CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Medway Council
Business Support Overview and Scrutiny Committee, Thursday 1 December 2011 at 6.30pm

Capital budget monitoring 2011/2012 - second quarter

Agreed Scrutiny 1 paper

Business Support Overview and Scrutiny Committee agreed this item on Thursday 1 December 2011. Below is the council's own wording, with the papers it was decided on.

Item555

Resolved

The committee agreed to: (a) note the spending and funding forecasts summarised in Tables 1 and 3; (b) request a Briefing Note on the outcome of the legal departments view on future recourse against the statutory undertakers of this section 106 agreement; (c) request a Briefing Note on the breakdown of the £2.4 million Better for Less project; (d) request further information to explain Appendix 1 in more detail.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Business Support Overview and Scrutiny Committee

Background

2.1The approved capital programme for 2011/12 and future years is £109.1m, being £53.4m in respect of brought forward schemes and £55.7m in respect of new approvals.

2.2This report consolidates the capital monitoring undertaken by each directorate, which is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.

3. Progress

3.1Table 1 below summarises the current overall expenditure and forecasts against each directorate’s 2011/12 capital programme and represents a summary of the detailed information at Appendix 1. Appendices 2 to 6 show the position by directorate. Table 1: Summary – capital spend and forecasts

Forecast spend

Forecast spend in later years Programme

March 2011 Approved

Spend to

Forecast Variance 2011-12 Directorate

£’000 £’000 £’000 £’000 £’000 Business Support 54,263 37,658 10,579 5,997 (28) Dept Children & Adult 129,458 64,591 47,420 17,393 (54) Services Regeneration, Community & 142,641 116,553 22,705 6,270 2,888 Culture Member Priorities 2,931 1,392 1,495 46 1 TOTAL 329,293 220,194 82,199 29,706 2,807

3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:

 Scheme progressing on time and within budget  Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales

 Scheme neither progressing within expected timescales nor within budget.

Table 2 summarises the projects progress. Full detail is shown in the appendices:

Table 2: Project Progress Summary

Progress Monitoring    Total Schemes BSD 18 2 0 20 Children & Adults 72 11 0 83 RCC 59 6 3 68 Member Priorities 23 2 0 25 Total 172 21 3 196 4. Specific Scheme Monitoring Issues and Completions 88% of schemes are progressing well, forecast to complete on time and to budget.

4.1Business Support

4.1.1 The current (2011/12 and beyond) BSD capital programme of £16.6m is made up of brought forward approvals for existing schemes, £8.2m, plus the following new approvals totalling £8.4m  £900,000 building repair & maintenance fund (net of transfers)  £300,000 housing renovation loans  £90,000 housing crisis grants  £1,236,100 disabled facilities grant  £45,000 Beechings Way flat conversion  £2.4m Better for Less  HRA £3,296,479 housing repairs  HRA £150,000 disabled adaptions

4.1.2 There are no areas of concern to report this cycle

4.2Children and Adults

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital budget monitoring 2011/2012: second quarterReport 44 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 22 attended
JA
Councillor John Avey (Con)Committee Member, present
NB
Councillor Nick Bowler (Lab)Committee Member, apologies, sent representative
MB
Councillor Matt Bright (Con)Committee Member, present
DC
Councillor David Carr (Con)Chairman, present
PG
Councillor Pat Gulvin (Con)Vice-Chairman, present
PH
Councillor Paul Harriott (Lab)Committee Member, present
CI
Councillor Chris Irvine (Con)Committee Member, present
GJ
Councillor Geoff Juby (Lib Dem)Committee Member, present
VM
Councillor Vince Maple (Lab)Committee Member, present
TO
Councillor Tristan Osborne (Lab)Committee Member, present
DR
Councillor David Royle (Con)Committee Member, present
KT
Councillor Kelly Tolhurst (Con)Committee Member, present

All 22 on the meeting page

On this subject at Medway

Search all
  1. Capital budget monitoring 2011/2012 - second quarterThis decision
  2. Capital Budget Monitoring - Round 1 2026/27Noted
  3. Capital Budget Monitoring - Round 1 2026/27Noted
  4. Capital Budget Monitoring - Round 1 2026/27Noted
  5. Capital Budget Monitoring - Round 1 2026/27Noted
  6. Amendments to the Revenue Budget and Capital ProgrammeAgreed

More from Medway Business Support Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Jul 2023 Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... Agreed Open
30 Mar 2023 Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. Noted Open
30 Mar 2023 Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... Agreed Open
25 Jan 2023 Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... Noted Open
25 Jan 2023 Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies