CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Manchester City Council
Executive, Wednesday 10 June 2026 at 2.00pm

Update on investment in District Centres and Localities

Noted Executive 1 paper

AI summaryManchester Executive notes update on District Centres and Localities investment, with delivery continuing in Gorton, Moston, Newton Heath and Wythenshawe Civic, and new frameworks planned for Harpurhey, Cheetham Hill and Longsight.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExecutive noted the update report
MoneyMultiple funding streams citedUp to £20m per Pride in Place area
What happens nextNew frameworks in 2026/27Harpurhey, Cheetham Hill, Longsight, Burnage, Northenden
Who it affectsAll wardsDistrict centres, local centres, high streets citywide

What was decided

The Executive noted the contents of the report on investment in district centres, local centres and high streets. Report P6

Why

The Council has developed an explicit District Centres and Localities Programme to focus development and regeneration activity across the city, aligned with the refreshed Our Manchester Strategy. Report 1.2, 1.3, P34

The report updates members on progress at Moston Lane, Gorton, Newton Heath and Wythenshawe Civic, and sets out a wider programme for 2026/27 onwards. Report P2, P3, 3.1

What happens next

Continued delivery in Gorton, Moston Lane and Newton Heath, and construction at Wythenshawe Civic under the joint venture with Muse. Report P2, 2.13, 2.14, 2.15

Drafting of development and investment frameworks for Harpurhey, Cheetham Hill and Longsight, with exploration of opportunities in Burnage and Northenden. Report P3, 3.2, 3.3, 3.4, 3.10

Aligning the programme with the work of five Pride in Place neighbourhood boards and progressing a shopfront improvement programme and new footfall monitoring system. Report P4, 3.11, 3.12, 3.13, 3.15, 3.16

The money

  • up to £20m Pride in Place funding per area over 10 years Report 3.11
  • £20m Levelling Up (now Local Regeneration) Fund for Wythenshawe public realm Report 2.12
  • £26m GMCA Good Growth Fund for 100% social rent housing at Wythenshawe Report 2.14
  • £6.4m Additional NIRF for 27/28-28/29 (£100k per annum for 32 wards) Report 3.14
  • £30,000 Per ward Your Neighbourhood Fund grant Report 3.14
  • 145 new homes (36% affordable) Indicative Moston Lane scheme by Aviva/Place Capital Group Report 2.1
  • around 70 Affordable homes on former Gorton Library site by Clarion
  • 35 Affordable independent living homes for care leavers, Chapman Street Report 2.8

Options considered

  • Chosen: Note the report. Report is an update; no specific decision sought Report P6
  • Rejected: Explore a future shopfront improvement programme. Detailed proposals to be submitted to Executive for approval in due course Report 3.15
  • Rejected: Procure new footfall monitoring system. Review underway to identify and procure a new system Report 3.16

Implications

  • Financial: No direct revenue or capital finance implications for the Council arise from this report; future infrastructure will require capital investment subject to approvals. Report P19, P20, P21
  • Equalities: Many district and local centres contain high levels of deprivation; the programme supports safer, vibrant places with new jobs, homes and opportunities. Report P11, P12
  • Climate: Interventions can contribute to the city's zero carbon target, depending on design, materials, sustainable drainage and active travel options in each location. Report P7, P8, P9, P10
  • Other: Public consultation processes seek to include children and young people's views, with the new Gorton Square cited as an inclusive, age friendly example. Report P13, P14, 2.5
  • Staffing: Recruitment is planned to add staff to a recently established regeneration team focused solely on the district centres and localities programme. Report 3.17

Who and where

  • All wards across Manchester Report P6
  • Residents and businesses in Moston, including a new Regeneration Forum Report 2.1, 2.2, 2.3
  • Gorton residents, with refurbishment of Gorton Market and new housing by Clarion and Centrepoint Report 2.5, 2.6, 2.8
  • Newton Heath residents and businesses, following adoption of the NDF in March 2026 Report 2.9, 2.10
  • Wythenshawe residents, with 1700+ new homes planned via the joint venture with Muse Report 2.11, 2.12, 2.13, 2.14
  • Manchester care leavers aged 18 to 25, via 35 homes on Chapman Street Report 2.8
  • Communities in five Pride in Place areas: Clayton Vale, Gorton South, Benchill South and Wythenshawe Central, Harpurhey South and Monsall, Moss Side West Report 3.11, 3.12

Timeline

  • 2023: Gorton and Wythenshawe Development Frameworks adopted Report 2.4, 2.11
  • 2025: Moston Superstore planning approval secured; Wythenshawe joint venture with Muse agreed; Gorton Square delivered Report 2.2, 2.5, 2.13
  • January 2026: Previous update report to Executive Report P29
  • March 2026: Newton Heath NDF endorsed by Executive; further funding secured to extend Gorton Square Report 2.5, 2.9
  • summer 2026: Planning determination expected for Chapman Street scheme; 50 social rented homes at former Chorlton Baths to complete Report 2.8, 3.7
  • later this year: Planning application expected for first Clarion phase at Gorton Library site
  • end of this year: Gorton Market refurbishment works to complete Report 2.6
  • 2027: Wythenshawe Civic public realm works programmed to complete Report 2.12

