Housing Repairs Insourcing and Recommissioning (Part A)

Agreed Executive 1 paper

AI summaryManchester Executive notes plan to bring council housing repairs in-house from 1 April 2027, with specialist functions recommissioned, after the Equans contract ends.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFinal approval is sought in Part B of the report
Money£4.8m forecast annual operating cost cutAcross first five years, per Ark Consultancy business plan
What happens nextDepot lease signing planned for October 2026Subject to Executive agreement of Heads of Terms
Who it affectsCouncil housing tenants in 11 listed wardsWards include Moston, Piccadilly, Gorton and Abbey Hey, others

What was decided

The Executive noted and agreed the proposal to establish a combined insourcing and recommissioning model for housing repairs and maintenance, with the principal operational elements delivered directly by the Council and specialist functions procured externally. Report P6, 1.3

The Executive noted that the existing contract with Equans expires on 31 March 2027 and that the new model is intended to start on 1 April 2027, with mobilisation and procurement activity needed to support that date. Report 1.1, 1.4, 2.1

The Executive noted that the recommended approach is a hybrid model, having rejected the options of retendering externally and of full insourcing. Report P40, P41, P43

Why

The current Equans contract expires on 31 March 2027 with no further extension options, so the Council must set new delivery arrangements from 1 April 2027. Report 1.1, 2.1

The Housing Revenue Account is operating at a significant annual deficit of £22.758m, and the existing repairs and maintenance contract is described as unsustainable, with the proposed model a key part of the HRA Sustainability Plan. Report P16

The proposal is intended to give the Council greater control over prioritisation, productivity, performance management and customer experience, while keeping access to specialist accredited expertise where needed. Report 2.6, 2.22, P17

What happens next

Officers are progressing mobilisation activity, including a depot lease (signing targeted for October 2026), new ICT systems, fleet provision, workforce transition, and procurement of specialist managed services. Report 1.4, 2.11, 3.1, 3.8

Officers are engaging with Equans on contingency arrangements to support service continuity during the transition, and Legal Services will continue to advise on workforce transfer, procurement and contractual transition. Report 1.1, 3.3, 3.8

An Equality Impact Assessment will inform the project plan, with further detail on financial, capital and risk implications set out in Part B of the report. Report P8, 3.1, 4.1

The money

  • £22.758m Current annual HRA operating deficit Report P16
  • £4.8m Forecast reduction in annual operating costs over the first five years, per Ark Consultancy business plan Report P16
  • £13.1m Projected responsive repairs cost in 2027/28 under the proposed model Report P16
  • £8.3m Projected responsive repairs cost by Year 5 of the new model Report P16

Options considered

  • Rejected: Retender with Equans or an alternative external contractor. Would not give the Council sufficient direct control over prioritisation, resourcing and productivity improvements Report P40
  • Rejected: Full insourcing of all repairs and maintenance activity. Specialist, intermittent or accreditation-led work such as scaffolding and fire safety is better delivered by external contractors Report P41
  • Chosen: Hybrid model: insource principal operations, recommission specialist services. Balances direct control over day-to-day service with access to specialist expertise and offers the best value for money Report P42, P43, 2.5

Implications

  • Financial: Forecast £4.8m reduction in annual operating costs over five years, but insourcing alone will not resolve the HRA's financial challenges. Report P16, P17
  • Financial: Potential capital implications from ICT, depot, fleet and building safety investment, which may require reprofiling of the HRA capital programme, alternative funding or additional borrowing. Report P19, P20
  • Financial: Long-term lease arrangements for depots and operational facilities would be recognised on the HRA balance sheet as right-of-use assets, with associated depreciation and financing charges. Report P21
  • Legal: Workforce transfer, contractual transition, procurement, property and information governance matters will be supported by Legal Services. Report 3.3, 3.8
  • Equalities: The decision could affect vulnerable and disadvantaged tenants; an Equality Impact Assessment will consider impacts on tenants, employees and other affected groups. Report P8
  • Risk: Contingency arrangements are being put in place with Equans to support service continuity and mitigate implementation risk during the transition. Report 1.1, 1.4, 3.5
  • Staffing: Workforce transition, including a TUPE-style transfer from the current contractor, is part of the mobilisation plan. Report 1.4, 3.3, 3.8
  • Other: The model is designed to support the Council's obligations under the Social Housing (Regulation) Act and Consumer Standards, including on damp and mould. Report 2.22

Who and where

  • Council housing tenants in 11 Manchester wards, including Ancoats and Beswick, Ardwick, Charlestown, Cheetham, Clayton and Openshaw, Gorton and Abbey Hey, Harpurhey, Higher Blackley, Miles Platting and Newton Heath, Moston and Piccadilly Report P7
  • The current contractor, Equans, whose contract ends on 31 March 2027 Report 1.1, 2.1
  • The directly employed workforce that will deliver the new Internal Property Service from 1 April 2027 Report 1.3, 2.12, P48
  • Specialist external contractors who will be tendered for the recommissioned managed services Report 2.12, P50, P51

Timeline

  • December 2023: Major Contracts Board received a report proposing in-sourcing of high-volume repairs components Report 2.13
  • February 2026: Executive gave in-principle approval to develop a combined insourcing and recommissioning model Report P1, 1.2, 2.3
  • October 2026: Depot lease intended to be signed, subject to Executive agreement of Heads of Terms Report 2.11
  • 31 March 2027: Existing contract with Equans expires, with no further extension options Report 1.1, 2.1
  • 1 April 2027: Combined insourcing and recommissioning model intended to commence Report P2, 1.4, 2.8

