Project Commencement/Options Appraisal - Gateway 1 Report: Advocacy Service for Parents with Children in or on the Edge of Care

Agreed Executive 1 paper

AI summaryMedway Council Cabinet agreed to pursue procurement of a parent advocacy service for families on the edge of care and families with children already in care [D]. It is expected to cost £250,000 per year from the social care revenue budget [P3].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFamilies on the edge of care and children in care [D]
Money£250,000 per year [P3]
What happens nextOpen procurement procedure [P8]Commissioners view the market as limited [P8]
Who it affectsEdge of care families [D]Edge of care parents and parents of children in care [D]

What was decided

Cabinet decided to begin procuring an advocacy service for parents [D]. The service would support families on the edge of care and families with children already in care [D]. It would build their strength and emotional resilience [D].

The service would give parents confidence to access support and services [D]. This would help them safely keep their children with them [D].

The service would build on the existing advocacy service, which ends in March 2026 [D].

Why

Medway Council believes that, where appropriate and safe, every effort should be made to support families to keep their children in their family setting [D].

The existing approach directly contributed to keeping 29 children out of care in the last 4 years [D]. Those children could remain safely and appropriately with their birth families [D].

Cost avoidance over 4 years is circa £7million [D]. This is based on a conservative estimated cost of £65000 per year [D].

What happens next

This is an above threshold service under the Procurement Act 2023, so an open procedure is appropriate [P8]. Commissioners view the market as limited [P8]. Report P8

Include the standard social value outcomes and measures in the tender, without requiring bidders to deliver every line [11.1]. Score each bidder's accumulated value as part of the price evaluation [11.1]. Report 11.1

Turn the winning bidder's social value commitments into contract key performance indicators [11.2]. Report 11.2

The money

  • £250,000 per year Anticipated cost of the advocacy service, funded from the social care revenue budget [P3]. Report P3
  • £65000 per year Conservative estimated cost used in the cost avoidance estimate [D].
  • circa £7million Estimated cost avoidance over 4 years [D].

Options considered

  • Chosen: Open procedure. The service is above threshold under the Procurement Act 2023, and commissioners view the market as limited [P8]. Report P8
  • Chosen: No formal consultation. The Council did not undertake formal consultation [9.1]. The provider commissioned Activ Mob to consult service users, and parents' views were included in the specification [9.1]. Report 9.1

Implications

  • Financial: Anticipated cost is £250,000 per year [P3]. It is funded from the social care revenue budget, with no need to seek additional funding sources [P3]. Report P3
  • Financial: Cost avoidance over 4 years is circa £7million, based on a conservative estimated cost of £65000 per year [D].
  • Legal: There are no direct legal implications arising from the report [P4]. Good contract management is essential to ensure the Council receives the services it is paying for [P4]. Report P4
  • Risk: Contract management will provide evidence needed to terminate contracts or recover money where contractors are not performing [P4]. Report P4
  • Staffing: If an alternative provider is awarded the contract and delivers the service from a different location, TUPE is likely to apply [P6]. Report P6
  • Other: No ICT implications have been identified [P10]. The service is an above threshold procurement under the Procurement Act 2023, with an open procedure proposed [P8]. Report P10, P8
  • Other: Tender social value measures cover local hiring, apprenticeships, local supply spend, local supply chain events and health initiatives [P15] [P16]. Bidder values will form part of the price evaluation [11.1]. The winning bidder's commitments will become contract key performance indicators [11.2]. Report P15, P16, 11.1, 11.2
  • Climate: Tender social value measures cover carbon emission reductions, sustainable procurement requirements and lower carbon delivery methods [P16]. Report P16

Who and where

  • Families on the edge of care
  • Parents with children already in care
  • Children remaining with their birth families
  • Service users consulted by Activ Mob Report 9.1
  • Existing staff if an alternative provider takes over Report P6
  • Local employees, apprentices and local suppliers Report P15, P16
  • Prospective bidders and the winning contractor Report P8, 11.2
  • Council contract management staff Report P4

Timeline

  • 2025-12-16: Cabinet agreed to pursue procurement of the advocacy service [D].
  • last 4 years: The existing approach contributed to keeping 29 children out of care [D].
  • March 2026: The existing advocacy service ends [D].

