Resolved
RESOLVED That Cabinet received this report.
Cabinet decided this item on Wednesday 26 July 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That Cabinet received this report.
To inform Councillors of the health and safety Improvement Notice recently served upon the authority, and of the work being undertaken to satisfy this notice.
1.1On 23rd March 2006 a meeting took place between Council officers and an Inspector from the Health & Safety Executive (HSE) to discuss the action to be taken by the authority with regard to reducing risks from glazed surfaces within educational premises.
1.2Regulation 14 of the Workplace (Health, Safety & Welfare) Regulations 1992 requires that every window or transparent surface in a wall, partition, door or gate shall, where necessary for reasons of health and safety, be of a safety material or be protected against breakage and appopriately marked.
1.3The HSE Inspector is concerned to note that the authority has carried out no risk assessments of glazed surfaces within educational premises.
1.4The Inspector has therefore issued an Improvement Notice requiring the Council to remedy the identified legal contraventions by 1st June 2007.
2.0AIM
2.1The aim is to comply with the requirements of the Improvement Notice by the deadline of 1st June 2007, and thus avoid further enforcement action. 3.0 OBJECTIVES
The proposed programme of work to satisfy this notice is as follows:
3.1Prepare a prioritised list of educational premises. (See Appendix A).
3.2Bring together a team of officers who will work with schools in order to undertake glazing risk assessments.
3.3Complete all risk assessments by 31st December 2006.
3.4Undertake remedial work for all ‘high risk’ glazing by 31st May 2007.
3.5Make recommendations for low and medium glazing risks based upon the risk assessment findings.
4.1There are likely to be financial implications associated with satisfying the notice, but these are unknown until the risk assessments are completed.
4.2Remedial works might include fitting new glazing, applying safety film, removing hazardous glass or covering it with boarding.
4.3The cost of remedial works will need to be met from either schools’ delegated budgets or from a rolling programme of planned maintenance funded by ICS. However, the exact details of the funding will depend upon the volume and type of work required.
4.4It is possible that the total costs involved and the timescale set by the HSE might mean having to come back to Council to request additional funds as a last resort.
4.5A further information report will be produced once the assessments have been carried out to alert members to the financial implications.
JILL SHUKER DIRECTOR OF CORPORATE CENTRE INTERNAL REPORT CONSULTATION:
The following officers have been consulted in respect of the proposals and recommendations set out in this report.
Chief Executive Deputy Chief Director of Director of Director of Chief Officer, Executive and Integrated Customer Integrated Adult Finance, Audit Director of Children’s Community Services and Risk Customer Services Services Management Corporate Services
Title of Document(s) Document(s) Date Document Location
HSE Improvement Notice 27th April 2006 (Alyn Dinham) Appendix A Phase One
Comprehensive & Special Schools
School Start End
Afon Taf High School 24 July 2006 26 July 2006
Bishop Hedley RC High School 27 July 2006 01 August 2006
Cyfarthfa High (Lower) School 02 August 2006 04 August 2006
Cyfarthfa High (Upper) School 07 August 2006 09 August 2006
Pen-y-Dre High School 10 August 2006 14 August 2006
Greenfield Special School 15 August 2006 17 August 2006
Phase Two
Nursery, Infant, Junior & Primary Schools
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Improvement Notice: Risks from Glazed SurfacesReport | 5 pages | DownloadRead as text |
Follow Cabinet at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... | Approved | Open |
| 22 Oct 2026 | Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. | Approved | Open |
| 22 Oct 2026 | Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... | Noted | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... | Approved | Open |
| 22 Oct 2026 | Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.