Gateway 1 / Gateway 3 Project Commencement / Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund Works
AgreedExecutive1 paper
Cabinet agreed this item on Tuesday 16 January 2024. Below is the council's own wording, with the papers it was decided on.
14/2024 The Cabinet: i) agreed the preferred option of a direct award to Medway Development Company. ii) agreed the award of services/works for the cost. Reasons: The appointment of MDC as Project Manager and Contractor to deliver the enabling works for the OPE BLRF, will ensure the project is completed and the grant funding is utilised .
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks to detail the options relating to the delivery of the One Public Estates (OPE) Brownfield Land Release Fund (BLRF) enabling works Contract, with subsequent information relating to directly awarding a contract thereafter.
Recommendations
1.1The Cabinet is requested to:
i) agree the preferred option of a direct award as identified in paragraph 6.3.1. ii) agree the award of services/works for the cost.
2. Suggested reasons for decision
2.1The appointment of MDC as Project Manger and Contractor to deliver the enabling works for the OPE BLRF, will ensure the project is completed and the grant funding is utilised. 3. Background Information
3.1Budget and Policy Framework
3.1.1. Medway Council has been awarded £1.7m ring fenced grant funding from One Public Estates Brownfield Release Fund to deliver enabling works at the former Strood Civic Site, to facilitate residential delivery of a minimum of 171 residential units.
3.1.2. The ring fenced grant funding has been added to the capital programme.
3.1.3. Cabinet approval is required for direct awards over £1m and high profile projects.
3.2Background Information and Procurement Deliverables
3.2.1. The former Strood Civic site is high profile and will be the first phase of residential led redevelopment along Strood Waterfront. The site benefits from its highly accessible location with prestigious views across the river to Rochester Castle and Cathedral and will be the flagship site of the Strood’s waterfront regeneration.
3.2.2. The previous procurement activity for this site was unsuccessful due to the forecast values for the site not being realised. Further investment in the site will thereby improve the site’s potential capital receipt.
3.2.3. It is proposed that Medway Development Company (MDC) is contracted to deliver these works to bring forward the site. MDC will be appointed in the capacity of Project Manager and Contractor, utilising the teckal exemption, as this is a direct award over £1 million and a high profile site it requires Cabinet approval.
3.2.4. The enabling works focus on the main access road into the site, primarily addressing the level differences, following the land raising for the flood defence works and removing below ground obstructions and installing drainage as well as rediverting of utilities. The funding requirements stipulate that a contractor needs to be appointed by March 24.
3.3Urgency of Report
3.3.1. The funding requirements from OPE stipulate that a contractor needs to be appointed by March 24. This requires MDC to undertake the project management and contractor role to undertake a procurement exercise to appoint the enabling works contractor.
3.4Parent Company Guarantee/Performance Bond Required
3.4.1. This will be waived as the subsequent works contracts will have suitable retention clauses. 4. Procurement Dependencies and Obligations
4.1Project Dependency
4.1.1. The £1.7m grant funding from the OPE BLRF for enabling works for the future delivery of a minimum of 171 residential units. The land release must be completed by March 2027, Land release is defined in the grant agreement and therefore must comply with that definition, a future procurement exercise may be required depending on the land release mechanism chosen.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gateway 1 / Gateway 3 Project Commencement / Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund WorksReport
10Gateway 1 / Gateway 3 Project Commencement / Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund WorksThis decision
Gateway 1 / Gateway 3 Project Commencement / Options Appraisal with Subsequent Direct Award to Deliver the One Public Estates Brownfield Land Release Fund WorksThis decision
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.