Resolved
The Cabinet noted the report. Reasons: When Cabinet agreed to establish the joint venture company it was also agreed that regular monitoring reports would be provided to Cabinet.
Cabinet noted this item on Tuesday 13 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet noted the report. Reasons: When Cabinet agreed to establish the joint venture company it was also agreed that regular monitoring reports would be provided to Cabinet.
This report outlines the Company’s achievements and performance up to the third quarter in its second year of trading and its plans for future growth and development.
1. Budget and Policy Framework
1.1In March 2013 Cabinet agreed for the joint venture company, Medway Norse, to be established for the provision of facilities management (FM) services from 1 June 2013. In 2014 the joint venture has also taken on responsibility for the grounds maintenance contract and for an initial phase of school transport for children with special educational needs attending three schools. Medway Norse is now responsible for activity amounting to just under £11m per annum.
2.1Medway Norse joint venture company was established to:
Provide services to the Council more efficiently to give better value for money Grow the business through taking on external contracts Increase employment opportunities for local people
2.2Medway Norse now provides services to the Council in three main areas – facilities management, grounds maintenance and SEN transport. 3. Review of the second year’s trading to date
Governance 3.1 The Company’s Board of Directors comprises three representatives from Norse Commercial Services and two from the Council. The Council’s representatives are Councillor Filmer (Chair of the Board and has a Council Policy veto) and Stephanie Goad, Assistant Director Communications, Performance and Partnerships. The Board is responsible for the performance of the joint venture overall.
3.2There is also an Operational Liaison Board, which consists of representatives from Medway Norse and nine representatives from the Council. This is supported by ongoing liaison between Medway Norse and the Corporate Client.
3.3Responsibility for the Corporate Client now lies with the Strategic Property and Energy team, managed by Nick Anthony. The role previously sat with the Category Management team to manage the transition and having completed that phase we have now moved to a business as usual model.
Summary of operations 3.4 Medway Norse has continued to make good progress and this quarter it has experienced growth across the board. Year-to-date the joint venture is 6% up on the budgeted target in total sales and 4% up on the targeted profit, which for the year is targeted to be £521,080. Under the terms of the joint venture agreement in Year 2 the Council will retain 66.6% of any profit at year-end.
3.5A key objective for Medway Norse in the first 16 months of operation has been to develop the business offering. This has been achieved through training and employment of key skills in order to offer an FM solution externally. Medway Norse within this short time span has grown teams of tradesmen covering: electrical, mechanical, carpentry and wet trades. Having developed the self-delivery approach, not only has this generated savings within the partnership it has also allowed the Company to develop a service offering, which can be traded externally. External trading has always been a key driver for the partnership and this will be the key focus for the forthcoming year now that the service offering has been developed.
3.6The self-delivery model has allowed the partnership to undertake works that were previously contracted out. Utilising this model the current self-delivery team have completed 5,220 jobs internally since commencement of the Joint Venture with a reduction in overall average value per job of £59.20 (figures to 31 October 2014), which has given direct savings of £309,024. This means Medway Norse has been able to deliver more jobs at lower cost, whist still generating a rebate to the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Medway Norse Six Monthly ReportReport | 88 KB | DownloadRead as text |
Follow Cabinet at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Sep 2026 | Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... | Approved | Open |
| 22 Sep 2026 | Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... | Approved | Open |
| 22 Sep 2026 | Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... | Noted | Open |
| 22 Sep 2026 | Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... | Noted | Open |
| 22 Sep 2026 | Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.