224/2010 The Cabinet approved progress to Gateway 2 – Competitive Process, using the single stage tender, as set out in paragraph 7.3 of the report . Reasons: The new facilities are required to support the amalgamation of the predecessor schools and support the achievement of improved outcomes for students. The capital programme approved by Council in February 2010 includes funding for the project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report sets out the options appraisal for the building works to support the amalgamation of Lordswood Infant and Junior Schools.
1. BUDGET AND POLICY FRAMEWORK
1.1The project is within the policy and budgetary framework, being consistent with the provisions outlined in the Council’s Primary Strategy for Change policy.
2. RELATED DECISIONS
2.1On 12 May 2009, Cabinet (decision 72/2009) agreed to consult on the proposal to amalgamate Lordswood Infant School with Lordswood Junior School.
2.2At the 15 December 2009 meeting (decision: 212/2009) Cabinet “authorised the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children's Services, to publish full proposals including statutory notices relating to the closure of Lordswood Junior School and the prescribed alterations to Lordswood Infant School.
2.3In addition, (decision: 213/2009) the Cabinet agreed, “to delegate authority to the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children's Services to determine whether to approve the proposals at the end of the statutory representation period, if no objections are received.” 2.4 Children and Adult Services Directorate Management Team (CASDMT) confirmed approval of the business case paper, to proceed with detailed design on 13 May 2010.
3. BACKGROUND/INTRODUCTION
3.1Following the above approval from CASDMT on 13 May 2010, a design team has been established to develop the project to RIBA (Royal Institute of British Architects) stage G. This includes the relevant survey works to ensure any risks are managed or mitigated and detailed cost planning has been undertaken. The design is now sufficiently developed to approach construction companies to provide tendered costs. This report seeks approval to proceed to Gateway 2 to invite tenders for the scheme from contractors selected from the Kent County Council’s (KCC) select list of approved contractors.
4. BUSINESS CASE
4.1Business Case Summary
Lordswood Infant and Junior school were amalgamated in September 2010. The education vision for the headteacher, governors and senior team are to provide functional, inspirational and secure learning environments for all pupils using the foundation stage model of open plan spaces and project- based learning.
The project is needed to provide one united building for the school following their amalgamation and improved accommodation for teaching and learning.
By making better use of the space on the ground floor, all classrooms can be accommodated and situated together in year groups, with access to shared resources and to outside classroom space, enabling cross class working.
The link building to join the two schools will unite the schools physically as well as providing a functional weatherproof route for children, staff and visitors.
4.2Strategic Context
The project will support the council’s Primary Strategy for Change policy, in providing 21st century accommodation for high quality teaching and learning.
4.3Whole Life Costing/Budgets
This information is set out in an exempt appendix. 4.4 Risk Management
A copy of the full risk register is set out in the exempt appendix as it contains commercially sensitive information.
4.5Market Testing (Lessons Learnt/Bench Marking)
The works being undertaken can be offered by a number of quality contractors and good value for money can be obtained by tendering through the council’s contractor framework.
4.6Stakeholders Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.