RESOLVED That Cabinet approves and supports Merthyr Tydfil CBC working collaboratively with the 5 Valley’s authorities, Blaenau Gwent CBC, Bridgend CBC, Caerphilly CBC, Torfaen CBC and Rhondda Cynon Taff CBC to develop a Strategic Framework / projects to meet the requirements of the Convergence Programme.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To inform the Cabinet of the latest developments of the Operational Programmes for the Convergence Objective Programme 2007 – 2013 in West Wales & the Valleys.
1. INTRODUCTION AND BACKGROUND Objective 1 Achievements The present Objective 1 programme has achieved ( at mid term review ) 40,500 new jobs, the creation of 1,895 new SME’s and 84,800 unemployed / inactive people moving into employment / further learning. West Wales and the Valleys has also seen a 16.1% improvement in the GDP; a 3.3% increase in employment; a 1.8% reduction in unemployment and 2.2% reduction in inactivity. However the Valleys authorities still top the deprivation indices, which the Joseph Rowntree Foundation report on ‘Monitoring poverty and social exclusion in Wales 2005’ highlights.
2. OBJECTIVE 1 PROGRAMME LESSONS LEARNT The mid term review of the present Objective 1 Programme in 2004 noted that the programme had been driven by a ‘bottom-up’ approach, a lack of strategic direction with an air of “something for everyone” without an overall focus on raising GDP, job creation and combating inactivity, resulting in the programme becoming a menu of options. In summary the lessons learnt are as follows:- Need stronger strategic framework – programmes to be more closely aligned with national/regional policies and strategies; Programme structures and processes overly complex – too many priorities/measures; multi-fund programmes; scope for simplifying funding streams; Too many projects (over 2,500), not always sufficiently focused on headline programme objectives;
1 Need for more emphasis on regional collaboration in the development of strategies and projects; N+2 challenges – sufficient project activity in the pipeline and need to maximise expenditure; Partnerships – some positive experiences but overly elaborate structures; Monitoring and evaluation – build in from the start.
3. PROGRAMME PREPARATIONS In order to address the lessons learnt and the high deprivation levels, five work streams and the Stakeholder Group have been developing the operational programme. This will be launched and go to public consultation on July 28th and to be submitted to the commission at the end of October. As the Commission will have to negotiate around 350 individual Operational Programmes with nations and regions across the EU it is unlikely that these will be approved before May 2007.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.