42/2011 The Cabinet agreed that this project proceeds to Gateway 2 procurement stage, as part of the 2011/2012 Condition Programme, via the invitation to quote route, as set out in paragraph 3.4 of the report. Building & Design Services will package the projects into 3 or 4 projects per package and tender via the select list. Reasons: This project seeks to avoid a deterioration of school buildings and a position where school buildings are not energy efficient and school closures may result due to a lack of hot water and heating or leaking roofs.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks permission to commence the procurement of boiler works and roofing works at a number of Medway schools.
The Condition programme only includes those schools that are LA funded schools. Therefore this excludes Academies, which are separately funded by the DfE.
The whole Condition programme elements are based on data extracted from the regular Condition surveys of schools. Works are targeted at the worst affected schools and are prioritised (in line with the DfE prescribed Condition formula scoring.
This Gateway 1 report has been approved for submission to Cabinet after consideration by Children and Adults Directorate Management Team on 7 February 2011 and following consideration at the Strategic Procurement Board on 16 February 2011.
The Children and Adults Directorate Management Team and Strategic Procurement Board have recommended that this procurement project be approved as a Category B High Risk procurement project at Procurement Gateway 1 by Cabinet. This is because although this procurement project is Works Category B Medium Risk procurement with a total contract value above £250,000.00, a new project appraisals process was agreed by Cabinet on 28 September 2010 (decision number: 142/2010) that all Children’s Services Capital projects for schools over £500,000 would be considered by Cabinet.
1. Budget and Policy Framework
1.1Service Background Information
1.1.1 The Condition Programme is part of the overall annual Capital Programme 2011-12, agreed by Full Council on 24 February 2011, which focuses on major maintenance works for schools for roofing and boilers for schools along with other works to cover statutory items such as electrical works, asbestos surveys and health and safety.
1.1.2 The objective of the Condition Programme is to ensure schools are watertight and have heat and water supplies. These basic elements are needed to ensure schools can remain operational.
1.2Council’s Strategic Priorities And Core Values
The procurement of this requirement directly links into the following Council Strategic Priorities and Core Values:
Core Values
• Putting our customers at the centre of everything we do. This procurement requirement will deliver against the Core Value of ‘Putting our customers at the centre of everything we do’ through ensuring the schools will remain operational throughout the winter months and there should be no further closures due to plant failure.
• Giving value for money This procurement requirement will deliver against the Core Value of ‘Giving value for money’ through providing a more energy efficient plant and result in a reduction in the schools energy bills. The schools will remain operational throughout the winter months and there should be no further closures due to plant failure.
Strategic Priorities
• A clean and green environment. This procurement requirement will deliver against the Strategic Priority of ‘A clean and green environment’ through replacement of an old energy inefficient system with a modern and more sustainable system, which is more energy efficient.
• Putting our customers at the centre of everything we do. This procurement requirement will deliver against the Core Value of ‘Putting our customers at the centre of everything we do’ through ensuring the schools will remain operational throughout the winter months and there should be no further closures due to leaking roofs or failed heating systems.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.