AI summaryManchester scrutiny committee backs hybrid housing repairs model from April 2027, with about 75% of work brought in-house at a mobilisation cost of c.£3.3m.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedIn-sourcing and re-commissioning from 1 April 2027
Moneyc.£3.3m mobilisation costFunded from HRA reserves, to be replenished
What happens nextExecutive Board decision in February 2026Committee to set progress report frequency
Who it affectsCouncil housing tenants in 11 wardsIncludes Equans staff under TUPE transfer
What was decided
The committee agreed that the delivery model assessment could be provided to members, and the Executive Member for Housing and Development said residents would be communicated with in advance of the change.
The committee was asked to consider and comment on the proposed decision to establish a hybrid repair and maintenance service for council housing from 1 April 2027, and to decide the regularity of progress reports over the next 15 months. Report P8, P86, P87
Why
The current Equans contract expires at the end of March 2027 and contains no provision to extend, so a new delivery model is needed. Report P1, 2.1
The HRA revenue budget is under significant pressure, with a forecast drawdown of £13.0m against a £5.9m plan, driven by overspends on responsive repairs, disrepair claims and fire safety works. Report P19, P20, 3.1, 3.2
Bringing the principal functions in-house is expected to give the Council more direct control over work scheduling, quality and cost, and to retain a typical private-sector 10-11% profit margin within the HRA. Report P3, P21, 3.5, P49
What happens next
Seek Executive Board approval in February 2026 to establish the hybrid model and a Direct Labour Organisation within Housing Services. Report 4.1, 4.8
Appoint a project management organisation in February 2026 (21 hours a week for around 20 months) and award the ICT system contract by 1 April 2026 so a 12-month build can complete before go-live. Report 4.8, 4.11, P72, P76
Run competitive tenders for specialist services such as building, fire, gas and electrical safety, with critical procurements completed before Q4 2026 to Q1 2027, and start the new in-house and re-commissioned services on 1 April 2027. Report P3, 4.2, 4.3, 4.19, P74
The money
c.£3.3m Expected mobilisation cost, to be funded from HRA reserves Report P22, 3.5
£105.8m Original approved 2025/26 HRA revenue budget Report P19, 3.1
£5.9m Originally planned HRA reserves drawdown for 2025/26 Report P19, 3.1
£13.0m Forecast HRA reserves drawdown for 2025/26 Report P19, 3.1
£7.1m Additional reduction in HRA reserves now forecast Report P19, 3.1
£15m Annual repairs budget for 2025/26 Report P20, 3.2
£2.034m Forecast overspend on responsive and planned repairs in 2025/26 Report P20, P41, 3.2
£2.678m Forecast overspend on disrepair claims in 2025/26 Report P20, P41, 3.2
£1.969m Forecast overspend on fire safety works in 2025/26 Report P20, P41, 3.2
10-11% Typical private repair and maintenance service profit margin that could be retained within the HRA Report P21, 3.5, P49
Options considered
Chosen: Hybrid model: in-source principal functions and re-commission specialist functions. Equans contract ends March 2027 with no extension; in-sourcing gives greater control and could retain contractor profit margin within the HRA Report P1, P2, P3, P4, 2.1, 4.1
Rejected: Extend the existing Equans contract. No provision within the current contract to extend it Report P1, 2.1
Rejected: Fully insource the entire service. Specialist functions such as building, fire, gas and electrical safety are considered better placed with external providers Report P3, P46, 4.2
Implications
Financial: Mobilisation cost of c.£3.3m to be funded from HRA reserves, intended to be replenished by future savings; HRA already under pressure with reserves drawdown forecast to rise from £5.9m to £13.0m in 2025/26. Report P19, P22, 3.1, 3.5, 3.6
Financial: Potential capital consequences for depot space, fleet and ICT requirements; if depot land comes from the General Fund, a transfer of indebtedness between HRA and General Fund is expected. Report P24, P25, P26, 4.13
Legal: TUPE will apply to Equans staff carrying out in-sourced functions and may apply to sub-contracted work; transferring staff will join the Local Government Pension Scheme and bidders will be expected to seek admission to the Greater Manchester Pension Fund under the Best Value Authorities Staff Transfers (Pensions) Direction 2007. Report P50, 4.12, P63, P78
Equalities: The repair and maintenance service needs to reflect an increasingly diverse tenant profile; an Equality Impact Assessment will inform the project plan as the decision could impact vulnerable and disadvantaged tenants. Report P11
Staffing: Workforce implications include TUPE mapping, induction, training, and consideration of GMPF membership for staff not previously employed by the Council, which would raise staffing costs but support a positive transfer. Report P50, 4.12, P78
Climate: Retrofitting existing council properties to meet zero carbon objectives is a key part of the wider council housing capital programme that this service supports. Report P10
Risk: Key unknowns include final TUPE arrangements, depot and fleet costs, and the full impact on the 30-year HRA business plan; the ICT contract must be awarded by 1 April 2026 to allow 12 months to initial operating capability. Report 4.11, 4.14, 4.15, P76
Who and where
Tenants of Manchester council housing in Ancoats and Beswick, Charlestown, Cheetham, Crumpsall, Harpurhey, Higher Blackley, Moston, Ardwick, Clayton and Openshaw, Miles Platting and Newton Heath, and Piccadilly wards Report P9
Equans employees whose roles are in-sourced, who will transfer under TUPE Report P50, 4.12
Sub-contracted organisations whose staff may also fall within TUPE scope Report P50
Future specialist contractors to be appointed for building, fire, gas and electrical safety, cyclical investment, structural work, damp and mould, adaptations, roofing, asbestos, legionella and lifts Report P3, 4.2, P53
