Cabinet, Tuesday 4 August 2026 at 7.00pm

Capital Budget Monitoring - Round 1 2026/27

Noted Executive 1 paper

AI summaryMedway Cabinet notes £308.222million 2026/27 capital programme with £586,000 forecast underspend. Report flags planned virements to address smaller overspends on Street Furniture and SEND schemes.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted 2026/27 round one capital results
Money£586,000 forecast underspendAgainst approved capital programme of £308.222million
What happens nextVirements within delegations plannedTo address overspends on Street Furniture and Danecourt SEND
Who it affectsAll council directoratesPlus schools, residents, highways users and town centres

What was decided

Cabinet noted the results of the first round of capital budget monitoring for 2026/27. Report P4

Cabinet noted the budgetary changes since Council approved the 2026/27 Capital Budget on 25 February 2026. Report 1.2

The report shows a projected underspend of £586,000 against the approved £308.222million programme, with all four directorates currently within budget. Report P10, P11

Why

Full Council is responsible for agreeing the capital programme, while Cabinet is responsible for keeping spend within the approved programme. Report P6

Cabinet can take corrective action to prevent any forecast overspend from materialising, including approving virements up to £2million. Report P6, P7

What happens next

The service will request a virement under the Director of Place's delegation from the Highways Maintenance LTP3 budget to cover a £225,000 overspend on Street Furniture. Report P23

The service will request a virement under the Director of People's delegation from the £613,000 underspend at Rivermead to cover a £613,000 overspend on the Danecourt Secondary Expansion. Report P18

Any capital additions made under the Chief Operating Officer's delegated authority will be reported in the next budget monitoring report. Report 3.2, 3.3

The money

  • £308.222million Approved capital programme for 2026/27 at Round 1 Report P10
  • £586,000 Projected underspend across the programme Report P10
  • £116.190million Children and Adults approved budget Report P13
  • £116.339million Regeneration, Culture and Environment general fund approved budget Report P20, P21
  • £86.395million Housing Revenue Account approved budget Report P31
  • £225,000 Street Furniture forecast overspend, to be vired from Highways Maintenance LTP3 Report P23
  • £613,000 Rivermead at Stoke Refurb underspend, to be vired to Danecourt Secondary Expansion Report P18

Options considered

  • Chosen: Vire £225,000 from Highways Maintenance LTP3 to Street Furniture. Street Furniture is forecasting an overspend of £225,000 and the service will request this under the Director of Place's delegation. Report P23
  • Chosen: Vire £613,000 from Rivermead at Stoke Refurb to Danecourt Secondary Expansion. Rivermead delivered an underspend of £613,000 and Danecourt is forecasting an overspend of £613,000, with the service to request this under the Director of People's delegation. Report P18
  • Chosen: Vire £3,000 from Maidstone Road Playzone to The Strand Playzone. Maidstone Road reported a small underspend of £3,000, to be vired under the Director of Place's delegation. Report P27

Implications

  • Financial: Overall programme is forecasting an underspend of £586,000, mainly driven by Children's Social Care schemes. Report P10, P19
  • Financial: Some schemes are likely to need additional funding, with requests to be made via the School Place Planning Strategy, including All Saints Primary SEN Provision. Report P14, P18
  • Risk: The Gun Wharf Improvement Works budget is being monitored closely, with value engineering required to keep costs within budget. Report P27
  • Other: The Brook Theatre Refurbishment programme will now extend into spring 2028 following the discovery of serious structural issues, with the grant spend deadline extended by MHCLG. Report P27
  • Other: East Hill New Primary School will not commence until late 2027, with contractors on site from 2028 and completion in 2030. Report P14

Who and where

  • Children and Adults Directorate, including schools and SEND provision Report P11, P13
  • Regeneration, Culture and Environment Directorate, including highways, libraries and theatres Report P11, P20, P21
  • Housing Revenue Account tenants and residents on the temporary accommodation programme Report P11, P31
  • Highways users, including those affected by LED replacement, pothole repairs and school streets Report P23, P25
  • Visitors to country parks subject to new car park charges Report P26

Timeline

  • 25 February 2026: Full Council approved the 2026/27 Capital Budget Report 1.2
  • 4 August 2026: Cabinet meeting held to note Round 1 monitoring Report P1
  • Summer 2026: Hoo Sports Centre wetside works, LED lantern completion, ANPR roll-out and Brook demolition programme due to start Report P23, P27, P31
  • By 31 March 2027: Pride in Place Impact Fund grant funding must be spent or contractually committed Report P31
  • 2030: East Hill New Primary School and Danecourt Secondary Expansion anticipated to complete Report P14, P18

Plain English for the jargon

  • Capital programme: The council's budget for spending on long term assets such as buildings, roads and equipment.
  • Virement: Moving budget from one scheme to another within the capital programme.
  • HRA: Housing Revenue Account, the ringfenced budget for council housing.
  • SEND: Special Educational Needs and Disabilities.
  • RAAC: Reinforced Autoclaved Aerated Concrete, a type of building material that has raised safety concerns in some public buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Cabinet noted the results of the first round of capital budget monitoring for 2026/27. The Cabinet noted the budgetary changes since Council approved the 2026/27 Capital Budget on 25 February 2026, as set out in sections 10.1 to 10.2 of the report. Reasons: Full Council is responsible for agreeing the capital programme. Cabinet is responsible for ensuring that expenditure remains within the approved programme, including instructing corrective action to prevent any forecast overspend from materialising.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Cabinet

Cabinet 4 August 2026 Capital Budget Monitoring – Round 1 2026/27 Portfolio Holder: Councillor Vince Maple, Leader of the Council

Report from: Phil Watts, Chief Operating Officer

Author: Abbey Gough, Chief Finance Officer Andy McNally-Johnson, Head of Corporate Accounts Summary This report presents the results of the first round of the Council’s capital budget monitoring process for 2026/27.

