First Quarter Capital Budget Monitoring 2011/2012

Agreed Scrutiny 1 paper

Business Support Overview and Scrutiny Committee agreed this item on Thursday 4 August 2011. Below is the council's own wording, with the papers it was decided on.

Item253

Resolved

The committee agreed to: (a) note the spending and funding forecasts summarised at Tables 1 and 3; (b) request that officers provide details of schemes which had been rejected from the Members Priority Fund scheme; (c) request that officers notify Members of the ... view the full minutes text for item 253.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Business Support Overview and Scrutiny Committee

Background

2.1Cabinet Members will be considering this report on 2 August and their recommendations will be reported to this meeting.

2.2The approved capital programme for 2011/12 and future years is £107.7m, being £53.6m in respect of brought forward schemes and £54.1m in respect of new approvals.

2.3This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest. 3. Progress

3.1Table 1 below summarises the current overall expenditure and forecasts against each directorate’s 2011/12 capital programme and represents a summary of the detailed information at Appendix 1. Appendices 2 to 6 show the position by directorate.

Table 1: Summary – capital spend and forecasts

Forecast spend

Forecast spend in later years Programme

March 2011 Approved

Spend to

Forecast Variance 2011-12 Directorate

£’000 £’000 £’000 £’000 £’000 Business Support 54,359 37,658 11,285 5,403 (13) Dept Children & Adult 130,188 65,241 44,616 20,331 0 Services Regeneration, Community & 141,113 116,553 20,630 5,568 1,638 Culture Member Priorities 2,904 1,392 1,502 2 (8) TOTAL 328,564 220,844 78,033 31,305 1,617

3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:

 Scheme progressing on time and within budget  Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales

 Scheme neither progressing within expected timescales nor within budget.

Table 2 summarises the projects progress. Full detail is shown in the appendices: Table 2: Project Progress Summary

Progress Monitoring    Total Schemes BSD 16 3 0 19 Children & Adults 75 8 0 83 RCC 54 5 5 64 Member Priorities 18 2 0 20 Total 163 18 5 186

4. Specific Scheme Monitoring Issues and Completions 87% of schemes are progressing well, forecast to complete on time and to budget.

4.1Business Support

4.1.1 The current Business Support directorate capital programme of £16.7m is made up of brought forward approvals for existing schemes, £8.2m, plus the following new approvals - £1m building repair & maintenance fund - £300,000 housing renovation loans - £90,000 housing crisis grants - £1,232,000 disabled facilities grant - £45,000 Beechings Way flat conversion - £2.4m Better for Less - HRA £3.3m housing repairs - HRA £150,000 disabled adaptions

4.1.2 There are no areas of concern to report this cycle.

4.2Children and Adults

4.2.1 At its meeting on 24 February, Council agreed a 2011/12 capital programme of £14,820,930 for the Children and Adult Services directorate. To this has been added £25,845,137 rolled forward from the 2010/11 programme, together with a number of other new funding streams, as outlined below, and giving a total capital budget for the directorate of £64,946,935:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
First Quarter Capital Budget Monitoring 2011/2012Report 115 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 19 attended
JA
Councillor John Avey (Con)Committee Member, present
NB
Councillor Nick Bowler (Lab)Committee Member, apologies, sent representative
MB
Councillor Matt Bright (Con)Committee Member, present
DC
Councillor David Carr (Con)Chairman, present
PG
Councillor Pat Gulvin (Con)Vice-Chairman, present
PH
Councillor Paul Harriott (Lab)Committee Member, present
CI
Councillor Chris Irvine (Con)Committee Member, apologies, sent representative
GJ
Councillor Geoff Juby (Lib Dem)Committee Member, present
VM
Councillor Vince Maple (Lab)Committee Member, present
TO
Councillor Tristan Osborne (Lab)Committee Member, present
DR
Councillor David Royle (Con)Committee Member, present
KT
Councillor Kelly Tolhurst (Con)Committee Member, present

All 19 on the meeting page

On this subject at Medway

Search all
  1. First Quarter Capital Budget Monitoring 2011/2012This decision
  2. Medway Commercial Group Limited - First Year Quarter 3 ReportNoted
  3. Medway Commercial Group Limited - First Year Quarter 2 ReportAgreed
  4. Medway Commercial Group Limited - First Year Quarter 2 ReportNoted
  5. Medway Commercial Group Limited - First Year Quarter 1 ReportNoted
  6. First Quarter Council Plan monitoring 2011/2012Noted

More from Medway Business Support Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Jul 2023 Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... Agreed Open
30 Mar 2023 Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. Noted Open
30 Mar 2023 Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... Agreed Open
25 Jan 2023 Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... Noted Open
25 Jan 2023 Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... Agreed Open