Plain English for the jargon

  • HRA: Housing Revenue Account, the ringfenced account that records income and expenditure relating to council housing
  • Responsive repairs: Repairs requested by tenants in occupied council homes, as opposed to planned or void works
  • Voids: Council properties that are empty between tenancies and may need work before reletting
  • Insourcing: Bringing services currently provided by an external contractor back into direct delivery by the Council's own workforce
  • Requisitioning: Procuring services again from external providers, here used to mean recommissioning specialist functions through new contracts
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item73

Resolved

Decision The Executive note and agree the proposal for the Council to establish a combined insourcing and recommissioning model for delivery of the housing repairs and maintenance service.
Word for word from the decision Manchester published for this meeting. Source: democracy.manchester.gov.uk

Follow this further

Built from Manchester's papers

What the report saysPro

Report to Executive

Summary

The Council’s contract with Equans for repairs, maintenance and compliance services to directly managed council housing expires on 31 March 2027. In February 2026, Executive gave in-principle approval to develop a combined model under which the principal operational elements of the service would be brought into direct Council management, with specialist functions recommissioned through externally procured arrangements.

This report sets out the proposed model, supporting business plan, mobilisation arrangements, financial implications and key risks, and seeks approval to proceed with the insourcing of the principal operational elements of the service and the recommissioning of specialist managed services from 1 April 2027.

Recommendations

The Committee is recommended to:

1. Note and comment on the contents of the report.

Executive is recommended to:

1. Note the proposal for the Council to establish a combined insourcing and recommissioning model for delivery of the housing repairs and maintenance service, further details of which are set out in Part B.

Wards Affected: Ancoats and Beswick; Ardwick; Charlestown; Cheetham; Clayton and Openshaw; Gorton and Abbey Hey; Harpurhey; Higher Blackley; Miles Platting and Newton Heath; Moston; Piccadilly;

Environmental Impact The retrofitting of existing council properties to Assessment - the impact of the meet zero carbon objectives is a key part of the issues addressed in this report on council housing capital programme and this is part achieving the zero-carbon target of the wider programme on maintaining and for the city improving council housing. Equality, Diversity and The tenant composition of council housing is Inclusion - the impact of the increasingly diverse and the council housing issues addressed in this report in repair and maintenance service needs to reflect meeting our Public Sector and respond to the diversity of Equality Duty and broader tenants. Responding to the diversity of tenants is equality commitments a key part of the Consumer Standards. The decision on the future management of the repair and maintenance service could impact on vulnerable and disadvantaged tenants and the project plan will be informed by an Equality Impact Assessment. The assessment will consider the impact of the of proposals on tenants, employees and other affected groups to ensure the Council meets its Public Sector Equality Duty. Children and Young People – It is vital that council housing the impact of the issues is managed, repaired and maintained to a high addressed in this report on standard so that children who live in council children and young people housing have a decent home to live which will be a platform for them to thrive in everything they do.

Our Manchester Strategy Summary of how the contents of the report Outcomes supports the delivery of the Our Manchester Strategy Our People: Our People is about Council housing repaired and maintained to a high everyone who calls Manchester standard will create a platform for all council home, making sure they can live tenants to thrive in everything they do. their best lives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Repairs Insourcing and Recommissioning (Part A)Report 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 19 attended
GB
Councillor Garry BridgesChair, present
SB
Councillor Shazia ButtCommittee Member, apologies
TR
Councillor Tracey RawlinsCommittee Member, present
JR
Councillor Julie ReidCommittee Member, present
TF
Councillor Thomas Frederick RobinsonCommittee Member, present
BS
Councillor Basat SheikhCommittee Member, present
MS
Councillor Mandie Shilton GodwinCommittee Member, present
AS
Councillor Andrew SimcockCommittee Member, present
GW
Councillor Gavin WhiteCommittee Member, present
SA
Councillor Sian AstleyAdvisory Member, present
BC
Councillor Becky ChambersAdvisory Member, present
AJ
Councillor Astrid JohnsonAdvisory Member, apologies

All 19 on the meeting page

On this subject at Manchester

Search all
  1. Housing Repairs Insourcing and Recommissioning (Part A)This decision
  2. Housing Repairs Insourcing and Recommissioning (Part A)Noted
  3. Re-establishment of the Housing Repairs and Maintenance Service Scrutiny SubgroupDeferred
  4. Establishment of the Housing Repairs and Maintenance Contract Scrutiny SubgroupApproved
  5. Call In - Extension of Repairs and Maintenance contract for MCC Housing ServicesDecided

More from Manchester Executive

All decisions
MeetingDecisionOutcome
16 Sep 2026 Adult Social Care - Unpaid Carers Strategy 2026 – 2029Decision The Executive approve and adopt the Unpaid Carers Strategy 2026-29 Approved Open
10 Jun 2026 Appointment of Executive Members and their PortfoliosDecision The Executive note the appointments of Deputy Leader and Executive Members Noted Open
10 Jun 2026 Delegation of Executive Functions to the Executive and Council OfficersDecision The Executive:- (1) Note the decision of the Leader of the Council to exercise the power under Section 9E(2)... Noted Open
10 Jun 2026 Corporate Priorities 2026/27Decision The Executive adopt the commitments made in the Manchester Labour 2026 manifesto as priorities for the Execu... Approved Open