1. Recommendations 1.1. The Cabinet is asked to note the results of the first round of capital budget monitoring for 2026/27.

1.2The Cabinet is asked to note the budgetary changes since Council approved the 2026/27 Capital Budget on 25 February 2026 as set out in sections 10.1 to 10.2 below.

2. Suggested reasons for decisions 2.1. Full Council is responsible for agreeing the capital programme. Cabinet is responsible for ensuring that expenditure remains within the approved programme, including instructing corrective action to prevent any forecast overspend from materialising.

3. Budget and policy framework 3.1. Cabinet is responsible for ensuring that capital expenditure remains within the budget approved by Council. Where required, the report will give details relating to additional schemes (capital additions) or movements in budgets between schemes (virements). Capital virements of up to £1million can be approved by the Chief Executive and Directors, capital virements up to £2million can be approved by Cabinet with anything above that being reported to Full Council for decision.

3.2The Chief Operating Officer has delegated authority to approve in year additions to the capital programme, in consultation with the Finance Portfolio Holder, subject to the following criteria: • funding coming from external sources, to be used for a specific purpose on a specific asset, • no financial contribution coming from the Council, • funding being ringfenced for specific purposes.

3.3Any additions made under delegated authority are reported through the next budget monitoring report.

4. Summary Capital Budget Position 2026/27 4.1. The approved capital programme for 2026/27 as at Round 1 is £308.222million. Table 1 below summarises the capital programme and Round 1 forecast position showing a projected underspend of £586,000. Table 2 details how the approved programme will be funded.

Table 1: Round Three Capital Monitoring Summary Forecast Total Total Forecast Forecast Spend Directorate Approved Expenditure Remaining Spend (Under)/ in Future Cost to 31/03/26 Budget 2026/27 overspend Years £000 £000 £000 £000 £000 £000 Children and Adults (including 116,190 10,730 105,460 14,964 89,910 (586) Public Health) Regeneration, Culture and 336,330 219,990 116,339 78,732 37,607 0 Environment Housing Revenue Account 149,617 63,222 86,395 26,049 60,346 0 Business Support Department 150 123 27 27 0 0 Total 602,287 294,065 308,222 119,772 187,864 (586)

Table 2: Funding the Capital Budget Funding Source Total C&A RCE HRA BSD £000 £000 £000 £000 £000 Capital Grants 70,986 44,721 26,151 114 0 Developer Contributions 4,249 2 4,247 0 0 Capital Receipts 613 0 585 0 27 RTB Receipts 600 0 0 600 0 Revenue / Reserves 12,962 0 300 12,662 0 Borrowing 218,812 60,737 85,056 73,019 3 Total 308,222 105,460 116,339 86,395 27 5. Children and Adults 5.1. The Children and Adults programme is forecast to underspend by £0.586million against the approved budget of £116.190million as set out below.

Forecast Total Total Forecast Spend Total Approved Exp to Remaining Spend in Future Scheme Cost 31/03/26 Budget 2026/27 Years Variance £000 £000 £000 £000 £000 £000 Basic Needs - Primary 19,600 583 19,017 1,946 17,071 0 Basic Needs - Secondary 12,140 3,362 8,778 2,158 6,621 0 School Condition Programme 1,056 0 1,056 1,056 0 0 Schools Devolved Capital 117 0 117 117 0 0 Basic Needs - SEND 37,566 5,601 31,966 4,668 27,298 0 Children’s Social Care 1,432 653 779 194 0 (586) Adult Social Care 44,278 531 43,747 4,826 38,921 0 Children and Adult Services Total 116,190 10,730 105,460 14,964 89,910 (586)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring: Round 1 2026/27Report 357 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
VM
Councillor Vince Maple (Lab)Committee Member, present
TM
Councillor Teresa Murray (Lab)Committee Member, present
TC
Councillor Tracy Coombs (Lab)Committee Member, present
SC
Councillor Simon Curry (Lab)Committee Member, present
NG
Councillor Nina Gurung (Lab)Committee Member, apologies
HM
Councillor Harinder Mahil (Lab)Committee Member, present
AP
Councillor Alex Paterson (Lab)Committee Member, present
LP
Councillor Louwella Prenter (Lab)Committee Member, present
AP
Councillor Adam Price (Lab)Committee Member, present
ZV
Councillor Zoë Van Dyke (Lab)Committee Member, present

On this subject at Medway

Search all
  1. Capital Budget Monitoring - Round 1 2026/27This decision
  2. Capital Budget Monitoring - Round 1 2026/27Noted
  3. Capital Budget Monitoring - Round 1 2026/27Noted
  4. Capital Budget Monitoring - Round 1 2026/27Noted
  5. Amendments to the Revenue Budget and Capital ProgrammeAgreed
  6. Capital Budget Monitoring – Round 3 2025/26Noted

More from Medway Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Articles on the Highway Policy132/2026 The Cabinet approved the final , set out at Appendix 3 to the report, for implementation and noted that futu... Approved Open
22 Sep 2026 Continuation of the Grow in Kent Visitor Economy and Inward Investment Service136/2026 The Cabinet approved the continuation of Medway Council participation in the Grow in Kent service. 137/2026 ... Approved Open
22 Sep 2026 Medium Term Financial Outlook 2026-2031The Cabinet noted the projected budget requirement, the Council’s resource assumptions, and the resultant projected b... Noted Open
22 Sep 2026 Private Sector Licensing (Additional & Selective Licensing Schemes)The Cabinet noted the outcome of the consultation process detailed in the Consultation Report (June 2026), which prov... Noted Open