Cabinet, Tuesday 8 June 2010 at 3.00pm

Gateway 3 Contract Award: A228 Stoke Crossing

Agreed Executive 2 papers

Cabinet agreed this item on Tuesday 8 June 2010. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

75/2010 The Cabinet agreed to waive contract rules to permit the following decision without the Procurement Board having first considered the report. 76/2010 The Cabinet agreed to accept the most economically advantageous tender submitted by Birse Construction as set out in the exempt appendix to the report. 77/2010 The Cabinet agreed that these decisions are urgent and therefore should not be subject to call-in. Reasons: The decision to appoint the contractor who submitted the most economically advantageous tender will ensure that the project can proceed efficiently and ... view the full minutes text for item 43.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet, 9 pages

Summary

This report seeks the approval to the award of a contract for the construction of a bridge at Stoke Crossing on the A228.

1. Budget and Policy Framework

1.1The A228 Stoke Crossing is funded by the Homes and Communities Agency (HCA). The improvement schemes to the A228 of which this forms part are supported by relevant policies contained within the Local Transport Plan and are key to the delivery of the regeneration proposals for the former refinery site at Grain. The project will be part funded from HCA and part from a developer contribution.

1.2A funding agreement with HCA is in place and a S106 Agreement with National Grid has been signed. The estimated project costs are within the funding agreements as shown in the financial section of the report. The project is the subject of a major planning application. This application provides detailed assessment of the project against national, regional and local planning policies. These include PPS1 & Climate Change Supplement PPG13, Towards a Sustainable Transport System, South East Plan CC1, CC4, T1 & T14 and Medway Local Plan T3, T4 & T18.

1.3The project is, therefore, within the Policy and Budgetary Framework of the Council.

1.4The project funding from the HCA is limited to the current financial year. The very restricted timescale means that delivery is dependent on thorough planning of initial operations, in particular gaining the approval of Network Rail, the Environment Agency (EA) and the GPSS (who control the Government fuel pipeline). The involvement of the contractor at this stage of the project, even before planning permission is granted, will significantly increase the efficiency of the project delivery and mitigate against a number of the risks which are dealt with in more detail later in the report.

1.5Delays in obtaining the approvals will delay the start. Certain works, such as moving water voles to safe areas are seasonal and cannot be delayed. This work must be planned and approved by the EA. Delays to the start will put at risk the likelihood of committing all the HCA funding in the current financial year in accordance with the funding agreement. In addition, it is essential that early approval is gained to methods of working near services and over the railway in order that there can be certainty that no changes are going to be made prior to the steel being ordered. Over the last 6 months steel prices have risen by 200/tonne. Delay in approval will result in delay in ordering and the current best estimate is that the price is expected to rise by a further 80/tonne. For these reasons Cabinet is asked to consider this an urgent item.

1.6The Chairman of the Regeneration, Community and Culture Overview and Scrutiny Committee has agreed to waive call in on this report on the basis that this matter is reasonable in all the circumstances and to it being treated as a matter of urgency in accordance with Rule 16.11 of the Overview and Scrutiny Rules (Part 5 of Chapter 4 in the Constitution).

2. RELATED DECISIONS

2.1Cabinet approved the scheme and the submission of a planning application at its meeting on 15 December 2009 (decision 234/2009 refers). A further approval to seek Compulsory Purchase Powers, should they be required, was made at Full Council on 4 March 2010.

3. BACKGROUND/INTRODUCTION

3.1Tenders have been received for this project and details of their analysis are set out in the exempt appendix. The value of the tender exceeds the Director’s delegated authority and the matter is therefore a decision for Cabinet. The report recommends that the tender be accepted. However, full commitment to the project will not occur until the grant of planning consent. A decision on the planning application is expected on 14 July 2010.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateway 3 Contract Award: A228 Stoke CrossingReport 9 pages DownloadRead as text
PDF
Gateway 3 Contract Award: A228 Stoke Crossing Revised Risk RegisterReport 218 KB Download

At this meeting

Whole meeting

Who was there

10 of 16 attended
RC
Councillor Rodney Chambers (Con)Committee Member, present
AJ
Councillor Alan Jarrett (Con)Committee Member, present
JB
Councillor Janice Bamber (Con)Committee Member, present
JC
Councillor Jane Chitty (Con)Committee Member, present
HD
Councillor Howard Doe (Con)Committee Member, present
PF
Councillor Phil Filmer (Con)Committee Member, present
TM
Councillor Tom Mason (Con)Committee Member, present
MO
Councillor Mike O'Brien (Con)Committee Member, present
LW
Councillor Les Wicks (Con)Committee Member, present
DW
Councillor David Wildey (Con)Committee Member, present
RC
Rose CollinsonOfficer, in attendance
RC
Robin CooperOfficer, in attendance

All 16 on the meeting page

On this subject at Medway

Search all
  1. Gateway 3 Contract Award: A228 Stoke CrossingThis decision
  2. Gateway 3 Contract Award: for the Pre-Construction and Design Development for the Danecourt Secondary New Build ProjectAgreed
  3. Gateway 3 Contract Award: Medway All Age Service (Substance Misuse)Agreed
  4. Gateway 1 Report: Highways Infrastructure ContractAgreed
  5. Gateway 3 Contract Award: Advocacy for Parents with Children in or on the Edge of CareAgreed
  6. Gateway 3 Contract Award: Recycling Resource Management (RRM) ProcurementAgreed

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies