Resolved
RESOLVED (a) That the report be received and the contents noted (b) That the Committees thanks be conveyed to all staff for their efforts in this matter (c) That an update on this matter be made to the Committee in six months.
Governance and Audit Committee noted this item on Monday 9 October 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (a) That the report be received and the contents noted (b) That the Committees thanks be conveyed to all staff for their efforts in this matter (c) That an update on this matter be made to the Committee in six months.
To provide Audit Committee members with an update on the DEBTORS system
1.1The Debtors section is based in Customer Community Services and is managed by the Head of Revenues & Benefits, with the section consisting of 2 full time members of staff. Whilst they are responsible for recovering all unpaid Sundry Debts raised by the Authority, and some work relating to the raising of invoices, Income Management work also accounts for approximately 50% of their duties.
1.2The Authority raises large numbers of invoices each year, with over 9900 issued in 2005/6 alone, ranging from £5 and under to large amounts of almost £100000.
1.3The average monthly corporate debt levels peaked at £2.76m in 2003/4, but by the end of 2005/6, this figure had been reduced to £2.33m. However, it was clear that due to the volume of invoices raised each year, more targeted work was required to reduce corporate debt levels, and these details are included in Paragraph 4.0.
1.4The profile of Debtors also needed to be raised amongst Directors and Heads of Services, to not only make them fully aware of the corporate debt levels, but also the debt outstanding on invoices raised by their own Directorates. To raise awareness of this issue, Mark Horrigan, Head of Revenues and Benefits, attended each SMB in recent months to present information on Debtors, which I will refer to further in the report. 2.0 AUDIT REPORTS/AGRESSO SYSTEM
2.1The Debtors section has been the subject of a number of Audit reports in recent years, both internally and by external agencies such as PWC. The reports have focused on operational and system functions, and have included a number of recommendations for improvements in both areas.
2.2Many of the operational recommendations in the most recent reports have been implemented, but due to issues with the Agresso Debtors module, it has not been possible to fully implement those relating to Agresso, especially where System Management reporting is involved.
2.3Over the last 5 months, there has been a major problem with the Agresso system in respect of “Automatic Matching”. When a payment is received against an invoice, the system should automatically match it, and if paid in full, reduce the balance to zero.
2.4However, since April 2006 the defect referred to in 2.3 has prevented this happening, and every report we now produce for debt monitoring purposes has to be manually checked, due to their inaccuracy. This is extremely resource intensive, and should not be required if the system is functioning correctly.
2.5This situation cannot continue indefinitely as it is having a significant impact on our debt recovery processes, and at the time of writing this report, a meeting is being arranged with Agresso representatives to escalate this issue.
3.0AUDIT ACTION PLANS (AAP’s)
3.1Following the introduction of the AAP’s earlier this year, progress on the Internal Audit report has been monitored and regularly updated on the AAP spreadsheet. To date, approximately 70% of the recommendations have been implemented, and whilst we are currently unable to implement some due to the Agresso problems referred to in paragraphs 2.1-2.5, I am confident that we will be able to fully complete all other recommendations by November 2006.
4.0PERFORMANCE
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress with Debtors SystemReport | 5 pages | DownloadRead as text |
Follow Governance and Audit Committee at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2026 | Peer Panel Performance Assessment - Response and Action PlanResolved that the report and draft action plan be noted and recommended to Council for approval. | Noted | Open |
| 28 Sep 2026 | Terms of ReferenceResolved that the Governance and Audit Committee be approved and reviewed annually. | Approved | Open |
| 28 Sep 2026 | Governance and Audit Committee Annual Report 2025/26Resolved that the Annual Report be noted, amended as appropriate in relation to the attendance record, and recommende... | Noted | Open |
| 22 Jun 2026 | Appointment of Chair and Vice ChairResolved; That Martin Veale continue as Chair and Colin Prosser continue as Vice-Chair of the Governance and Audit Co... | Decided | Open |
| 1 Sep 2025 | Time of Future MeetingsIt was agreed that future meetings would be moved to 5pm and if there was an issue with officer availability for any ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.