173/2012 The Cabinet: (a) noted the comments and recommendation of the Business Support Overview and Scrutiny Committee, as set out in paragraph 5.1 of the report; (b) approved the Risk Management Strategy, as set out in Appendix A to the report; (c) approved the amendments to the Council’s Risk Register as detailed in section 3 of the report. Reasons: The establishment of a corporate framework for risk management is recommended by CIPFA and SOLACE and will complement and support the work already being carried out within each directorate to manage risks.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
In accordance with paragraph 4.1 of the Council’s Risk Management Strategy, this report is to discuss both the annual review of the Risk Management Strategy and the 6 monthly review of the Council’s Corporate Business Risk Register
1. Budget and Policy Framework
1.1The Risk Management Strategy underpins all aspects of Council work and is fundamental to the Performance Plan in terms of "giving value for money”.
Background
2.1Risk Management Strategy - The Cabinet undertook the annual review of the strategy on 20 December 2011 and agreed the strategy and officers’ recommendations that no significant changes needed to be made at that time.
2.2The Corporate Risk Register - was last reviewed by Corporate Management Team on 7 March 2012 and Cabinet on 14 April 2012. The following changes were made to the register at that time:
2.2.1 The risk rating for risk reference 27 – Government changes to Local Authority’s responsibility for schools be reduced from B2 to C2 as we are clear and decisive about the actions we are taking as a council and increasingly so too are headteachers and chairs of governors 2.2.2 Risk Ref: SR29 -Transition to a new provider for mental health social care services be deleted as this was completed 1 February 2012.
2.2.3 Two proposals relating to Risk Ref: SR30- Delivering Better for Less transformation: a) reduce the list of triggers and corresponding actions to reflect progress made; b) given progress to date and the strength of governance of the programme the risk be down grade risk rating from B2 to C2.
2.3The Risk Management Audit 2010/2011 - confirmed that risk management arrangements are satisfactory. However it identified that training and arrangements regarding the creation of directorate risk registers require further development.
2.3.1 The Strategic Risk Management Group, in consultation with the Research and Review team (who manage Covalent), agreed a phased approach, to take this forward.
3. Advice and analysis
3.1Risk Management Strategy - The Strategic Risk Management Group has reviewed the Risk Strategy, (Appendix A) and recommended that no significant changes need to be made at this time.
3.2The Corporate Risk Register - Risks owners have reviewed their risks and updated them as detailed in Appendix C and the following recommendations have been proposed:
3.2.1 SR 28 Implementation of the Government’s agenda to the Health system – risk rating be increased from D2 to C2 to reflect the change in vulnerability arising from recent clarification on risks relating to finance and contracts.
3.2.2 SR 27 Government changes to Local Authority's responsibility for schools be increased from C2 to B2 to reflect the Council’s increased vulnerability arising from the new OFSTED framework, which comes into place from September 2012, that replaces ‘satisfactory’ with ‘requires improvement’. Any school with 2 consecutive ‘requires improvement’ will be in a vulnerable category. Medway currently has 23 schools with 2 consecutive ‘satisfactory’ inspection ratings and a further 11 with a single, current ‘satisfactory’ judgement.
3.2.3 SR 21 Procurement – risk rating be reduced from C2 to C3 to reflect the progress we have made in terms of embedding procurement processes across the Council which will be significantly enhanced by the introduction of the new Category Management Team.
3.2.4 A new risk SR 31 be created to reflect the Council’s new public health responsibilities involving the transfer of staff, contracts and functions from Medway PCT. 3.3 Appendix B - Record of Amendments, summarises the amendments to the risk register.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.