End of year Council Plan monitoring report 2010/2011
AgreedScrutiny1 paper
Business Support Overview and Scrutiny Committee agreed this item on Thursday 4 August 2011. Below is the council's own wording, with the papers it was decided on.
Members agreed to: (a) note the outcomes achieved against priorities and requested further information, as set out in full above; (b) nominate the Children’s Referral Assessment and Support Teams (CRAST) and Safeguarding teams together with the Chairs of Child Protection Conferences (Independent Reviewing Officers [IRO]) for a Recognition award, to acknowledge the hard work and effort put in by the team in the face of ever-increasing workloads and pressures.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Report to Business Support Overview and Scrutiny Committee
Summary
This report sets out year-end performance against the Council Plan objectives for 2010/11. Members are asked to review content and consider progress. This report also shows the new measures of success that will be used to monitor Council progress in 2011/12.
1. Budget and Policy Framework
1.1This document reports year end performance against the Council Plan 2010-11, which is a key part of the budget and policy framework. The tables (Appendix 2) are an exceptions report and show the performance indicators that have been rated red, amber or data only at the end of the financial year.
Background
2.1In February 2010 Full Council agreed the Council Plan 2010/13 including actions and performance measures to be achieved during the life of the plan. The Council Plan is refreshed annually and following changes to the national policy framework and self regulation agenda the authority is implementing a much streamlined Council Plan for 2011/12 onwards. As part of the new plan the number of priorities have been reduced to five, Appendix 3 details the new measures of success under each of the priorities. This report covers objectives related to the previous six priorities.
2.2The report sets out the final year-end achievement against the key outcomes and actions established as part of last year’s plan, it allows members to review progress in achieving the outcomes in order to identify any ongoing performance issues and take stock of the authority’s position.
2.3The performance of each action and performance indicator is rated green, amber or red to highlight whether actions have been achieved and whether performance levels meet the required standard. Along with the summary of performance below, Appendix 1 provides a draft narrative on performance, and Appendix 2 sets out an exceptions report on actions and performance indicators. Although this report is an ‘exception report’ it also briefly demonstrates the positive difference made in specific areas and highlights issues which have impacted on performance to date or issues that may impact on future performance.
3 Summary of 2010/11 year-end performance
3.1Performance on 56 key performance indicators measures of success can be rated at year-end. Year-end performance is as follows:
Green – 35 measures have achieved or outperformed the target (63%) Amber – 4 measures are below target but within acceptable variance limits (7%) Red – 17 measures are outside acceptable variance limits (30%)
3.2There are also 11 performance measures which are not rated as they are ‘data only’ and have been included for Cabinet information where the direction of travel is not as required.
3.3The chart below illustrates the breakdown across priority areas. Each priority has a different number of indicators contributing to the overall percentage:
Red Amber Indicators by priority area Green Data Only 14
0 A clean and Safer Children and Adults People travelling Everyone green communities young people easily and safely benefiting from environment in Medw ay the area’s regeneration 4 Due to Committee scheduling this report has already been considered by Cabinet. It identified improvement areas that it considered needed particular attention. Members of Business Support Overview and Scrutiny may wish to take those into account when considering areas falling within the Committee’s service remit or it overarching remit on performance.
They are: Strengthen school leadership Reduce reliance on bed and breakfast Continue to drive down SEN out of area placements Continue to push the personalisation agenda to exceed the 30% target Improve mental health services Drive down energy use via property rationalisation and other measures
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.