Manchester City Council Housing Services, which will host the new Direct Labour Organisation Report P2, 4.1
Timeline
February 2026: Appoint a project management organisation via framework and begin 21-hour-a-week support until September 2027 Report 4.8, P72
From February 2026: Bi-monthly progress reports to the Housing Board (Strategic Director Neighbourhoods; Strategic Director Growth and Development; Deputy Chief Executive) Report 4.8, P72
By 1 April 2026: Award the ICT system contract so providers have 12 months to reach initial operating capability Report 4.11, P76
Mid-2026 to Q1 2027: Secure depot sites, complete fit-out and procure the vehicle fleet Report 4.22, P80, P81
Q4 2026 to Q1 2027: Complete critical procurements for specialist services that will remain external Report 4.19, P74
1 April 2027: Start the hybrid in-house and re-commissioned repair and maintenance service, with staff TUPE transfer on Day 1 Report P2, 4.1, 4.21, P78
April to September 2027: Embedding, transition assurance, induction completion and performance bedding-in Report 4.18, 4.21, P72, P78
Plain English for the jargon
DLO: Direct Labour Organisation, a council-operated team that carries out work directly rather than via a contractor
HRA: Housing Revenue Account, the ring-fenced account that funds council housing services from rents and other income
TUPE: Transfer of Undertaking (Protection of Employment), regulations that move staff employment to a new employer on existing terms when work transfers
GMPF: Greater Manchester Pension Fund
LGPS: Local Government Pension Scheme
CMT: Corporate Management Team
RAGOS: Resources and Governance Scrutiny Committee, the committee considering this report
DLO mobilisation: The setup costs to establish the in-house team, estimated at c.£3.3m
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item2
Resolved
It was agreed that the delivery model assessment could be provided to members. The Executive Member for Housing and Development stated that there would be communication with residents in advance of the change. He also expressed hope that the proposal would enable repairs to be undertaken in ... view the full minutes text for item 2.
Word for word from the decision Manchester published for this meeting.Source: democracy.manchester.gov.uk
Report to Resources and Governance Scrutiny Committee
Summary
The repair and maintenance service for council housing is delivered by Equans with the contract expiring at the end of March 2027. There is no provision within the current contract to further extend the contract with Equans.
Prior to retendering for contracts, the Council undertakes a delivery model assessment review to assess whether the commissioned service is best undertaken in house or retendered. This review pointed to the opportunity to bring specific repair and maintenance functions (responsive repairs, disrepair, voids, heating, ground maintenance) into the direct management of the Council’s Housing Service from 1 April 2027.
Some specialist services would require separate to re - commissioning (covering building safety, fire safety, gas safety, electrical safety) through a competitive tendering process. The hybrid approach will result in the principal part of the service, in respect of work volume and cost, being brought into the management of the Council. This will give the Council the ability to greater control of work scheduling, targeting and cost. It will also mean that the Council is more accountable for the timeliness and quality of work.
The establishment of a Direct Labour Organisation (DLO) within Housing Services is a significant change to service delivery and taking a hybrid approach is believed to be the best current approach giving the Council control over the principal part of the service whilst more specialist works are carried out by other companies. The functions to be insourced comprise around 75% of the total works and cost of the repairs and maintenance service. The contracts will be framed so that there is scope for further insourcing at a later point.
The Council is procuring a company to commissioning some project management capacity to facilitate the insourcing work. This work will be overseen and complemented by Housing Services senior management team. The competitive tendering, of the functions that will continue to be re-commissioned, will be carried out by Housing Services, the Homeless Service Commissioning Team and the Corporate Integrated Commissioning and Procurement Service.
A project plan, covering key workstreams such as ICT, Finance, HR, Estate Services and Fleet Services, has been developed and work has started on all these work streams. Progress on the insourcing/re-commissioning will be reported to the bi- monthly Housing Board.
Recommendations
The Committee is recommended to:
• Consider and comment on the proposed decision to establish a hybrid repair and maintenance service for council housing services from 1 April 2027. • Decide on the regularity of progress reports to be presented to RAGOS over the next 15 months.
Environmental Impact The retrofitting of existing council properties to Assessment - the impact of the meet zero carbon objectives is a key part of the issues addressed in this report on council housing capital programme and this is achieving the zero-carbon target part of the wider programme on maintaining and for the city improving council housing.
Equality, Diversity and The tenant composition of council housing is Inclusion - the impact of the increasingly diverse and the council housing issues addressed in this report in repair and maintenance service needs to reflect meeting our Public Sector and respond to the diversity of tenants. The Equality Duty and broader decision on the future management of the repair equality commitments and maintenance service could impact on vulnerable and disadvantaged tenants and the project plan will be informed by an Equality Impact Assessment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Resources and Governance Scrutiny Committee at Manchester and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.