34/2011 The Cabinet approved the project to proceed to Gateway Two – Competitive Process, on the basis set out in paragraph 7.3.1 of the report (JCT Standard Form of Contract). Reasons: The new facilities are required to enable the school to deliver the quality of curriculum offered for the key subjects as described in the business case section of the report. The capital programme approved in February 2010 included funding for the project.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks approval to the options appraisal for the project at All Faiths Children’s Community School to provide improved accommodation for the school and Children’s Centre, which is currently insufficient to allow the school to deliver the curriculum for its pupils, including 21 statemented deaf children, and families and community within the area.
1. BUDGET AND POLICY FRAMEWORK
1.1The project is within the policy and budgetary framework, being consistent with the Council’s commitment to provide the best possible teaching and learning spaces, and improvements to community facilities. This project has been classified as high risk, therefore, this is a matter for Cabinet.
2. RELATED DECISIONS
2.1Education Programme Board which was held on 23 November 2010 discussed the projects identified to receive Primary Capital funding, totalling £14.9m, of which All Faiths was one of the schemes. This scheme was included in the list of projects included in the capital monitoring report to Cabinet on 30 November 2010.
3. BACKGROUND/INTRODUCTION
3.1A design team has been established to develop the project to RIBA (Royal Institute of British Architects) stage L. This includes the extensive survey works to ensure any risks are managed or mitigated and detailed cost planning has been undertaken. The design is now sufficiently developed to approach construction companies to provide tendered costs. This report seeks approval to proceed to Gateway 2 to invite tenders for the scheme from contractors selected from the Kent County Council’s (KCC) select list of approved contractors.
4. BUSINESS CASE
4.1Business Case Summary
4.1.1 All Faiths’ Children’s Community School in Strood is a single FE school which also provides for a 60 place integrated foundation stage, 22 deaf children and a Nurture group.
4.1.2 The current accommodation is insufficient for basic teaching and learning and the school is not able to admit their maximum PAN of 273, and this has had to be capped by the Council. Year groups share classrooms and some of the rooms do not meet the minimum requirements; the existing hall has to be used as a circulation route resulting in disruption to learning.
4.1.3 The Children’s Centre is based in temporary accommodation in the car park, and has limited planning approval. The unit has insufficient space and is in poor condition.
4.1.4 The main access for pedestrians and vehicles is from Gun Lane, and is shared with the doctors’ surgery and the PCT. This access point is extremely hazardous and requires remodelling work to improve safety.
4.1.5 A feasibility study was undertaken in June 2010 and identified the need for a new build Children’s Centre, a new hall, 3 new classrooms and internal remodelling of the existing school accommodation, which included improvements to the current kitchen, which is also undersized.
4.1.6 The study has been reviewed to ensure the project delivers the school’s immediate priorities, within the budget currently available:
• To deliver the much needed additional teaching space of 3 new classrooms • To provide a new hall which will not be disrupted by the main circulation of the school • To demolish the existing Children’s Centre and provide a new Children’s Centre with improved storage and external learning space • To allow for a new combined reception area, allowing for a stronger link between the school and Children’s Centre • To provide an extra parking area and a new, safer internal road • To provide 1 temporary classroom in September 2011, which will be removed following completion of the new extension, thus allowing the school to accept pupils in the new academic year.
4.2Strategic Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.