168/2013 The Cabinet approved the Business Case, which had been based on the initial options appraisal and allow this project to proceed for more detailed design work on the preferred option, as set out in paragraph 4.1 of the report . Reasons: Option 8 delivers the maximum compromise between budget availability and building content and provides best value for money. The cost estimates indicate that the preferred scheme, which will deliver the identified accommodation requirements, is the most cost effective solution. Accurate cost estimates will be developed during the detailed design stage and presented for approval at Gateway 1 stage. Every effort will be made to include additional elements identified during the discussions with the Headteacher and unit Staff prior to the tendering process.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks approval from Cabinet of the Business Case (OBC) for the expansion of Will Adams Pupil Referral Unit (PRU) and for permission to commence more detailed design works.
1. Budget and Policy Framework
1.1This project supports the Council’s School Organisation Plan 2011 – 2016, approved by Cabinet on 1 November 2011 (decision number 143/2011). The Council Plan 2013-2015 includes the following priority: Children and young people have the best start in life in Medway.
1.2Subject to the approval of the OBC and the recommendations in this report, officers will develop the design and report to Cabinet for approval in compliance with the Council’s procurement rules. This will then lead to Gateway 1, which will be undertaken in compliance with EU rules and Medway Council’s internal procurement processes and contract rules.
Background
2.1Will Adams PRU, Woodlands Road, Gillingham, currently have a roll of 40, (although from September the actual number on roll will be 43), based on 20 students in each Year Group (Year 11 & Y12). The PRU is currently geared to 6 rather than 8 students per class, giving a teaching accommodation need of 8 classrooms. 2.2 The Department for Education publishes guidance for all categories of Educational premises to identify expected standards know as Building Bulletins. Building Bulletin 77 sets out standards for PRUs and when compared to this the current accommodation is inadequate in that they are deficient in many areas:
The school only has 6 classroom spaces (which includes 1 classroom in the Youth Centre) – currently they lease 2 minibuses and use staff cars to take students off-site for alternative provision. IT, music and Art are delivered in the current classroom spaces rather than in specialist accommodation. The youth club hall is rented in order to deliver dining and hall activities. Visiting professionals have to use either; the reception area, corridor, Senco or Head teacher’s office for meetings. External spaces – no provision and currently use the Youth Club outside area. On-site storage is limited and they have to use a “shed” and off-site storage. The school rent 2 spaces from Woodlands Primary School for parking of the minibuses.
2.3The PRU has never benefitted from purpose built accommodation and the current provision is the result of various building modifications over the years. This also included swapping accommodation from Summit House to the back of Woodlands Youth Club.
2.4Ofsted has criticised the PRU and Local Authority for the inadequate provision, which prevents full curriculum entitlement and development. This leaves the PRU vulnerable to an Ofsted category of ‘special measures’.
2.5There is a severe pressure for places relating to the students excluded from mainstream secondary schools at Key Stage 4. As noted above the current facilities at Will Adams are currently deficient in a number of areas.
2.6The Outreach Centre, which is located very close to Will Adams, has been recently vacated, and there are proposals to relocate the Duke of Edinburgh occupants who currently use Summit House, which is adjacent to the Will Adams building. This gives us an opportunity to not only address the current deficiencies but also allow for an expansion, which will help to address the current pressure on places across Medway.
2.7In addition the transfer of part of the land to the rear of the site, previously the on-site playing field of Gillingham College, which closed in 2000, is proposed. This will provide a safe and secure route between the buildings and an outside space for the students, together with parking for the minibuses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.