Plain English for the jargon

  • NDF (Neighbourhood Development Framework): A document setting out a coherent approach to development and regeneration for a local area, adopted by Executive.
  • LIF (Local Infrastructure Framework): A study reviewing public realm, travel and health provision to identify investment opportunities in a district centre.
  • Pride in Place: A government programme providing up to £20m per area over 10 years for local priorities, directed by community-chosen neighbourhood boards.
  • NIRF (Neighbourhood Infrastructure Renewal Fund): Council funding for ward-level public realm improvements such as bins, benches and street features.
  • YNF (Your Neighbourhood Fund): Formerly the Neighbourhood Investment Fund; provides grants of £30,000 per ward for grassroots improvements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49

Resolved

Decision The Executive note the report.
Word for word from the decision Manchester published for this meeting. Source: democracy.manchester.gov.uk

Follow this further

Built from Manchester's papers

What the report saysPro

Report to Executive

Summary

This report provides an update on the work being done across the city to invest in, improve and regenerate Manchester’s district centres, local centres and high streets. Significant progress has been made over recent years with delivery of specific targeted interventions across the city designed to drive footfall, local spend, events, civic activities and maximise the economic potential of each community.

Further to the update to Executive in January 2026, project delivery continues apace in Gorton, Moston Lane and Newton Heath, whilst an extensive programme of construction activity is underway at Wythenshawe Civic via the Council’s Joint Venture with Muse.

Looking ahead, 2026/27 will see continued focus on delivery alongside the drafting of development and investment frameworks for Harpurhey, Cheetham Hill and Longsight along with exploring opportunities in Burnage and Northenden.

A key workstream for the year ahead will be aligning opportunities within the district centres and localities programme with the work of the Pride in Place boards that are being established across five areas of the city. These boards will work with communities to shape how up to £20m is spent to improve each of their local areas and implement a range of improvements centred around the needs of residents.

Regeneration and investment in district and local centres continue to be complemented by essential joined up collaboration between Council services, particularly between Neighbourhoods’ operational and management teams, Highways, Work & Skills and the MCC Compliance and Enforcement functions, as well as external partners such as the NHS and GMP. A coordinated and collaborative approach is critical to maximising the impact of resources and ensuring that meaningful and sustainable improvements are delivered across the city.

Recommendations

The Executive is recommended to note the contents of this report. Wards Affected – All

Environmental Impact District centres, local centres and high streets Assessment hold the potential to contribute significantly to – the impact of the issues the city’s zero carbon target, though the addressed in this report on extent and nature of that contribution will achieving the zero-carbon target for depend on the particular interventions being the city delivered in each location.

Where significant new residential development is set to occur, for example, efforts will be made to reduce carbon impacts both during construction and the operational life of the new homes, with a fabric first approach to design and the selection of appropriately sustainable materials and building systems, such as heat pumps and solar PV.

A place-based approach to district centres and localities promotes opportunities to develop new homes close to places of employment, community and leisure facilities, reducing the need to travel and/or enabling greater use of active travel options, such as walking, wheeling and cycling.

Where new or improved public realm is being introduced, sustainable urban drainage can be considered as well as options for biodiversity uplift. Hard and soft landscaping materials can also be selected that have a lower carbon footprint, be that through sourcing locally or through lower lifetime maintenance requirements.

Equality, Diversity and Inclusion Many of the city’s district centres and – the impact of the issues localities contain significant levels of addressed in this report in meeting deprivation, with those residents often facing our Public Sector Equality Duty and additional health inequalities. Creating and broader equality commitments sustaining safe, vibrant places that provide new jobs, homes and opportunities therefore supports the Council’s broader promotion of equality and diversity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on investment in District Centres and LocalitiesReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 20 attended
BC
Councillor Bev CraigChair, present
GB
Councillor Garry BridgesCommittee Member, present
SB
Councillor Shazia ButtCommittee Member, present
TR
Councillor Tracey RawlinsCommittee Member, apologies
JR
Councillor Julie ReidCommittee Member, present
TF
Councillor Thomas Frederick RobinsonCommittee Member, present
BS
Councillor Basat SheikhCommittee Member, present
MS
Councillor Mandie Shilton GodwinCommittee Member, present
AS
Councillor Andrew SimcockCommittee Member, apologies
GW
Councillor Gavin WhiteCommittee Member, present
SA
Councillor Sian AstleyAdvisory Member, present
BC
Councillor Becky ChambersAdvisory Member, present

All 20 on the meeting page

More from Manchester Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Adult Social Care - Unpaid Carers Strategy 2026 – 2029Decision The Executive approve and adopt the Unpaid Carers Strategy 2026-29 Approved Open
16 Sep 2026 Housing Repairs Insourcing and Recommissioning (Part A)Decision The Executive note and agree the proposal for the Council to establish a combined insourcing and recommissio... Agreed Open
10 Jun 2026 Appointment of Executive Members and their PortfoliosDecision The Executive note the appointments of Deputy Leader and Executive Members Noted Open
10 Jun 2026 Delegation of Executive Functions to the Executive and Council OfficersDecision The Executive:- (1) Note the decision of the Leader of the Council to exercise the power under Section 9E(2)... Noted Open
10 Jun 2026 Corporate Priorities 2026/27Decision The Executive adopt the commitments made in the Manchester Labour 2026 manifesto as priorities for the Execu... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies