Capital Budget Monitoring - Round 1 2026/27

Noted Scrutiny 1 paper

AI summaryMedway children and young people committee notes first round 2026/27 capital monitoring, showing a forecast underspend of £586,000 against the £61.779million children and adults capital budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedForecast underspend of £586,000 against budget
Money£586,000 forecast underspendAgainst £61.779million approved children and adults budget
What happens nextNext round of monitoringVirements to be processed under delegation
Who it affectsChildren services capital schemesSchools, SEND and social care in Medway

What was decided

The Committee noted the first round of capital budget monitoring results for 2026/27, recording a forecast underspend of £586,000 against the £61.779million children and adults approved budget. Report 1.1, P5, P8

The total approved capital programme for 2026/27 stood at £308.222million, with overall project cost across the programme of £602.287million. Report P5, P6, P7

Why

The report consolidated returns from individual budget managers and provided forecasts and progress updates for capital schemes within the committee's remit. Report P1, P5, P6

Several schemes had come in under budget while others were forecasting pressures, requiring the committee to be aware of underspends, overspends and proposed virements. Report P8, P10, P15

What happens next

The service intends to request a virement, via the Director of People's delegation, of £613,000 from the Rivermead at Stoke Refurbishment underspend to the Danecourt Secondary Expansion scheme. Report P15

The service will also request that the £586,000 overall children and adults underspend be vired to other schemes to support further capital improvements across children's social care. Report P15

Additions to the capital programme made under delegated authority, and any further virements, will be reported through the next budget monitoring round. Report 2.2, P5

The money

  • £308.222million Total approved capital programme for 2026/27 Report P5, P6
  • £602.287million Total approved cost of schemes in the programme including prior years Report P5, P7
  • £61.779million Approved 2026/27 budget for children and adults programme Report P8, P10, P11
  • £586,000 Forecast underspend within children and adults programme Report P7, P8, P10, P11, P17
  • £10.411million Spend to 31/03/26 on children and young persons schemes Report P11
  • £10.204million Forecast spend in 2026/27 for children and young persons schemes Report P11
  • £613,000 Underspend on Rivermead at Stoke Refurbishment to be vired to Danecourt Report P15
  • £512,000 Underspend on Aut Even Redevelopment proposed for virement Report P15

Options considered

  • Chosen: Note the first round capital budget monitoring results for 2026/27. Recommended action in the report Report 1.1

Implications

  • Financial: A forecast underspend of £586,000 is to be vired under delegation to other children's social care schemes, with some restrictions where funding is grant ringfenced. Report P15
  • Financial: A large share of the capital budget is funded from borrowing, exposing the Council to interest rate risk above budgeted levels. Report P18
  • Risk: Macro-economic conditions affecting cost and availability of materials and labour are rated B3 for risk to deliverability of the capital programme. Report P18
  • Legal: There are no direct legal implications from this monitoring report, though some schemes, such as Chatham Grammar SEN Provision, have been delayed by legal matters. Report P15, P21

Who and where

  • Pupils and families across Medway schools receiving new places and facilities Report P12, P13, P14, P15
  • Children and young people with SEND using new and expanded resourced provision Report P15
  • Children in social care, including those using the Children's Assessment Unit and Aut Even home Report P15
  • Early years providers in receipt of the Childcare Expansion Grant Report P12

Timeline

  • September 2026: Fort Pitt Grammar co-education works expected to complete; Napier Primary and St Margaret's Primary SEN provisions due to complete Report P14, P15
  • Summer 2026: Structural work at Aut Even expected to complete; fire risk surveys at schools to take place Report P14, P15
  • 2027/28: Final co-ed works at Chatham Grammar and Holcombe Grammar to take place; Leigh Academy SEND scheme expected to complete Report P14, P15
  • Summer 2027: Works expected to commence on site at Hoo St Werburgh school expansion Report P12
  • 2028/29: Strood Academy expansion and New Road Primary 2FE expansion expected to complete Report P12, P14
  • September 2028: Hoo St Werburgh and Marlborough Centre Relocation schemes expected to complete Report P12
  • 2030: East Hill New Primary School and Danecourt Secondary Expansion expected to complete Report P12, P15

Plain English for the jargon

  • FE: Form of entry, a measure of school capacity based on number of classes per year group
  • PAN: Published Admission Number, the school's stated admission limit for a year group
  • SEND: Special Educational Needs and Disabilities
  • ASD: Autism Spectrum Disorder
  • MLD: Moderate Learning Difficulties
  • Co-Ed: Co-education, mixed education of boys and girls
  • s106: Section 106 developer contributions, paid by developers towards local infrastructure
  • DfE: Department for Education
  • Virement: Movement of budget between schemes or budget headings
  • Ringfenced: Funding restricted to a specified purpose and unable to be spent on other items
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item209

Resolved

The Committee noted the results of the first round of capital budget monitoring for 2026/27.
Word for word from the decision Medway published for this meeting. Source: democracy.medway.gov.uk

Follow this further

Built from Medway's papers

What the report saysPro

Report to Children and Young People Overview and Scrutiny Committee

Summary

This report presents the results of the first round of the Council’s capital budget monitoring process for 2026/27. The Council’s summary position is presented in section 4, with section 5 providing the details for the service areas within the remit of this Committee.

Recommendation

1.1The Children and Young People Overview & Scrutiny Committee is asked to note the results of the first round of capital budget monitoring for 2026/27.

2. Budget and policy framework 2.1. Cabinet is responsible for ensuring that capital expenditure remains within the budget approved by Council. Where required, the report will give details relating to additional schemes (capital additions) or movements in budgets between schemes (virements). Capital virements of up to £1million can be approved by the Chief Executive and Directors, capital virements up to £2million can be approved by Cabinet with anything above that being reported to Full Council for decision.

2.2The Chief Operating Officer has delegated authority to approve in year additions to the capital programme, in consultation with the Finance Portfolio Holder, subject to the following criteria:

• funding coming from external sources, to be used for a specific purpose on a specific asset, • no financial contribution coming from the Council, • funding being ringfenced for specific purposes. • Any additions made under delegated authority are reported through the next budget monitoring report 3. Background 3.1. The approved capital programme for 2026/27 and beyond is £308.222million. Together with spend incurred on this programme in prior years, the total approved cost of these schemes in the approved programme is £602.287million. This report consolidates the first round of capital budget forecasts for 2026/27, based on returns submitted by individual budget managers. An analysis is provided below for each service area within the remit of this committee detailing both financial forecasts and providing an update as to the current progress of capital schemes, and any management action required to deal with either budgetary or progress issues. Where schemes are projected to complete later than the current financial year, a forecast of the anticipated spend profile is given.

4. Summary Capital Budget Position 2026/27 4.1. The approved capital programme for 2026/27 as at Round 1 is £308.222million. Table 1 below summarises the capital programme and Round 1 forecast position showing a projected underspend of £586,000. Table 2 details how the approved programme will be funded.

Table 1: Round One Capital Monitoring Summary Forecast Total Total Forecast Forecast Spend Directorate Approved Expenditure Remaining Spend (Under)/ in Future Cost to 31/03/26 Budget 2026/27 overspend Years £000 £000 £000 £000 £000 £000 Children and Adults (including 116,190 10,730 105,460 14,964 89,910 (586) Public Health) Regeneration, Culture and 336,330 219,990 116,339 78,732 37,607 0 Environment Housing Revenue Account 149,617 63,222 86,395 26,049 60,346 0 Business Support Department 150 123 27 27 0 0 Total 602,287 294,065 308,222 119,772 187,864 (586)

Table 2: Funding the Capital Budget Funding Source Total C&A RCE HRA BSD £000 £000 £000 £000 £000 Capital Grants 70,986 44,721 26,151 114 0 Developer Contributions 4,249 2 4,247 0 0 Capital Receipts 613 0 585 0 27 RTB Receipts 600 0 0 600 0 Revenue / Reserves 12,962 0 300 12,662 0 Borrowing 218,812 60,737 85,056 73,019 3 Total 308,222 105,460 116,339 86,395 27 5. Children and Young People 5.1. The Children and Adults programme within the remit of this Committee is forecast to underspend by £586,000 against the approved budget of £61.779million as set out below.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Budget Monitoring: Round 1 2026/27Report 211 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 41 attended
JH
Councillor Joanne Howcroft-Scott (Lab)Chairperson, present
LM
Councillor Lia Mandaracas (Lab)Vice-Chairperson, present
DA
Councillor Damola Animashaun (Lab)Committee Member, present
WB
Councillor William Burvill (Reform)Committee Member, present
AG
Councillor Adrian Gulvin (Con)Committee Member, present
DH
Councillor Douglas Hamandishe (Lab)Committee Member, present
DP
Councillor Dr Paula Hamilton (Lab)Committee Member, apologies, sent representative
SH
Councillor Stephen Hubbard (Lab)Committee Member, present
AH
Councillor Alex Hyne (Con)Committee Member, present
SJ
Councillor Sharon Jackson (Lab)Committee Member, apologies, sent representative
MJ
Councillor Mark Joy (Con)Committee Member, present
WS
Councillor Wayne Spring (Con)Committee Member, apologies, sent representative

All 41 on the meeting page

On this subject at Medway

Search all
  1. Capital Budget Monitoring - Round 1 2026/27This decision
  2. Capital Budget Monitoring - Round 1 2026/27Noted
  3. Capital Budget Monitoring - Round 1 2026/27Noted
  4. Capital Budget Monitoring - Round 1 2026/27Noted
  5. Amendments to the Revenue Budget and Capital ProgrammeAgreed
  6. Capital Budget Monitoring – Round 3 2025/26Noted

More from Medway Children and Young People Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
1 Oct 2026 Independent Reviewing Officer (IRO) Annual ReportThe Committee noted the Independent Reviewing Officer (IRO) Annual Report. Noted Open
1 Oct 2026 Work programmea) The Committee noted the report and agreed the work programme as set out at Appendix 1 to the report, subject to ac... Noted Open
12 Aug 2026 Early Years Update ReportThe Committee noted the report. Noted Open
12 Aug 2026 The One Medway Council Plan Performance Monitoring Report and Strategic Risk Summary - Quarter 1 2026/27The Committee noted: a) The Quarter 1 2026/27 progress of the performance indicators used to monitor progress of the ... Noted Open
12 Aug 2026 Revenue Budget Monitoring - Round 1 2026/27The Committee noted: a) The results of the first round of revenue budget monitoring for 2026/27. b) That Cabinet inst... Noted Open