The Cabinet noted the spending forecasts summarised at Tables 1 of the report and noted a reduction to the capital programme and budget virements as detailed in paragraph 5.1 of the report. 150/2011 The Cabinet requested that Council in due course consider the additional funding requirement from the Stoke Crossing overspend in conjunction with those previously requested by Cabinet in respect of other Homes and Communities Agency (HCA) supported schemes. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2011/12 and future years is £109.1m, being £53.4m in respect of brought forward schemes and £55.7m in respect of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
3. Progress
3.1Table 1 below summarises the current overall expenditure and forecasts against each directorate’s 2011/12 capital programme and represents a summary of the detailed information at Appendix 1. Appendices 2 to 6 show the position by directorate. Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2011 Approved
Spend to
Forecast Variance 2011-12 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 54,263 37,658 10,579 5,997 (28) Dept Children & Adult 129,458 64,591 47,420 17,393 (54) Services Regeneration, Community & 142,641 116,553 22,705 6,270 2,888 Culture Member Priorities 2,931 1,392 1,495 46 1 TOTAL 329,293 220,194 82,199 29,706 2,807
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
☺ Scheme progressing on time and within budget
Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget.
Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring ☺ Total Schemes BSD 18 2 0 20 Children & Adults 72 11 0 83 RCC 59 6 3 68 Member Priorities 23 2 0 25 Total 172 21 3 196 4. Specific Scheme Monitoring Issues and Completions 88% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
4.1.1 The current (2011/12 and beyond) BSD capital programme of £16.6m is made up of brought forward approvals for existing schemes, £8.2m, plus the following new approvals totalling £8.4m • £900,000 building repair & maintenance fund (net of transfers) • £300,000 housing renovation loans • £90,000 housing crisis grants • £1,236,100 disabled facilities grant • £45,000 Beechings Way flat conversion • £2.4m Better for Less • HRA £3,296,479 housing repairs • HRA £150,000 disabled adaptions
4.1.2 There are no areas of concern to report this cycle
4.2Children and Adults
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.