Plain English for the jargon

  • TUPE: The Transfer of Undertakings (Protection of Employment) Regulations 2006, likely to apply if an alternative provider delivers the service from a different location [P6].
  • Social value: Tender outcomes covering local jobs, skills, supply opportunities, health initiatives and carbon reduction [11.1] [P15] [P16].
  • Key performance indicators: Contractual measures based on the winning bidder's social value commitments [11.2].
  • Open procedure: The procurement route proposed because commissioners view the market as limited [P8].
  • Cost avoidance: Cost avoidance estimated at circa £7million over 4 years [D].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

198/2025 The Cabinet agreed to pursue the procurement of an Advocacy service for parents that would work in a multi-disciplinary way to support families on the edge of care and those with children already in care to build their strength and emotional resilience. Reasons: Medway Council believes that where appropriate and safe to do so, every effort should be made to support families to keep their children with their family setting. This service seeks to build on the experience of the original Advocacy service for mother’s contact which ends in March 2026. This service will work in similar multi-disciplinary way to support families on the edge of care and those with children already in care to build their strength and emotional resilience. Giving them the confidence to access support and services to ensure they can safely keep their children in their care. This multi-disciplinary approach to supporting mothers directly contributed to keeping 29 children out of care in the last 4 years, allowing them to safely and appropriately remain with their birth families. In addition to the benefits for a child in remaining with their birth family, based on a conservative estimated cost of £65000 per year, the cost avoidance over 4 years is circa £7million.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet, 14 pages

Cabinet

16 December 2025

Project Commencement/Options Appraisal - Gateway 1 Report: Advocacy Service for Parents with Children in or on the Edge of Care Portfolio Holder: Councillor Adam Price, Portfolio Holder for Children’s Services

Report from: Kelly Cogger, Assistant Director, Children’s Social Care

Author: John Taylor, Service Manager, Commissioning and Placements

Procurement Overview Total Contract Value (estimated): £1 million Regulated Procurement: Yes Proposed Contract Term: 3 years plus option to extend by 1 year

Summary This report seeks permission to commence the procurement of the Advocacy for Parent/s of Children in or on the Edge of Care Contract.

1. Recommendation 1.1. The Cabinet is asked to agree to pursue the procurement of an Advocacy service for parents that will work in a multi-disciplinary way to support families on the edge of care and those with children already in care to build their strength and emotional resilience.

2. Suggested reasons for decision

2.1Medway Council believes that where appropriate and safe to do so, every effort should be made to support families to keep their children with their family setting. This service seeks to build on the experience of the original Advocacy service for mother’s contact which ends in March 2026. This service will work in similar multi-disciplinary way to support families on the edge of care and those with children already in care to build their strength and emotional resilience. Giving them the confidence to access support and services to ensure they can safely keep their children in their care. This multi-disciplinary approach to supporting mothers directly contributed to keeping 29 children out of care in the last 4 years, allowing them to safely and appropriately remain with their birth families. In addition to the benefits for a child in remaining with their birth family, based on a conservative estimated cost of £65000 per year, the cost avoidance over 4 years is circa £7million.

3. Budget & Policy Framework

3.1A key part of Medway Council’s Sufficiency Strategy, A Place Called Home is Supporting Families. “Protecting children and young people, and strengthening families, so they can live safely at home”. The Council has committed to prioritising work to strengthen families, and the Advocacy service is referenced in the sufficiency strategy service as a key element of this work. Medway Council believes that keeping children in the family home (where safe and appropriate to do so) delivers better outcomes for those children. In addition, reducing the number of children coming into care contributes significant cost avoidance for the Council.

3.2The current service ends on 31 March 2026, so it is imperative to procure this service as soon as possible to minimise any disruption to service users.

4. Background Information and Procurement Deliverables 4.1. The overarching priority for this service is to reduce the number of children coming into care. The specification for this service has been shaped by learning from the current successful advocacy service. The successful provider will work with parents in a multi-disciplinary, non- judgemental way to give them the strength and emotional resilience to work with service to enable them to safely and appropriately care for their children in the family home.

4.1.1. The service provider will receive referrals via the Medway family Partnerships co-ordinator. They will then offer support in the form of advocacy, supported by mental health and domestic violence services with the aim to address and then mitigate some or all of the factors that prevent parents from safely looking after their own children.

4.2Procurement Deliverables

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Commencement/Options Appraisal: Gateway 1 Report: Advocacy Service for Parents with Children in or on the Edge of CareReport 14 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, apologies
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, present
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present
RH
Richard HicksOfficer, in attendance
AB
Adam BryanOfficer, in attendance

All 15 on the meeting page

On this subject at Medway

Search all
  1. Project Commencement/Options Appraisal - Gateway 1 Report: Advocacy Service for Parents with Children in or on the Edge of CareThis decision
  2. Gateway 1 Project Commencement/Options Appraisal: Provision of Residential and Nursing Care for Older People (Aged 65+)Agreed
  3. Gateway 1 Project Commencement/Options Appraisal: Recycling Resource Management (RRM) procurementAgreed
  4. Gateway 1 Project Commencement/Options Appraisal - Medway TestNoted
  5. Gateway 1 / Gateway 3 Project Commencement / Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund WorksAgreed
  6. Gateway 1 Batched Procurement Commencement: Abbey Court School, Rainham, Elaine Primary School, Strood, Twydall Primary School, Gillingham - Building ProjectsApproved

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open