Merthyr Tydfil County Borough Council
Governance and Audit Committee, Monday 9 October 2006 at 2.00pm

Progress with Pericles System

Noted Finance 1 paper

Governance and Audit Committee noted this item on Monday 9 October 2006. Below is the council's own wording, with the papers it was decided on.

Item424

Resolved

RESOLVED (a) That the report be received and the contents noted (b) That the Committees thanks to the Director of Customer Community Services, the Head of Revenues and Benefits and all staff involved be recorded (c) That an update be given to the Committee once the new Contract has been in operation for six months.
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Governance and Audit Committee, 4 pages

Purpose of report

To provide Audit Committee Members with an update on progress with the PERICLES system.

Background

1.1The Local Authority purchased Anite’s Pericles Benefits system in 2001, with the system going live in August that year. As Pericles was still in development at that time, Merthyr was effectively a “test” site operating in a “live” environment, and it became apparent that there were major problems with the software, resulting in significant delays in processing benefit claims. At that time, Merthyr were the only Authority in the UK with Pericles, which remained the position until 2004.

1.2The impact of the delays resulted in Members of the Council, via Scrutiny Committee, meeting with Anite representatives in July 2002, in an effort to resolve the software problems. The subsequent report contained many recommendations for improvements to the service, relating to its management, working practices and software.

1.3In April 2003, the management of the section passed over to the then Housing & Technical Department (now Customer Community Services).

1.4New Claim processing times for 2002/3 were 153 days, which identified Merthyr Tydfil as the second worst performing Local Authority in the UK. As a result of its poor performance, the Authority was selected for inspection by the Department for Work & Pensions (DWP) Benefit Fraud Inspectorate (BFI), and their report, published in December 2004, contained over 80 recommendations for service improvements. 1.5 Since that report, performance of the Pericles product has improved considerably, and new claim processing times have averaged 22 days for the 5 month period from April to August 2006 inclusive – these figures, and those of 29 days for the 2005/6 financial year, place the Authority in the top quartile performance in the UK. However, we would not have achieved the significant improvements in processing times without the input of the Benefit staff themselves, who have adapted to constant changes in working practices in the last 3 years, especially since the introduction of the Document Management System in November 2004.

1.6For information, I detail below the main areas of concern highlighted by Councillors, the BFI, and Internal Audit, and the progress to date.

2.0MTCBC / ANITE CONTRACT

2.1The Authority established a contract for the Pericles product with ICL in 1999. There has been considerable debate over the years on the validity of the contract, as it was not renewed when Anite took over ICL, and has resulted in the Authority being placed in difficult financial and operational situations on many occasions in recent years. Since 2005 however, a SOCITM Consultant has been working closely with the Head of Benefits & Revenues, and Anite, to finalise a new agreement, and the Authority’s Legal Section has recently approved the final draft.

It is expected that the contract will be signed in the next 4-6 weeks.

3.0BENEFIT OVERPAYMENTS

3.1A significant backlog of work accrued as a result of the Pericles software problems, with claims and other correspondence taking many months to action. As a result, changes in claimant’s circumstances, which resulted in their benefit entitlement reducing, led to the creation of many overpayments of benefit to both claimants and landlords, some of which were quite substantial. These debts would normally be recovered by invoicing via the Pericles system, but despite assurances given by senior Anite staff that the Overpayments module was being developed, we did not actually go “live” until January 2006.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress with Pericles SystemReport 4 pages DownloadRead as text

At this meeting

Whole meeting

More from Merthyr Tydfil Governance and Audit Committee

All decisions
MeetingDecisionOutcome
28 Sep 2026 Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. Noted Open
28 Sep 2026 Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. Approved Open
28 Sep 2026 Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... Noted Open
22 Jun 2026 Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... Decided Open
1 Sep 2025 Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies