The Council agreed: (1) To make a Compulsory Purchase Order for the acquisition of the land and rights needed for the scheme as shown on the plans set out in appendix 1 to the report; (2) To grant delegated powers to the Director of Regeneration, Community and Culture to finalise the details of the Compulsory Purchase Order and make the Compulsory Purchase Order including making minor variations to the areas to be acquired; (3) To grant delegated powers to the Director of Regeneration, Community and Culture to finalise the details of the Side Roads Order and make the Side Roads Order including making minor variations to the areas to be included; To resolve to hold a joint Compulsory Purchase Order/Side Roads Order and Planning Inquiry should one be requested by the Secretary of State.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks agreement to make a Compulsory Purchase Order (CPO) in respect of land required for the A228 Stoke Crossing bridge.
1. Budget and Policy Framework
1.1The A228 Stoke Crossing is funded by the Homes and Communities Agency (HCA). The improvement schemes to the A228 of which this forms part are supported by relevant policies contained within the Local Transport Plan and are key to the delivery of the regeneration proposals for the former refinery site at Grain. The project will be part funded from HCA and part from a developer contribution.
1.2Whilst much of the land required for the works is within the Council’s control, there is a need to acquire some additional land and in order to ensure the works are delivered within the funding period a CPO is proposed. The decision to make a CPO must be made by Full Council.
1.3The funding from HCA is only available until 31 March 2011 and must be fully spent by then. The S106 contribution will have the usual 5-year spend window. Delays in land acquisition would affect environmental mitigation works, which can only take place during specific periods of the year. Mitigation of environmental impact is critical to the delivery of this project and it is proposed to include mitigation land within the CPO, although it is still the intention to try to secure rights to enter onto land and to manage and monitor the mitigation through agreement. 2. Acquisition of Land
2.1There are only 3 freehold landowners directly affected by the project. There are others who have rights of access, which will be maintained during the works and ultimately re-provided on a slightly different line but with no detriment to the right. There is also an agricultural tenancy. One owner is Network Rail whose operational land cannot be acquired by CPO but the primary requirement from this organisation is the agreement of air rights to permit the building of a bridge over the railway line. There is a standard procedure and form of agreement for local highway authorities to acquire such rights for new roads and this is not expected to present any particular problems.
2.2Cabinet approved the line and layout of the proposed bridge on 15 December 2009. As a result, the exact land requirements have now been determined. Government guidance on the use of CPO powers indicates that before embarking on compulsory purchase and throughout the preparation and procedural stages, acquiring authorities should seek to acquire land by negotiation wherever practicable. Negotiations have been started with affected landowners, but given the time constraints it is considered that unless the Council initiates the use of its CPO powers, there is a risk that the scheme will either be substantially delayed or will not occur at all. The biggest risk is that in the absence of the CPO, the legal completion of the transfers may not be completed in time given that the programme is extremely tight. Government guidance accepts that, given the amount of time which needs to be allowed to complete the compulsory purchase process, it may often be sensible for the acquiring authority to initiate the formal procedures in parallel with such negotiations.
2.3It is to address this particular risk that it is important that CPO powers are available. Once CPO powers have been confirmed by the Secretary of State, the Council has powers to serve notice to enter and use the land even though the formal transfer has not taken place. This means that the transfer can take place once all formalities have been concluded without affecting project delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.