Resolved
The Committee agreed to note: (a)the Risk Management Strategy; (b)the Management Team’s recommendations on amendments to the Council’s Risk Register as detailed in section 4 of the report.
Business Support Overview and Scrutiny Committee agreed this item on Thursday 1 December 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee agreed to note: (a)the Risk Management Strategy; (b)the Management Team’s recommendations on amendments to the Council’s Risk Register as detailed in section 4 of the report.
2.1Cabinet undertook the annual review of the strategy on 30 November 2010 and agreed with the strategy and officers’ recommendations and that no significant changes needed to be made at that time.
2.2The Corporate Risk Register was last reviewed by Cabinet on 29 March 2011. The following changes were made to the register at that time:
Risk Ref: SR 21 – Procurement downgraded to C2. Risk Ref: SR23 – ‘Improvement Plan for Housing Service (HRA)’ downgraded to E2
3. Related Information
3.1The Risk Management Audit 2010/2011 confirmed that risk management arrangements are satisfactory. However it identified that training and arrangements regarding the creation of directorate risk registers require further development.
3.1.1 These two issues were outstanding actions from the plan reported to the Audit Committee in March 2010.
3.1.2 Service risks continue to be recorded in service plans and monitored by Service Managers and through Assistant Directors quarterly reports. It was agreed that adding risks to Covalent, the Council’s performance management system, should be in a later phase of implementation (2011/12) and that training would be provided to assist managers in using Covalent to manage risks.
3.1.3 The Strategic Risk Management Group, in consultation with the Research and Review team (who manage Covalent), have agreed a phased approach, detailed in Appendix D, to take this forward
4 Advice and analysis
4.1The Strategic Risk Management Group has reviewed the Risk Strategy, (Appendix A) and recommended that no significant changes need to be made at this time
4.2Risks owners have reviewed their risks and updated them as detailed in Appendix C and the following recommendations have been proposed:
4.2.1 SR 24 – Managing Change be replaced with a new risk SR 30 Delivering Better for Less Transformation.
4.2.2 SR 09a - ‘Delivering the Transformation Agenda’ be removed as the Transformation programme no longer exists and that it be replaced by a new risk SR 25 ‘Adult Social Care Demographics’ to recognise that the focus must now be on the demographic impact on both demand and capacity to deliver statutory responsibilities. The risk rating of C2 remains the same.
4.2.3 SR 09b – ‘Keeping vulnerable young people safe and on track’ be retained and refocused but remove and create a new risk concentrating on looked after children (ref SR26) risk rating B2. This reflects the fact that there is National and local evidence that children and young people in care are more vulnerable to poorer outcomes which could impact on our statutory responsibilities and regulatory judgement and increased costs.
4.2.4 SR 08a – ‘Partnership Working’ be removed as it is too generic and be replaced with three new risks focusing on key partnerships as described in 4.2.5, 4.2.6 and 4.2.7. 4.2.5 Create a new risk SR 27 risk rating B2 to reflect the fact that Councils are responsible for poor performance of schools including independent, academies and free schools but lack levers for change with potential impact on our statutory responsibilities and regulatory judgement and could have financial consequences.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Review of Risk Management Strategy and six monthly review of Corporate Risk RegisterReport | 291 KB | DownloadRead as text |
Follow Business Support Overview and Scrutiny Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2023 | Work programmeDecision a) The Committee agreed the Committee’s provisional work programme at Appendix 1 to the report. b) The Commi... | Agreed | Open |
| 30 Mar 2023 | Annual Review of the Council's Petitions SchemeThe Committee noted the 2022 annual review of the Council’s Petitions Scheme. | Noted | Open |
| 30 Mar 2023 | Work programme and review of the Committee's work, 2019/231) The Committee agreed the Committee’s provisional work programme at Appendix 1, subject to the following and the vi... | Agreed | Open |
| 25 Jan 2023 | Contract Procedure RulesThe Committee: a) noted the comments of the Audit Committee on the draft revised set out in Appendix 2 to the report;... | Noted | Open |
| 25 Jan 2023 | Work programmeThe Committee: a) agreed the committee’s work programme at Appendix 1 to the report; b) noted the work programmes of ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.