69/2018 The Cabinet recommended to Full Council the addition to the capital programme of a facility for £120 million over the next 5 years to enable development. 70/2018 The Cabinet approved the amendments to the Medway Development Company Ltd (MDC) governance structure, as outlined in option 1 of the report and Exempt Appendix 1, to reflect the Teckal test and noted that Cabinet previously delegated authority to the Chief Legal Officer, in consultation with the Leader, to finalise the Articles of Association (decision no. 92/2017) and that Cabinet now approved the form of Articles of Association similar to that of MCG Ltd, as set out in Appendix 1 to the report. 71/2018 The Cabinet noted the draft Business Plan as set out in Exempt Appendix 2 to the report and agreed to delegate authority to the Chief Legal Officer, in consultation with the Leader, to approve the final version of the Business Plan . 72/2018 The Cabinet approved the amendments to the Employee Delegation Scheme as set out in paragraphs 8.3.1 and 9.2.2 of the report. Reasons: To enhance the generation of new and alternative investment returns for the Council and to deliver housing units principally in Medway .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report updates Cabinet as shareholder about the need for capital funding to be added to the Council’s capital programme and proposals to amend the governance arrangements for Medway Development Company Ltd (MDC) in order to take advantage of tax efficiencies in the development of property.
1. Budget and Policy Framework
1.1The responsibility for agreeing budgetary provision and additions to the Capital Programme is for Council.
1.2The responsibility for managing the Council’s land is a matter for Cabinet as is the provision and management of housing.
1.3Medway Council is the sole shareholder of MDC and changes to the company’s constitution must be agreed by Cabinet.
Background
2.1Cabinet approved the Business Case submitted at the 5 September 2017 meeting for the creation of a new company to be called Medway Development Company Limited.
2.2Cabinet agreed to delegate authority to the Chief Legal Officer, in consultation with the Leader, to finalise the Articles of Association in a form similar to those established for an independent, non Teckal company (decision no. 92/2017 refers). It was incorporated with the model Articles to enable an efficient set up.
2.3MDC was incorporated on 24 October 2017 and Councillor Howard Doe and Councillor Adrian Gulvin were appointed as directors. Additional directors Jonathan Sadler and Barbara Richardson have been recruited externally and are to be formally appointed to the Board by the Chief Executive of Medway Council in accordance with his delegated authority (decision no. 97/2017 refers).
2.4MDC has recruited a Head of Operations, Lewis Small, who is taking forward the initial projects identified in the Business Case presented to Cabinet. He has created a first draft Business Plan for the MDC Board at its inaugural meeting, to progress the first three schemes. A copy is attached as exempt Appendix 2. There are nine other schemes identified. Capital funding is now needed for a variety of enabling activity such as producing architect’s drawings for planning applications. The Business Case estimates that over an initial five year period, funding of £120 million will be needed to unlock twelve Council owned sites. This investment represents capital expenditure and it is proposed to add this to the capital programme, to be funded from borrowing in advance of the future receipts generated.
2.5The Board has reviewed the Business Case agreed by Cabinet on 05 September 2017 and considers that to enable the generation of the maximum return for the Council whilst delivering housing units principally in Medway, an alternative Teckal structure for the company should be pursued which is more tax efficient.
2.6The Public Contract Regulations 2015 codify the so-called “Teckal Exemption” at regulation 12 allowing public to public contracts without procurement where three criteria are met:
1. The contracting authority exercises over the body control which is similar to that which it exercises over its own departments.
2. More than 80% of the activities of the body are carried out in the performance of the tasks entrusted to it by the controlling contracting authority.
3. There is no direct private capital participation in the controlled body.
2.7Criteria 1 is met because the Council has appointed Directors to the Board of MDC. Criteria 2 is met since MDC will carry out 80%+ of its activities for Medway Council. Criteria 3 is met as the capital funding will be from the Council. 3. Options for the amending MDC’s constitution
Option 1: To agree a change to the governance structure of the company as follows:
3.1.1 This option is recommended. Amend MDC’s Articles of Association and governance arrangements to reflect the Teckal test:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.