10/2024 The Cabinet instructed officers to review a potential change of approach to deliver the re development of the Debenhams building, by repaying the capital development cost with future revenue income, as opposed to only reviewing options for repayment via future capital receipts. 11/2024 The Cabinet recommended to full Council, additions to the Capital Programme, of £2,752,000 for the delivery of the Healthy Living Centre in the Pentagon Centre, noting this figure would be reimbursed by the NHS and would be subject to NHS final approvals and S106 contributions. 12/2024 The Cabinet approved the virement of £869,250 in relation to Wilkinsons unit, from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre. 13/2024 The Cabinet recommended to full Council the following virements from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre. A. £1,245,900 to deliver the Healthy Living Centre B. £1,811,366 to deliver the Innovation Hub. Reasons: Officers will be able to explore alternative potential options which could result in repayment of the capital borrowing via future revenue income, as opposed to capital receipts. The final business case for the redevelopment of Debenhams will require further Cabinet approval. Additional funding is required, following the design progression and subsequent cost inflation to build out the Healthy Living Centre in the Pentagon Centre. The additional funding will be reimbursed by the NHS. Lastly, the virements will not impact project delivery, with no change to the funding source/project budgets but will improve reporting clarification. The virements are in line with the decision approved by Council, that a proportion of the underspend on the purchase of the Pentagon Shopping Centre would be utilised for future capital works at the Pentagon Centre. (Minute no.713D, 20 February 2020).
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 16 January 2024 Project Update – Pentagon Shopping Centre and Former Debenhams Building Portfolio Holder: Councillor Naushabah Khan, Portfolio Holder for Housing and Property
Report from: Sunny Ee, Assistant Director Regeneration
Summary This report is a project update paper which provides options being considered for the redevelopment of Debenhams and also requests capital additions to deliver the Healthy Living Centre in the Pentagon Centre, a cost which will be reimbursed by the NHS. Finally, the report also seeks approval for virements for reporting clarity purposes.
1. Recommendations 1.1 Cabinet is asked to instruct officers to review a potential change of approach to deliver the re development of the Debenhams building, by repaying the capital development cost with future revenue income, as opposed to only reviewing options for repayment via future capital receipts.
1.2Cabinet is asked to recommend to full Council, additions to the Capital Programme, of £2,752,000 for the delivery of the Healthy Living Centre in the Pentagon Centre, noting this figure will be reimbursed by the NHS and is subject to NHS final approvals and S106 contributions.
1.3Cabinet is asked to approve the virement of £869,250 in relation to Wilkinsons unit, from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre.
1.4Cabinet is asked to recommend to full Council the following virements from the existing Pentagon Centre future works budget, to deliver the diversification of the first floor of the Pentagon Centre. A. £1,245,900 to deliver the Healthy Living Centre B. £1,811,366 to deliver the Innovation Hub 2. Suggested reasons for decisions 2.1 Officers will be able to explore alternative potential options which could result in repayment of the capital borrowing via future revenue income, as opposed to capital receipts. The final business case for the redevelopment of Debenhams will require further Cabinet approval.
2.2Additional funding is required, following the design progression and subsequent cost inflation to build out the Healthy Living Centre in the Pentagon Centre. The additional funding will be reimbursed by the NHS.
2.3Lastly, the virements will not impact project delivery, with no change to the funding source/project budgets but will improve reporting clarification. The virements are in line with the decision approved by Council, that a proportion of the underspend on the purchase of the Pentagon Shopping Centre would be utilised for future capital works at the Pentagon Centre. (Minute no.713D, 20 February 2020).
3. Budget and policy framework 3.1 In February 2019, Cabinet recommended to Full Council the acquisition of the head lease of the Pentagon Centre and in so doing granted delegated authority to carry out the re-configuration and improvement works to the Pentagon Centre and to manage and let the centre (decision no. 32/2019).
3.2On 21 February 2019, the Council added £45 million to the capital programme to fund the acquisition of the Pentagon Centre.
3.3In 2020 Council approved the virement of the underspend following the acquisition of the Pentagon Centre to a new capital scheme for future capital works at the Pentagon Centre (Minute no.713D, Full Council 20 February 2020).
3.4Full Council in Feb 2022 added £10,348,000 to the Capital Programme to fund the Healthy Living Centre (HLC), on the provision that the NHS would reimburse the full amount.
3.5The Council was awarded c.£9.5m grant funding from the Future High Street Fund (FHSF), to assist with the delivery of the HLC and Innovation Hub on the first floor of the Pentagon Centre, the acquisition and redevelopment of the ground floor of the former Debenhams project, along with other regeneration projects in the heart of Chatham. The £9,497,720 was added to the Capital Programme in 18 February 2021.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.