85/2013 The Cabinet recommended to Council that a capital scheme be approved to secure sufficient additional places for young children to meet the authority’s statutory duty. 86/2013 The Cabinet recommended to Council that, initially, an upper limit of £560,000 be set – equivalent to the additional capital funding allocated by the Department for Education (DfE). 87/2013 The Cabinet agreed that a further report be brought back to Cabinet in spring 2014 to allow for a review of progress to date, and to assess whether further capital works and funding is required to ensure that the statutory duty is met. Reasons: The local authority is obliged to meet the new duty within the Education Act 2011 to secure sufficient early education places for eligible children aged two-years. The development of a capital programme working with existing good quality providers in the private, voluntary and maintained sectors across the next 12 months will provide a secure basis for expansion of places whilst maintaining a focus on high quality provision for both the child and the family as a whole.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
The duty to secure early education places for vulnerable young children & those from low income households requires provision for around 1400 children.
This report identifies the number of additional places required, and proposes a capital programme across 2013 and 2014 to ensure that the Council’s statutory duty is met, drawing upon the additional capital grant funding allocated to Medway by the Department for Education (DfE) for this purpose.
1. Budget and Policy Framework
1.1These proposals are consistent with the Council Plan and the Children and Young People’s Plan. The Council Plan includes as one of the four strategic priorities that “children and young people have the best possible start in life”.
1.2Additions to the capital programme where the funding source is not ring- fenced are a matter for Full Council.
1.3The Cabinet is asked to consider this as an urgent item to enable this matter to be referred to Full Council on 25 April 2013. The new statutory duty to secure sufficient places for eligible families commences in September 2013. Deferral to a later meeting would not allow sufficient time for works to be carried out prior to the introduction of the duty.
Background
2.1The Coalition Agreement included commitments to improve children’s readiness for school, and to increase fairness in education, through providing free early education places for children aged two years from the most vulnerable and low income households. Regulations define eligibility by a number of income related criteria, which means around 40% of all children of this age will be eligible for a free place by 2014. In Medway this equates to approximately 1400 children.
2.2The provision of high quality interventions targeted at the most disadvantaged and vulnerable young children has the potential to address many of the current issues affecting Medway’s child population – in particular the persistent low attainment in reading and communication of some children in primary education.
2.3At the meeting on 4 September 2012, Cabinet instructed officers to:
Develop a robust and detailed project plan to ensure that by September 2013 the authority is able to meet its statutory duty to provide free early education places to children aged two-years from low income households Encourage providers of good quality early education and childcare to engage with the programme for two-year-olds, and to maximise opportunities to expand and develop new provision to meet the needs of local families.
2.4Medway has a large number of private & voluntary (PVI) settings that already provide publicly funded places for children aged 3 years, and generally also provide places for children aged two years where parents are willing and able to pay fees. Strategically, we have adopted an approach of seeking to secure the large majority of additional places required to meet the duty by working with the existing 100 PVI settings.
2.5Revenue funding for places is from within the Dedicated Schools Grant (DSG), which includes some capacity for ensuring that settings are supported to prepare for additional numbers of younger children, for example through purchase of additional resources and play equipment.
2.6In assessing the capacity of the existing market to supply sufficient places, it is apparent that a capital programme is required. There are currently insufficient places in the localities where places will be required. Whilst we anticipate that the market will expand over time, reliance entirely on market forces to respond to the increased demand for places is judged to represent a significant (“catastrophic”) risk to the Council’s statutory duty.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.