Authority Monitoring Report and Infrastructure Funding Statement
ApprovedExecutive3 papers
AI summaryMedway Cabinet approved publication of the Authority Monitoring Report 2024/25 and Infrastructure Funding Statement 2024/25, making development and developer contribution information public. [D][P43] The statement records £21,739,839.14 retained for infrastructure projects at the end of the reported year. [6.9]
What happens nextPublish both 2024/25 reports [D]Publication will inform the public and planning system users. [P43]
Who it affectsServices and infrastructure [4.5]Contributions support education, affordable housing, waste, greenspace, leisure and transport. [4.5]
What was decided
Cabinet decision 182/2025 approved publication of the Authority Monitoring Report 2024/25, set out in Appendix 1. Report P53
Cabinet decision 183/2025 approved publication of the Infrastructure Funding Statement 2024/25, set out in Appendix 2. Report P54
Why
Publication meets the duty to compile and publish a planning monitoring report. Report P7
Publication meets the requirement to publish an Infrastructure Funding Statement every year. Report 2.2, P20
What happens next
Publish both approved reports for public and planning system use. Report P43
Continue annual publication of the monitoring report and funding statement. Report P11, 4.6
Add the Local Aggregates Assessment to Volume 2, the detailed data volume, once the South East England Aggregates Working Party approves it. Report P23
The money
£21,739,839.14 S106 contributions retained for infrastructure projects at the end of the reported year. Report 6.9
£4,971,854.48 Total received from planning obligations during the reported year. Report 6.9
£7,389,786.85 Total agreed under planning obligations entered into during the reported year. Report 6.9
£2,658,349.76 Total spent from planning obligations during the reported year. Report 6.9
£293,838 Average Medway house price following the 2023/24 dip. Report 6.2
£297,382 Average Medway house price level seen in 2022/23. Report 6.2
Options considered
Chosen: Publish the Authority Monitoring Report annually. This is an appropriate way to publish current development information and report progress against the Local Development Scheme. Report P20
Chosen: Publish the Infrastructure Funding Statement annually. The Council must publish it annually, and Government has specified the data standard, with limited options for publication and content. Report P20
Implications
Financial: Approval of the Authority Monitoring Report has no budget or financial implications. Report 3.2, P48
Financial: Developer contributions provide income for upgrading services in response to development, and the statement was produced using Planning Service resources. Report 10.2
Legal: The publications fulfil the planning monitoring and annual Infrastructure Funding Statement requirements, and the Authority Monitoring Report has no legal implications. Report P50, 2.2
Risk: Developer contribution data are estimates at a point in time and can change if development does not proceed or agreements are revised. Report 6.11
Risk: If S106 funds are not spent as specified and within the required timescales, developers could request a return with added interest. Report 7.4
Climate: Developer funded projects include nature conservation, recycling services and sustainable transport, which support climate change mitigation. Report 9.5
Equalities: Medway Local Plan preparation includes a Sustainability Appraisal and a Diversity Impact Assessment. Report 6.14
Other: The Authority Monitoring Report gives context to Local Plan preparation and supports ongoing assessment of the Council's wider objectives. Report 6.14
Who and where
Medway Council services Report 4.5
Developers Report 4.5
NHS Kent & Medway Integrated Care Board Report 4.5
Medway residents Report P37
The public Report P43
People using the planning system Report P43
External organisations and potential investors Report 4.2
The planning and development sector Report 4.2
Timeline
1 April 2024 to 31 March 2025: The Authority Monitoring Report covered this period. Report 4.2
2024/25: Housebuilding was 634, and developer contribution activity was reported. Report 6.2, 6.9
each December: The Council follows an annual Authority Monitoring Report publication timetable. Report P11
March 2025: The Local Cycling and Walking Infrastructure Plan was adopted. Report 9.4
16 December 2025: Cabinet approved publication of both 2024/25 reports. Report P1
Plain English for the jargon
Authority Monitoring Report: Annual assessment of development trends and wider social, economic and environmental indicators, plus progress on preparing the new Medway Local Plan. [P3][4.3]
Infrastructure Funding Statement: Annual statement of developer contributions received, spent, agreed and proposed for future infrastructure provision. [P4][4.6][P19]
S106 agreement: Planning obligation used to secure developer contributions for infrastructure and services. [4.4][4.5]
Developer contributions: Money collected through S106, the Community Infrastructure Levy or other contribution routes. [4.6]
Local Development Scheme: Programme for Local Plan preparation and review. [4.3]
Medway Local Plan: Main part of the statutory development plan and part of the Council's Policy Framework. [3.2]
Local Aggregates Assessment: Assessment of mineral aggregate supply from land won and imported sources in Medway. [P23]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
182/2025 The Cabinet approved publication of the Authority Monitoring Report 2024/25, as set out at Appendix 1 to the report. 183/2025 The Cabinet approved publication of the Infrastructure Funding Statement 2024/25, as set out at Appendix 2 to the report. Reasons: To comply with the duty to compile and publish a planning monitoring report. To satisfy the requirement to annually publish an Infrastructure Funding Statement.
