81/2024 The Cabinet agreed to award the building contract for the Healthy Living Centre to Bauvill Ltd as they had been evaluated as the most economically advantageous tender against the Council’s award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix. The Cabinet noted that the formal award to the preferred contractor would not be issued until such time as the NHS had fully committed and signed the legal agreement. 82/2024 The Cabinet agreed the waiver of a Performance Company Guarantee (PCG) or Performance Bond, as set out at 3.3.1 of the report. 83/2024 The Cabinet agreed that recommendations 1.1 and 1.3 [decision nos. 81/2024 and 82/2024] were urgent and therefore should not be subject to call in, as set out in 3.1.15 of the report. Reasons: Bauvill Ltd had a successful track record of delivering healthcare projects. Most recently delivering a health centre facility in Ashford (£13.5million), as well as a Maritime Hospital D&B project (£8million), and separately experience with BREEAM and working in live environments. Bauvill Ltd had been evaluated as the most economically advantageous tender against the Council’s award criteria.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
This report seeks Cabinet approval to award the procurement of the Building Contractor for the Healthy Living Centre Contract. 1. Recommendations 1.1 It is recommended that the Cabinet agrees to award the building contract for the Healthy Living Centre to the organisation named in 3.2 of the Exempt Appendix as they have been evaluated as the most economically advantageous tender against the Council’s award criteria as per the evaluation spreadsheet contained within 3.1 of the Exempt Appendix.
1.2The Cabinet is asked to note that the formal award to the preferred contractor will not be issued until such time as the NHS have fully committed and signed the legal agreement.
1.3The Cabinet is asked to agree the waiver of a Performance Company Guarantee (PCG) or Performance Bond, as set out at 3.3.1 of the report.
1.4The Cabinet is asked to agree that recommendations 1.1 and 1.3 are urgent and therefore should not be subject to call in, as set out in 3.1.15 of the report.
2. Suggested reasons for decisions
2.1The proposed contractor named in the Exempt Appendix has a successful track record of delivering healthcare projects. Most recently delivering a health centre facility in Ashford (£13.5million), as well as a Maritime Hospital D&B project (£8million), and separately experience with BREEAM and working in live environments.
2.2The proposed contractor has been evaluated as the most economically advantageous tender against the Council’s award criteria.
3. Background Information 3.1. Budget and Policy Framework
3.1.1 The Council acquired the Pentagon Centre in April 2019. This was a strategic decision to regenerate the town centre while also enabling Mountbatten House to be utilised for future redevelopment, further aiding the regeneration of the town centre. It was acknowledged that whilst the ground floor was trading well and returning a good net income, the first floor required investment to secure a blue-chip tenant, in order to cover rates and service charges and also generate a reliable income.
3.1.2 Various options have been considered for the redevelopment of the first floor, however most would be risky for the Council, as it would need to spend a significant amount of capital making the first floor suitable for a given private sector use, with the risk that the tenant of this area may then default and no new occupier found. 3.1.3 The favoured option for development of the first floor is for it to be used as:
• An NHS Healthy Living Centre (HLC), this will provide a much- needed medical facility in Chatham, as well as bring in rental income for the council and reduce void costs. • An Innovation Hub, will primarily be funded from the Future High Street Fund (FHSF), • A Pharmacy letting to the private sector, this will only happen if the letting to the NHS goes ahead.
3.1.4 A flagship Healthy Living Centre will integrate key community health services, the Primary Care Team, additional General Practitioner capacity and consultant specialists in a visible, highly accessible location, supporting town centre diversification and improved health outcomes.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.