The Cabinet noted: (a) the spending forecasts summarised at Tables 1 and Appendix 1 of the report; (b) budget virements and additions as detailed in paragraphs 4.2.1, 4.2.2 and 4.3.1 of the report. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2012/13 and future years amounts to £105.6million, comprising £83.0million in respect of brought forward schemes and £22.6million of new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendices. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest. 3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1. Appendices 2 to 5 show the position by directorate.
Table 1: Summary – capital spend and forecasts
Forecast spend
Forecast spend in later years Programme
March 2012 Approved
Spend to
Forecast Variance 2012-13 Directorate
£’000 £’000 £’000 £’000 £’000 Business Support 34,138 26,886 3,195 4,057 0 Department Children and 151,940 79,963 53,400 18,411 (166) Adult Services Regeneration, Community and 89,460 64,104 18,465 6,285 (607) Culture Member Priorities 1,993 996 985 0 (12) TOTAL 277,531 171,949 76,045 28,753 (785)
3.2The progress reports utilise a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time and within budget Scheme progressing on time but not within budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within budget. Table 2 summarises the projects progress. Full detail is shown in the appendices:
Table 2: Project Progress Summary
Progress Monitoring Total Schemes BSD 10 2 0 12 Children & Adults 41 17 0 58 RCC 46 6 0 52 Member Priorities 20 1 0 21 Total 117 26 0 143
4. Specific Scheme Monitoring Issues and Completions 83% of schemes are progressing well, forecast to complete on time and to budget.
4.1Business Support
4.1.1 There have been no changes to the approved programme since the previous report and no schemes are predicting a variance to budget.
4.1.2 However, the scheme in respect of demolition of the Civic Centre was underpinned by anticipated funding of £250,000 from rental income. This will not now be forthcoming and alternative means of funding are being explored.
4.2Children and Adults
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.