Provision for Gypsy and Traveller Accommodation

Noted Executive 5 papers

AI summaryMedway Cabinet backs £2.68m council-run Gypsy and Traveller site at Wigmore, with up to 8 pitches now and possible 6 more in a later phase.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedDevelop permanent council managed Gypsy and Traveller site
Money£2,684,000 capital additionFunded by prudential borrowing, recommended to Full Council
What happens nextRecommend to Full CouncilTo add £2,684,000 to Capital Programme
Who it affectsGypsy and Traveller households in MedwayPlus current occupants of the Wigmore site

What was decided

Cabinet noted the work to identify additional options for Gypsy and Traveller sites, to give greater certainty the Local Plan will meet needs. Report 1.2

Cabinet agreed to proceed with Option 3 for the Wigmore Site: a permanent, council managed site for 10 touring caravans over 8 pitches, with approval to explore a second phase on adjacent land adding 6 pitches. Report 1.2, 5.4

Cabinet agreed to recommend to Full Council an addition of £2,684,000 to the Capital Programme, funded by prudential borrowing, to deliver the initial proposals in Option 3. Report 1.3

Why

The submission version of the Medway Local Plan 2041 does not meet full Gypsy and Traveller and Travelling Showpeople needs, and Plan inspectors have raised concerns about supply. Report P6, 4.7, 4.8, P27

The residual need in the Plan is 30 pitches for Gypsy and Traveller households and 8 plots for Travelling Showpeople; formalising Wigmore would help meet this and show a deliverable supply at examination. Report 4.7, P65, 6.2

The current informal use of the site has no permanent water, drainage, power, defined pitches or formal management, leaving the council in a reactive position. Report 4.3, 4.4, 4.5, 4.6

What happens next

Submit a new full planning application for the Wigmore site, following a pre-application and tender for architect and quantity surveyor. Report 5.10

Run a full tender to appoint a build contractor and Employers Agent, with construction of the first phase expected 12 to 18 months after that process starts; the current family group will be decanted during works. Report 5.11, 5.12

Planning Service will report back to Cabinet with further options from the Council land review and Call for Sites exercise, including any consultation on additional site allocations from mid-August to late September. Report 4.10, 5.20

The money

  • £2,684,000 Capital addition requested (worst case, assumes no grant funding) to deliver initial Option 3 proposals for the Wigmore site Report 1.3, 5.8, P41
  • £50,000 per year Ongoing Council costs if Option 1 (do nothing) is chosen and the site remains as is Report 5.8, P40
  • £24.00 per caravan per week Currently collected from occupants to cover rubbish collection and toilet facilities Report 4.3

Options considered

  • Rejected: Option 1: Do nothing, leave the site as it is. Does not meet identified need, has limited impact on Local Plan adoption, leaves the council in a reactive position with site safety and welfare concerns. Report 5.8, P40
  • Rejected: Option 2: Develop and improve the site within its current boundary to provide 8 pitches for 10 touring caravans. Only provides limited provision with no room for future expansion as family needs grow, and does not make best use of the whole site. Report 5.3, 5.8, P41
  • Chosen: Option 3: Develop the site for 8 pitches for 10 touring caravans now, with approval to explore a second phase on adjacent land adding 6 pitches. Provides a compliant, good quality site for current and new residents, helps meet identified need, allows for larger future provision, and supports Local Plan progress. Report 1.2, 5.4, 5.8, P41
  • Rejected: Dispose of the site. Disposal would not achieve vacant possession, raises equalities and human rights issues, and would not contribute to meeting Gypsy and Traveller accommodation needs. Report 5.2

Implications

  • Financial: Adding £2,684,000 to the Capital Programme funded by prudential borrowing; the figure assumes no grant funding, but officers will pursue Homes England Social and Affordable Homes Programme funding, which could reduce the council's outlay. Report 1.3, 5.14, 5.16, 5.17, P77
  • Legal: The Public Sector Equality Duty applies because race is a protected characteristic; the Council must consider impacts on people of Gypsy and Traveller heritage, and any decision could be subject to Judicial Review on public law grounds. Report 6.3, 6.4, 11.3
  • Equalities: The Diversity Impact Assessment confirms an advance equality impact and positive impact on fostering good relations; permanent provision should improve safeguarding, health and wellbeing, and access to services for the community. Report 6.5, 6.6, P85
  • Risk: Key risks rated in the report include Local Plan adoption (B2), tender delays (C2), environmental constraints (C3), budget overspend (C3) and complications decanting current occupants (B3). Report P71
  • Climate: Plans will explore renewable energy such as solar PV and heat pumps, water saving devices, and landscaping for carbon capture, with a biodiversity net gain study required for any planning application. Report 9.2, 9.3, 9.4

Who and where

  • The current family group occupying the Wigmore site, who will need to be decanted to alternative accommodation during construction Report 4.1, 4.3, 5.12
  • Gypsy and Traveller households in Medway with an identified need for 30 more pitches in the Local Plan 2041 Report 4.7, 6.4
  • Travelling Showpeople communities, with an identified residual need for 8 plots Report 4.7
  • Residents near Maidstone Road, Wigmore, and the wider Medway community affected by potential unauthorised encampments Report 5.8, 6.5

