Resolved
RESOLVED That Council approve the use of the Corporate Improvement and Risk Management Calendar recognising that certain amendments will be necessary to the calendar as time progresses and further experience is gained.
Full Council approved this item on Wednesday 7 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That Council approve the use of the Corporate Improvement and Risk Management Calendar recognising that certain amendments will be necessary to the calendar as time progresses and further experience is gained.
MERTHYR TYDFIL COUNTY BOROUGH COUNCIL
DATE WRITTEN 16th February 2007 REPORT AUTHOR Mark Thomas/Kerry O’Donovan HEAD OF SERVICE Mark Thomas COMMITTEE Council COMMITTEE DATE 7th March 2007
TO: Mayor, Ladies and Gentlemen
CORPORATE IMPROVEMENT AND RISK MANAGEMENT CALENDAR
PURPOSE OF REPORT: To demonstrate to Councillors the links between improvement, risk management and statutory matters through the utilisation of the Corporate Improvement and Risk Management Calendar.
1. INTRODUCTION
1.1This report was considered by the Audit Committee on 12th February 2007. The Committee agreed the following :
1. To approve the Corporate Improvement and Risk Management Calendar. 2. To endorse the use of the Calendar by the Authority. 3. That the Calendar be placed before Council in March 2007.
1.2This report is being presented to Council as resolved by the Audit Committee.
1.3The issue of the Authority needing to try and better integrate Improvement Risk Assessments (Wales Programme for Improvement) and traditional Risk Management has been identified over the last year.
1.4The benefits of identifying other corporate activities which need to be undertaken has also been recognised and this has led to the development of a Corporate Improvement and Risk Management Calendar (This can be seen in Appendix 1).
1.5The purpose of the Calendar is to:
• Show how corporate activities are linked, capturing improvement, risk management and statutory tasks.
• Minimise duplication. • Enable work planning to be undertaken.
• Assist in identifying peak workloads.
2. BACKGROUND AND EXPLANATION
2.1The Corporate Improvement and Risk Management Calendar was developed through collaborative working between Internal Audit and Improvement Planning.
2.2The Calendar has also been shared with the Wales Audit Office to ensure that their input was obtained. The feedback from the Wales Audit Office was very positive to the approach that the Authority is pursuing.
2.3During the design and development stage of the Calendar the Chief Executive and all Directors were individually consulted. A number of suggestions were made which were then reflected in the Calendar.
2.4The Calendar was presented to Executive Board on Tuesday 16th January 2007. It is planned that the Calendar will also be presented to Full Council in March 2007.
2.5The spreadsheet based Calendar shows improvement, risk management and statutory activities and can act as a rolling Calendar which can be printed out to cover any specific period of time e.g. Monthly, quarterly, six monthly, yearly or even on an eighteen monthly basis if needed.
2.6Each service area is expected to complete individual Service Assessments (SAM2s), with the exception, for now, of Integrated Children’s Services and Integrated Adult Services who are currently involved in the Joint Review Inspection. Each SAM2 will then be used to inform the Council’s service risk registers which will aim to capture the detail once and then be used for a number of purposes.
2.7Following completion of the SAM2s there will be an internal challenge and quality assurance process carried out by the Head of Improvement Planning, Head of Audit, Counter Fraud and Risk Management and Risk Management Officer followed by Heads of Service presenting their service risks at the relevant Service Management Boards. These findings will then be used to inform the Council’s Corporate Risk Register, supported by an Executive Board Risk Identification Workshop.
2.8This information will then be used to update the Joint Risk Assessment and the Statement of Internal Control. During May and November Risk Reports will be presented to Executive Board, Cabinet and the Audit Committee to outline progress on the management of risks.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Improvement and Risk Management CalendarReport | 4 pages | DownloadRead as text |
PDF |
Council 7th March 07 Corp Imp & Risk Man Calendar (Appendix 2).pdfAppendix | 1 pages | Download |
PDF |
Council 7th March 07 Corp Imp & Risk Man calendar (Appendix 1).pdfAppendix | 1 pages | Download |
Follow Full Council at Merthyr Tydfil and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | Allocations Policy for Community HousingResolved; That the recommendations as contained within the report be approved | Approved | Open |
| 22 Oct 2026 | MTCBC Receiving and Awarding Grants PolicyResolved; That the recommendations as contained within the report be approved | Approved | Open |
| 22 Oct 2026 | Greenfield Special School - Satellite ProvisionResolved; That the recommendations as contained within the report be approved. | Approved | Open |
| 22 Oct 2026 | Youth Service Statutory 5-Year Strategic Plan 2027-32Resolved; That the recommendations as contained within the report be approved | Approved | Open |
| 30 Sep 2026 | Healthy Organisation Strategy: Workforce Strategy 2026-2029Resolved; That the recommendations as contained within the report be approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.