Resolved
The Committee noted the report and expressed their appreciation to staff for the work undertaken.
Planning Committee noted this item on Wednesday 29 August 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee noted the report and expressed their appreciation to staff for the work undertaken.
This report is presented quarterly to committee informing Members on current Planning performance and the Local Plan.
1. Budget and Policy Framework
1.1There are no budget and policy framework decisions arising directly from this report. This is an information item for the Planning Committee.
2.1Performance relating to the processing of planning applications is collected as National Indicator 157. The NI157 targets are:
Major developments: to determine 60% of applications within 13 weeks.
Minor Developments: to determine 70% of applications within 8 weeks.
Other Developments: to determine 70% of applications within 8 weeks.
3. Performance
3.1See attached charts in Appendices A to G for performance concerning the processing of planning applications, benchmarking, appeals, enforcement activity, Tree Preservation applications and a breakdown of complaints received. 3.2 During the period 1 April to 30 June 2018 the authority received 391 planning applications; this is compared to 389 for the same period in 2017. For the year 2017/18 the authority received 1546 applications, this compares to 1543 in 2016/17.
Performance for applications is split between those subject to an extension of time and those not. An extension of time can be in the form of a Planning Performance Agreement (PPA) or a Planning Extension Agreement (PEA).
Performance for major applications not subject to an extension of time during the quarter is 88.89%. Applications subject to an extension of time is 100%. This provides a combined percentage of 93.33% of major applications determined within 13 weeks or within the agreed timeframe. This is against a target of 60%.
Performance for minor applications not subject to an extension of time during the quarter is 76.92%. Applications subject to an extension of time is 62.50%. This provides a combined percentage of 71.43% of minor applications determined within 8 weeks or within the agreed timeframe. This is against a target of 70%.
Performance for other applications not subject to an extension of time during the quarter is 95.51%. Applications subject to an extension of time is 70%. This provides a combined percentage of 93.73% of other applications determined within 8 weeks or within the agreed timeframe. This is against a target of 70%.
Appendix A, figure 2, 3 and 4 shows performance against target (including those not subject and those subject to an extension of time) for majors, minor and other applications for the year.
Comparing performance against the latest data available nationally (January to March 2018), Medway performed above the national average for all types of applications (see Appendix B).
Pressure on officer resources has been carefully managed in order to meet national performance targets. This pressure continues and with the added pressure of annual leave, maternity leave and vacancies, the workload will need to be carefully managed if performance is to continue to be maintained.
3.3During the quarter 50 applications with Planning Extension Agreements were decided, this compares to 69 in the previous quarter (see Appendix C). Comparing performance against national data for the period January to March 2018, 89% of applications were determined within the agreed extended timeframe nationally compared to 70% by Medway. 3.4 2 Planning Performance Agreements (PPA’s) were entered into during the quarter. These related to:
259-261 High Street, Rochester Land at White House Farm, Stoke Road, Hoo St Werburgh
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Performance Report for the period 1 April: 30 June 2018Report | 449 KB | DownloadRead as text |
Follow Planning Committee at Medway and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Sep 2026 | Planning application - MC/26/0561 St John Fisher School, 79 Maidstone Road, Chatham, Medway ME4 6DPApproved subject to: A. Subject to the applicant entering into a legal agreement under the terms of Section 106 of th... | Approved | Open |
| 23 Sep 2026 | National Scheme of Delegation for Planning ApplicationsThe Committee noted the proposed recommendations being submitted to full Council on 15 October 2026 and referred to t... | Noted | Open |
| 26 Aug 2026 | Planning application - MC/26/0194 Land at Buckland Road and Higham Road, Cliffe, Rochester KentRefused for the reasons 1 to 5 as set out in the report and amended in the supplementary agenda advice sheet, and for... | Refused | Open |
| 26 Aug 2026 | Planning application - MC/26/1032 4 Barnsole Road, Gillingham, Medway ME7 4DJRefused for the reasons 1 to 4 as set out in the report and the supplementary agenda advice sheet with reason 2, 3 an... | Refused | Open |
| 26 Aug 2026 | Planning application - MC/22/0486 Land at Longhill Avenue, Gillingham, Chatham, Medway ME5 7ATApproved subject to: A. Subject to the applicant entering into a legal agreement under the terms of Section 106 of th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.