The Cabinet noted the officer responses to the requests made to officers by the Business Support Overview and Scrutiny Committee, as set out in paragraphs 3.2 to 3.4 of the report. 79/2023 Noting the officer comments set out at paragraphs 3.1 to 3.6.2 of the report, the Cabinet agreed the following requests as made by the Business Support Overview and Scrutiny Committee: i) A commitment to revisiting the consultation process if changes are proposed. ii) Provision of a refreshed governance structure for the project going forward to include the relevant community groups such as councillors, parish councillors and other community groups. Reasons: The Business Support Overview and Scrutiny Committee has made this recommendation to Cabinet in accordance with its entitlement, under the Council’s Constitution, to make recommendations to Cabinet arising from the outcome of the scrutiny process (Constitution – Articles of the Constitution - Chapter 2, Article 6, Paragraph 6.4). Cabinet is, therefore, was required to consider its response.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report sets out a referral from the Business Support Overview and Scrutiny Committee held on 30 March 2023. This related to the Housing Infrastructure Fund, in the light of the decision to pause the rail element of the HIF scheme and concerns over the related Grampian agreement currently in place for the housing developments, as discussed during consideration of agenda item No.7, Capital Budget Monitoring - Round 3 2022/23 (Minute No. 710 refers).
1. Budget and policy framework
1.1Overview and Scrutiny Committees may make recommendations to the Cabinet arising from the outcome of the scrutiny process (Constitution – Articles of the Constitution - Chapter 2, Article 6, Paragraph 6.4).
1.2At its meeting held on 30 March 2023, the Business Support Overview and Scrutiny Committee agreed to make recommendations to Cabinet, as detailed in section 2 of this report.
Background
Business Support Overview and Scrutiny Committee – 30 March 2023
2.1The minutes of the Committee’s discussion relating to the Housing Infrastructure Fund are as follows. This includes a request for information to be provided by officers and a referral to the Cabinet, as set out at paragraph 2.8.
2.2Housing Infrastructure Fund (HIF) rail element – reference was made to the reports that the rail element of the project had been paused and it was asked whether this would mean the Council would have to return the circa £62m that was aligned with that element of the project. Officers confirmed that, as could be seen across all projects, the inflation pressures had negatively impacted on the HIF project and it would no longer be possible to deliver the original specification within the £170m budget. The initial action taken had been to approach Homes England (HE) to request the additional funding required. However, HE had rejected this and requested the Council to review its proposals to deliver the project within the £170m budget. Therefore, the rail element of the project had been paused and officers were working on alternative proposals. Criticism was made as to why it had taken so long to establish that the rail element of the project was unaffordable when this had been a concern raised by some from the beginning.
2.3HIF and member oversight – concern was raised about a lack of member oversight and public transparency which the Committee considered had been missing. Officers explained that the Cabinet had set up a Cabinet Advisory Group to monitor the project and that Cabinet had also delegated authority of some decisions in relation to HIF to officers, in consultation with Portfolio Holders, and undertook to circulate these to the Committee. It was reiterated that no decisions had been made in relation to the revised plans and that once proposals were at a point which would be acceptable to HE, they would be presented to the Cabinet for approval.
2.4HIF spending deadline – reference was made to the delays to the project due to the redesigns required and how this could impact on the deadline to spend the funding by 2025 and whether the Council would be successful in negotiating a further extension.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.