4/2011 The Cabinet approved progress to Gateway 2 – Competitive Process, using the single stage tender, as set out in paragraph 7.3 of the report Reasons: The new facilities are required to enable the school to deliver the quality of curriculum offer for the key subjects as described in the business case section of the report and the capital programme approved by Cabinet in February 2010 includes funding for the project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report sets out the options appraisal for the building works to support the amalgamation of Thames View Infant and Junior Schools.
1. BUDGET AND POLICY FRAMEWORK
1.1The project is within the policy and budgetary framework, being consistent with the provisions outlined in the Council’s Primary Strategy for Change policy.
2. RELATED DECISIONS
2.1On 12 May 2009, Cabinet agreed to consult on the proposal to amalgamate Thames View Infant School with Thames View Junior School (decision 71/2009).
2.2At the 15 December 2009 meeting Cabinet “authorised the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children's Services, to publish full proposals including statutory notices relating to the closure of Thames View Junior School and the prescribed alterations to Thames View Infant School” (decision: 217/2009).
2.3In addition, the Cabinet agreed, “to delegate authority to the Director of Children and Adult Services, in consultation with the Portfolio Holder for Children's Services to determine whether to approve the proposals at the end of the statutory representation period, if no objections are received.” (decision: 218/2009) 2.4 Children and Adult Services Directorate Management Team (CASDMT) confirmed approval of the business case paper, to proceed with detailed design on 19 August 2010.
3. BACKGROUND/INTRODUCTION
3.1Following the above approval from CASDMT on 19 August 2010, a design team has been established to develop the project to RIBA (Royal Institute of British Architects) stage G. This includes the relevant survey works to ensure any risks are managed or mitigated and detailed cost planning has been undertaken. The design is now sufficiently developed to approach construction companies to provide tendered costs. This report seeks approval to proceed to Gateway 2 to invite tenders for the scheme from contractors selected from the Kent County Council’s (KCC) select list of approved contractors.
4. BUSINESS CASE
4.1Business Case Summary
Thames View Infant and Junior school have federated and will amalgamate in April 2012. In order for the school to sustain the number of pupils on roll, we will extend the nursery accommodation. This will increase the number of places the school is able to offer to align with their published admission number of 60. We will also improve the dropping off/waiting area outside the nursery entrance with use of a canopy.
The junior school building will have a new main entrance, offering a more obvious focal point for visitors to the school and allowing sufficient space for a central hub for administrative staff for the amalgamated school.
4.2Strategic Context
The project will support the council’s policy, in providing 21st century accommodation for high quality teaching and learning.
4.3Whole Life Costing/Budgets
This information is set out in an exempt appendix.
Risk management
A copy of the full risk register is set out in the exempt appendix as it contains commercially sensitive information.
4.5Market Testing (Lessons Learnt/Bench Marking)
The works being undertaken can be offered by a number of quality contractors and good value for money can be obtained by seeking tenders from contractors on KCC’s select list of contractors. 4.6 Stakeholders Consultation
We have worked with the headteacher, governors and the senior management team at the school to develop a scheme that will deliver their aim for this project. The headteacher has engaged with the pupils for their views and this has been reported back to the design team during the scheme development. Consultation will continue throughout the project.
4.7Other Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.