The committee agreed to: (a) note the spending and funding forecasts summarised at Tables 1 and 3; (b) request that officers provide details of schemes which had been rejected from the Members Priority Fund scheme; (c) request that officers notify Members of the ... view the full minutes text for item 253.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Report to Business Support Overview and Scrutiny Committee
Background
2.1Cabinet Members will be considering this report on 2 August and their recommendations will be reported to this meeting.
2.2The approved capital programme for 2011/12 and future years is £107.7m, being £53.6m in respect of brought forward schemes and £54.1m in respect of new approvals.
2.3This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest. 3. Progress
3.1Table 1 below summarises the current overall expenditure and forecasts against each directorate’s 2011/12 capital programme and represents a summary of the detailed information at Appendix 1. Appendices 2 to 6 show the position by directorate.
Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2011 Approved
Spend to
Forecast Variance 2011-12 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 54,359 37,658 11,285 5,403 (13) Dept Children & Adult 130,188 65,241 44,616 20,331 0 Services Regeneration, Community & 141,113 116,553 20,630 5,568 1,638 Culture Member Priorities 2,904 1,392 1,502 2 (8) TOTAL 328,564 220,844 78,033 31,305 1,617
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices: Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 16 3 0 19 Children & Adults 75 8 0 83 RCC 54 5 5 64 Member Priorities 18 2 0 20 Total 163 18 5 186
4. Specific Scheme Monitoring Issues and Completions 87% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
4.1.1 The current Business Support directorate capital programme of £16.7m is made up of brought forward approvals for existing schemes, £8.2m, plus the following new approvals - £1m building repair & maintenance fund - £300,000 housing renovation loans - £90,000 housing crisis grants - £1,232,000 disabled facilities grant - £45,000 Beechings Way flat conversion - £2.4m Better for Less - HRA £3.3m housing repairs - HRA £150,000 disabled adaptions
4.1.2 There are no areas of concern to report this cycle.
4.2Children and Adults
4.2.1 At its meeting on 24 February, Council agreed a 2011/12 capital programme of £14,820,930 for the Children and Adult Services directorate. To this has been added £25,845,137 rolled forward from the 2010/11 programme, together with a number of other new funding streams, as outlined below, and giving a total capital budget for the directorate of £64,946,935:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.