74/2024 The Cabinet requested that officers review the Asset Management Strategy. 75/2024 The Cabinet instructed that following a review of the Asset Management Strategy, officers would report back to Regeneration, Culture and Environment Overview and Scrutiny Committee with an update and action plan for corporate buildings. The Cabinet noted that the revised Asset Management Strategy and action plan would be reported back to the Cabinet for approval, having been considered by the Regeneration, Culture and Environment Overview and Scrutiny Committee as pre-decision scrutiny. Reasons: The Regeneration, Culture and Environment Overview and Scrutiny Committee has made these recommendations to Cabinet in accordance with its entitlement, under the Council’s Constitution, to make recommendations to Cabinet arising from the outcome of the scrutiny process (Constitution – Articles of the Constitution – Chapter 2, Article 6, Paragraph 6.4). Cabinet was, therefore required to consider its response.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 30 April 2024 Referral from the Regeneration, Culture and Environment Overview and Scrutiny Committee – Asset Management Strategy Portfolio Holder: Councillor Naushabah Khan, Portfolio Holder for Housing and Property
Summary This report sets out a referral from the Regeneration, Culture and Environment Overview and Scrutiny Committee with regard to the Corporate Building Survey Results Report that was considered by the Committee on 28 February 2024.
The Committee recommended to Cabinet that they ask officers to review their Asset Management Strategy for corporate buildings and provide an update and action plan at a future Overview and Scrutiny Committee.
1. Recommendations 1.1. The Cabinet is asked to consider the following recommendation from the Regeneration, Culture and Environment Overview and Scrutiny Committee and agree a way forward.
1.2It be recommended to Cabinet that:
a) Officers be requested to review the asset management strategy
b) Following a review of the Asset Management Strategy officers are instructed to report back to Regeneration, Culture and Environment Overview and Scrutiny Committee with an update and action plan for corporate buildings.
1.3The Cabinet is also recommended to note that the revised Asset Management Strategy and action plan will be reported back to the Cabinet for approval, having been considered by the Regeneration, Culture and Environment Overview and Scrutiny Committee as pre-decision scrutiny. 2. Suggested reasons for decisions 2.1. The Regeneration, Culture and Environment Overview and Scrutiny Committee has made these recommendations to Cabinet in accordance with its entitlement, under the Council’s Constitution, to make recommendations to Cabinet arising from the outcome of the scrutiny process (Constitution – Articles of the Constitution – Chapter 2, Article 6, Paragraph 6.4). Cabinet is, therefore required to consider its response.
3. Budget and policy framework 3.1. Overview and Scrutiny Committees may make recommendations to the Cabinet arising from the outcome of the scrutiny process (Constitution – Articles of the Constitution – Chapter 2, Article 6, Paragraph 6.4).
3.2At the meeting held on 28 February 2024, the Regeneration, Culture and Environment Overview and Scrutiny Committee agreed to make recommendations to Cabinet, as set out in section 4 of the report.
4. Background 4.1. Regeneration, Culture and Environment Overview and Scrutiny Committee 28 February 2024 – Corporate Building Survey Results
4.2The Committee received a report regarding the outcome of the corporate building that outlined the required budgets for Building Repairs and Maintenance Fund (BRMF) for the next 5-year cycle (2023-2028) to ensure Medway Council corporate estate (which consists of over 120 properties) is safe, warm and dry for staff, visitors and contractors.
4.3A BRMF survey had been conducted and the results provided details of costs to fully maintain the corporate portfolio, which amount to £23,963,400 (with inflation and project risk included) for the 5 years. To carry out the essential works for health & safety/major repairs/major lifecycle repairs across the corporate portfolio, the cost is £15,484,174.00 (with inflation and project risk included).
4.4The Committee were informed that all options were being looked at with the Transformation Team including whether it would be more financially viable to dispose of corporate buildings, subject to appropriate governance tests.
4.5Members were keen to ensure that the deficit would be more closely monitored in future alongside robust action planning to address the shortfall and its impact.
4.6The Committee:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.