The Cabinet noted the spending forecasts summarised at Table 1 of the report. 15/2015 The Cabinet agreed the £1.0million virement requested in paragraph 6.1 of the report. 16/2015 The Cabinet recommended the new approvals set out in paragraph 6.2 of the report to Council. Reasons: Cabinet has the responsibility to ensure effective budgetary control to contain expenditure within the approved limits set by Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
2.1The approved capital programme for 2014/15 and future years is £86.8 million, representing both brought forward schemes and new approvals.
2.2This report consolidates the capital monitoring undertaken by each directorate and this is summarised in the appendix that details the individual schemes and their financial position. The ‘smiley’ attached to each scheme is indicative of the scheme progress as set out in 3.2 below. The notes in the main body of the report, below, represent a commentary on areas of concern or items of particular interest.
3. Progress
3.1Table 1 below summarises the current overall expenditure and the forecast position against the capital programme, representing a summary of the detailed information at Appendix 1, which includes the detailed narrative from project managers providing a more detailed explanation of the progress of each scheme against its plan. Table 1: Summary – capital spend and forecasts
spend 2014- Programme
March 2014
later years Approved
Spend to
Forecast
Forecast
Forecast Variance spend in Directorate
15 £’000 £’000 £’000 £’000 £’000 Children and Adult Services 166,258 131,918 22,770 12,502 932 Regeneration, Community 77,782 42,217 18,242 17,311 (12) and Culture Business Support 36,055 31,180 2,339 2,536 (0) Department Housing Revenue Account 35,088 23,890 6,483 4,405 (310) Member Priorities 842 247 530 40 (25) Public Health 200 0 4 296 100 TOTAL 316,225 229,452 50,368 37,090 685
3.2The Appendix utilises a ‘smiley face’ project monitoring system that indicates progress at a glance. With only a few exceptions, the relevant budget manager has provided the information in the progress fields of the report. The criteria for the ‘smiley’ rating is as follows:
Scheme progressing on time or within budget Scheme progressing on time but not within 5% of budget or scheme progressing on budget but not within expected timescales
Scheme neither progressing within expected timescales nor within 5% of budget.
4. Specific Scheme Monitoring Issues and Completions
4.1Children and Adults
4.1.1 The 2014/15 initial capital programme was funded as follows: Condition Programme - £2.5 million; Basic Need - £4.6 million, covering 2015/16 and 2016/17; Adult Social Care - £547,000; Schools Devolved Formula Capital - £452,000. Universal Infant School Means - £567,000 2013/14 carry forward amounted to £23.4 million £2.0 million DSG Reserves.
4.1.2 The following schemes have been approved following round one and have been added to the capital programme: Expansion of the Old Vicarage £120,000 YOT move to Strood Youth Centre £50,000. 4.1.3 This has resulted in a Children and Adult Services 2014/15 capital programme of £34.3 million.
4.1.4 The directorate is forecasting total capital expenditure of £35.3 million of which £25.5 million is anticipated to be spent this year and £9.8 million in future years. This represents an overspend of just over £1.0 million.
4.1.5 The academies programme is forecasting an overspend of almost £1.0 million due to the removal costs of additional asbestos found at Brompton, Strood and Bishop of Rochester Academies that the council has accepted liability for. This follows a successful legal challenge against the contractor, BAM, which resulted in liability for the additional costs being split between the council and the contractor.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.