoats and Beswick; Ardwick; Charlestown; Cheetham; Clayton and Openshaw; Gorton and Abbey Hey; Harpurhey; Higher Blackley; Miles Platting and Newton Heath; Moston; Piccadilly;

Environmental Impact The retrofitting of existing council properties to Assessment - the impact of the meet zero carbon objectives is a key part of the issues addressed in this report on council housing capital programme and this is part achieving the zero-carbon target of the wider programme on maintaining and for the city improving council housing. Equality, Diversity and The tenant composition of council housing is Inclusion - the impact of the increasingly diverse and the council housing issues addressed in this report in repair and maintenance service needs to reflect meeting our Public Sector and respond to the diversity of Equality Duty and broader tenants. Responding to the diversity of tenants is equality commitments a key part of the Consumer Standards. The decision on the future management of the repair and maintenance service could impact on vulnerable and disadvantaged tenants and the project plan will be informed by an Equality Impact Assessment. The assessment will consider the impact of the of proposals on tenants, employees and other affected groups to ensure the Council meets its Public Sector Equality Duty. Children and Young People – It is vital that council housing the impact of the issues is managed, repaired and maintained to a high addressed in this report on standard so that children who live in council children and young people housing have a decent home to live which will be a platform for them to thrive in everything they do.

Our Manchester Strategy Summary of how the contents of the report Outcomes supports the delivery of the Our Manchester Strategy Our People: Our People is about Council housing repaired and maintained to a high everyone who calls Manchester standard will create a platform for all council home, making sure they can live tenants to thrive in everything they do. their best lives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Repairs Insourcing and Recommissioning (Part A)Report 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
SW
Councillor Sam WheelerChair, present
AS
Councillor Amna Saad Omar AbdullatifCommittee Member, present
SE
Councillor Sam Easterby-SmithCommittee Member, present
GE
Councillor Glynn EvansCommittee Member, present
DG
Councillor David GodfreyCommittee Member, present
NH
Councillor Naeem HassanCommittee Member, present
RK
Councillor Richard KilpatrickCommittee Member, present
TL
Councillor Tom LaneCommittee Member, present
JL
Councillor Jon-Connor LyonsCommittee Member, apologies
MR
Councillor Munaver RasulCommittee Member, apologies
FR
Councillor Fesl Reza-KhanCommittee Member, apologies
SR
Councillor Suzanne RichardsCommittee Member, present

All 16 on the meeting page

On this subject at Manchester

Search all
  1. Housing Repairs Insourcing and Recommissioning (Part A)This decision
  2. Housing Repairs Insourcing and Recommissioning (Part A)Agreed
  3. Re-establishment of the Housing Repairs and Maintenance Service Scrutiny SubgroupDeferred
  4. Establishment of the Housing Repairs and Maintenance Contract Scrutiny SubgroupApproved
  5. Call In - Extension of Repairs and Maintenance contract for MCC Housing ServicesDecided

More from Manchester Resources and Governance Scrutiny Committee

All decisions
MeetingDecisionOutcome
10 Sep 2026 MinutesTo approve the minutes of the Resources and Governance Scrutiny Committee meeting held on 23 July 2026. Approved Open
10 Sep 2026 Overview ReportTo note the report and agree the work programme. Noted Open
10 Sep 2026 Exclusion of Press and PublicTo exclude the press and public during consideration of the following item which involved consideration of exempt inf... Decided Open
23 Jul 2026 MinutesTo approve the minutes of the Resources and Governance Scrutiny Committee meeting held on 2 July 2026. Approved Open