Word for word from the decision Medway published for this meeting.Source: democracy.medway.gov.uk
Cabinet 16 December 2025 Authority Monitoring Report and Infrastructure Funding Statement Portfolio Holder: Councillor Simon Curry, Portfolio Holder for Climate Change and Strategic Regeneration
Report from: Adam Bryan, Director of Place
Authors: Dave Harris, Chief Planning Officer Samantha Beatty, Senior Planner Monitoring and Data Rachel Flintoft, Section 106 Officer Summary This report concerns monitoring information prepared by the Planning Service to meet statutory requirements for publishing data on development and infrastructure. It presents the annual Authority Monitoring Report, which provides an assessment of development trends and wider social, economic and environmental indicators, together with progress on the preparation of the new Medway Local Plan. A key monitoring measure is the annual level of housebuilding, which this year 2024/25 fell from the highs of the last few years to 634, a fall which is consistent elsewhere both regionally and nationally.
The report also presents the Infrastructure Funding Statement, which sets out details of funding agreed, received and spent through developer contributions, and proposed spend on infrastructure.
1. Recommendations 1.1. The Cabinet is requested to approve publication of the Authority Monitoring Report 2024/25, as set out at Appendix 1 to the report.
1.2The Cabinet is requested to approve publication of the Infrastructure Funding Statement 2024/25, as set out at Appendix 2 to the report.
2. Suggested reasons for decision(s) 2.1. To comply with the duty to compile and publish a planning monitoring report.
2.2To satisfy the requirement to annually publish an Infrastructure Funding Statement. 3. Budget and policy framework 3.1. The Medway Local Plan forms the main part of the statutory development plan for the area and is part of the Council’s Policy Framework. The Planning and Compulsory Purchase Act, 2004 and The Town and Country Planning (Local Planning) (England) Regulations 2012 requires local planning authorities to publish Authority Monitoring Reports setting out development data and wider social, economic and environmental indicators, and to report progress on plan making as set out in the Local Development Scheme. There is also a requirement to report on Neighbourhood Development Orders/Plans and details of what co-operation has taken place with other planning authorities, county councils or a body/person prescribed under Section 33A of the Act.
3.2The Monitoring Report complies with the Policy Framework. Approval of publication of the Monitoring Report is a matter for Cabinet. It has no budget implications. The report is produced to meet statutory requirements for the local planning authority to publish information about development in the area and the implementation of the Local Plan.
3.3The Community Infrastructure Levy (Amendment) (England) (No.2) Regulations 2019 require the Council to prepare an Infrastructure Funding Statement. The Council collects developer contributions in line with planning legislation and the Medway Local Plan, 2003 and the supplementary planning document, Medway Guide to Developer Contributions and Obligations, 2018.
4. Background Authority Monitoring Report 4.1. The Planning Service has been compiling and publishing annual Monitoring Reports for the last 20 years, following the statutory requirement introduced in the Planning and Compulsory Purchase Act, 2004. The Council has adhered to a timetable for the publication of the Authority Monitoring Report on an annual basis each December. This provides a basis for comparison with previous years.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.