Timeline

  • 8 June to 20 July: Planning Service Call for Sites exercise running Report 4.10
  • by 31 July: Planning Service to report back to Plan Inspectors on review of Council owned land and Call for Sites Report 4.10
  • mid-August to late September: Proposed consultation on any additional site allocations identified for Gypsy and Traveller use Report 4.10, P72
  • late 2026: Anticipated Stage 2 hearing sessions for the Local Plan examination Report 4.10
  • 12 to 18 months: Estimated time from tender through planning to start construction on site for 8 pitches for 10 touring caravans Report 5.11

Plain English for the jargon

  • PPTS: Planning Policy for Traveller Sites, the national planning policy framework for Gypsy and Traveller accommodation.
  • GTAA: Gypsy and Traveller Accommodation Assessment, the council's evidence base identifying pitch and plot needs.
  • SAHP: Homes England's Social and Affordable Homes Programme, a potential source of grant funding for new sites.
  • DIA: Diversity Impact Assessment, the council's assessment of equalities impacts of a decision.
  • HMY: Hazle McCormack Young LLP, the architects commissioned for the Stage 1 feasibility study at the Wigmore site.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

The Cabinet noted the work that had been carried out to identify additional options for Gypsy and Traveller sites; to provide greater certainty that the Local Plan would meet needs. 107/2026 The Cabinet agreed to proceed with Option 3 for the future provision and use of the Wigmore Site as set out in section 5.8 of the report: to develop and improve the site as a permanent Council managed Gypsy and Traveller site to provide a good quality, compliant site for 10 touring caravans over 8 pitches, with approval to explore the provision of a second phase in future years. The second phase would expand the site into adjacent land as set out in Appendix B to the report and provide an additional 6 pitches to meet increasing future need, subject to the budget addition below ... view the full minutes text for item 9.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Cabinet 4 August 2026 Provision for Gypsy and Traveller Accommodation Portfolio Holders: Councillor Louwella Prenter, Portfolio Holder for Housing & Homelessness

Councillor Simon Curry, Portfolio Holder for Climate Change & Strategic Regeneration

Report from: Gill James, Assistant Director, Culture & Community

Authors: Becs Wilcox, Chief Housing Officer

Dave Harris, Chief Planning Officer

Summary This report outlines proposed steps to address the needs for Gypsy and Traveller accommodation in Medway. The submission version of the Medway Local Plan 2041 does not meet the full needs of the Gypsy and Traveller and Travelling Show People. Published correspondence between the Council and the inspectors, appointed to examine the Plan, sets out actions for the Council to identify a sufficient supply of land to meet needs.

The Council has confirmed that it will carry out actions to seek to increase certainty on meeting the identified needs for this specialist accommodation through the Plan. This is critical to the timing and progress of the Local Plan.

The Council has reviewed land in its ownership to identify further capacity for Gypsy and Traveller accommodation. It is also held a ‘Call for Sites’ to identify if there is suitable land in other ownership.

As part of the review of Council owned land, this report sets out proposed options and recommendations for the future use of the former Park & Ride Car Park site in Maidstone Road, Wigmore (referred to in this report as the ‘Wigmore Site’). Members have previously been presented with an overview of potential options for the provision of a permanent, Council owned and managed Gypsy and Traveller site. The following report presents three options for consideration in relation to this site, with further detail and clarity to enable a formal decision on the way forward. 1. Recommendations 1.1. The Cabinet is asked to note the work that has been carried out to identify additional options for Gypsy and Traveller sites; to provide greater certainty that the Local Plan will meet needs.

1.2The Cabinet is asked to agree to proceed with Option 3 for the future provision and use of the Wigmore Site as set out in section 5.8 of the report: to develop and improve the site as a permanent Council managed Gypsy and Traveller site to provide a good quality, compliant site for 10 touring caravans over 8 pitches, with approval to explore the provision of a second phase in future years. This second phase would expand the site into adjacent land as set out in Appendix B to the report and provide an additional 6 pitches to meet increasing future need, subject to the budget request in 1.3 below, required to deliver the second phase.

1.3The Cabinet is asked to agree to recommend to Council to add £2,684,000 to the Capital Programme (funded by prudential borrowing) to deliver the initial proposals set out in the recommended Option 3.

2 Suggested reasons for decision(s) 2.1 The decisions in this report are required to ensure progress and adoption of the Local Plan and for the Council to meet the identified accommodation need for the provision of Gypsy and Traveller sites in Medway.

3. Budget and policy framework 3.1. The decisions in this report are outside of the Council’s current budget frameworks as an addition to the Capital Programme is being requested.

3.2The decision to proceed with the recommended options in this report is a matter for Full Council.

3.3National planning policy for Gypsy and Traveller sites requires Local Authorities to identify and seek to meet accommodation needs. The Medway Local Plan forms the main part of the Development Plan for the Council. The Development Plan is part of the Policy Framework.

3.4The Council’s Community Safety Plan and One Medway Plan support the positive engagement with the Gypsy and Traveller community as well as ensuring improved health and wellbeing [Priority 4] and living in good quality affordable housing [Priority 5].

4. Background Wigmore Site

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Addendum reportAddendum 123 KB Download
PDF
Appendix AAppendix A 1.2 MB Download
PDF
Appendix BAppendix B 1.3 MB Download
PDF
Appendix DAppendix D 154 KB Download
PDF
Provision for Gypsy and Traveller AccommodationReport 203 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, apologies
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open
22 Sep 2026 Procurement Strategy 2025-2030 Update ReportThe Cabinet noted the comments of the Business Support and Digital Overview and Scrutiny Committee, as set out in sec... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies