59/2018 The Cabinet agreed to recommend to Full Council on 26 April 2018 the addition of this project, as set out in section 2 of the report, to the Capital Programme, subject to approval from the South East Local Enterprise Partnership (SELEP) for the funding. Reasons: Additions to the Capital Programme are a matter for Full Council.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report will set out a current Growing Places Fund (GPF) bid to bring the Fitted Rigging House at Chatham Historic Dockyard into full use. The report will ask Cabinet to recommend to Full Council on 26 April 2018 the addition of the project to the Capital Programme, subject to approval from the South East Local Enterprise Partnership (SELEP) for the funding.
1. Budget and Policy Framework
1.1It is the responsibility of Cabinet to ensure that expenditure for each capital scheme remains within the budget approved by the Council but it remains the responsibility of Council to approve schemes for inclusion in the capital programme.
1.2As this scheme is being delivered by the Chatham Historic Dockyard Trust (CHDT) the responsibility for remaining within the budget falls to CHDT and as such the Council assumes no liability for the budgeting of the works.
2. Fitted Rigging House – Business Space Development
2.1The Fitted Rigging House Project converts a large, Grade 1, former industrial building into office and public benefit spaces initially providing a base for 3 organisations employing over 350 people. The project also frees up space to create a postgraduate study facility elsewhere onsite for the University of Kent’s Business School. 2.2 The project forms a critical element of Chatham Historic Dockyard Trust’s corporate plan based on a strategy of “preservation through re-use” that generates income to maintain the 80 acre heritage site and maintain its educational purposes, both at the core of Medway’s wider regeneration strategy.
2.3Further to these initial ambitions the project also provides expansion space for the future, which has the potential to enable the creation of a high tech cluster based on the work of one core tenant and pre-existing creative industries concentrated on the site.
2.4The total cost of the project to CHDT is £8,400,000. CHDT have secured £7,600,000 from other funding pots and are seeking the remaining £800,000 from the Growing Places Fund. CHDT submitted a final Business Case to the South East Local Enterprise Partnership (SELEP) at the beginning of March 2018. Subject to the Independent Technical Evaluator being satisfied with the Business Case it will be presented to SELEP Accountability Board for a funding decision on 27 April.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.