(a) The Council agreed the addition of £800,000 to the capital programme to fund the adaptation and fit-out of new premises, associated relocation costs and the demolition of the Riverside One building. (b) The Council agreed the additional works to Strood Sports Centre redevelopment to be added to the capital programme, with funding of £1.4m to be funded by Prudential Borrowing.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks authority for additions to the Council’s Capital Programme in respect of the relocation of Riverside One and the redevelopment of Strood Sports Centre.
1. Budget and Policy Framework
1.1The Council’s Constitution requires Full Council approval for additions to the Capital Programme.
2. Relocation of Riverside One
2.1The Council owns in excess of 1,000 property assets and, next to staff, property is the Council’s largest single cost. Effective management is therefore essential if the Council is to fulfill its core objectives and provide good quality, value for money services.
2.2To ensure that the Council’s property assets contribute to its priorities, outcomes, objectives and key actions, as set out within the Council Plan, all properties are considered in the context of rationalisation.
2.3This report brings forward proposals to lease new premises in order to relocate the existing services provided at Riverside One, (Revenue and Benefits, Customer Contact, Housing Solutions and Client Financial Services) which will enable the building to be vacated, demolished and the Great Barrier Ditch to be restored.
2.4The Riverside One building is located within a conservation area and from a heritage perspective English Heritage, Fort Amherst Heritage Trust and the Council’s conservation and regeneration teams would like to see the building removed and the Great Barrier Ditch restored. The proposal forms part of a joint Heritage Lottery Fund bid by the Council and the Trust. If successful the scheme will continue the development at the Great Lines Heritage Park, and provide excellent linkages between the park and waterfront.
2.5The building is suffering from structural subsidence, which is such that its foundations will require underpinning within the next two years if it is to remain open and operational. Indications suggest the cost of such works will be in excess of £500,000 and are further complicated by the fact that the building is located within the area of a scheduled monument, as indicated on the attached plan edged in black. Should consent to such works be forthcoming it will certainly necessitate extensive and costly archeological investigations.
2.6The building also has a significant level of other required maintenance, which is estimated to be in the region of at least an additional £450,000. In particular, the building’s services are antiquated with both poor levels of insulation and an oil fired central heating system, which is both expensive to run and difficult to maintain. For example, the oil fill point is located on Dock Road itself, which due to traffic levels makes refueling particularly challenging.
2.7The layout of the building is also not well suited to the requirements of the service with a significant number of cellular spaces making it operationally cumbersome and unwelcoming for service users.
2.8As a consequence, coupled with the desire to demolish the building and restore the Great Barrier Ditch, the Cabinet, on 15 July 2014, considered a report which proposed that the services provided at the building are relocated and that the building is closed.
2.9At its meeting on 15 July 2014, the Cabinet agreed:
2.9.1 The Cabinet agreed to delegate authority to the Assistant Director of Legal and Corporate Services in consultation with the Portfolio Holder for Finance to acquire a lease of alternative premises and ancillary parking on the best terms reasonably obtainable.
2.9.2 The Cabinet recommended to Full Council that it makes an addition of £800,000 to the capital programme to fund the adaptation and fit-out of new premises, associated relocation costs and the demolition of the Riverside One building.
3. Strood Sports Centre
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of the Council's Petitions Schemea) The Council noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.