RESOLVED that An agreement be entered into under Section 25 of the Highways Act 1980 between the Forestry Commission and the County Borough Council to create a bridleway as described above and shown on the plan in appendix 1 of the report. In the event of the Public Path Creation Agreement being executed, a Definitive Map Modification Order be made pursuant to Section 53(3 )( a)(iii) of the Wildlife and Country side Act 1981, to amend the Definitive Map and Statement accordingly to reflect the creation of a bridleway as referred to above, such a bridleway being a right of way to which the map relates, being a right of way such that the land over which the right subsist is a bridleway.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To recommend the acceptance of an offer made by the Forestry Commission for dedication of a Right of Way under Section 25 Highways Act 1980.
INTRODUCTION AND BACKGROUND
The Forestry Commission is the owner of a large tract of land west of the A470. This land is the subject of the proposed dedication.
Since 1990 the Local Authority has received a number of applications to create rights of way over land in the west Merthyr area, and in particular in relation to this report, within the Gethin Woodland Park, i.e. the land in the ownership of the Forestry Commission.
As a result of one of these applications, the route which is the subject of this report was included in an Investigation Report which was made available to the landowner as part of the required consultation exercise. The Forestry Commission now consider that the evidence proffered in this report shows incontrovertibly that a right of way (bridleway) exists on the route and that they wish to regularise the matter by means of a dedication agreement with the local authority, thus enabling the route to be recorded on the Definitive Map and Statement. Dedication by agreement avoids the need for prolonged procedures.
This route is depicted on the plan, Appendix 1 and described below.
The bridleway commences at a gate and adjacent stile (Point A on the plan), grid reference SO0454 0420 and proceeds downhill in a general easterly direction, initially through a wooded avenue and then on a path through open grassland, to its termination, west of the A470 near Upper Abercanaid, at Point B, grid reference SO 0492 0421.
Under Section 25 Highways Act 1980, the authority is entitled to enter into an agreement with a freehold owner for the dedication of a footpath, bridleway or restricted byway. The only consultation that is required for a dedication is with any other local authority which may be affected in any way. There is no other relevant local authority and the only other body that would need to be consulted is the Forestry Commission as the relevant landowner. As the Forestry Commission is the dedicating body, this requirement has been met.
Officers consider that the route which is the subject of the dedication is of benefit to the general public.
It is advised that the dedication of this route will have no adverse effect on the needs of agriculture or forestry or on the conservation of flora, fauna and geological and physiographical features. The creation of the route on a formal basis will enhance the local footpath and bridleway network offering health and leisure benefits to the community.
This route continues onto land which is not within the ownership of the Forestry Commission. The continuation route is subject to further investigation (ongoing) and will be reported separately.
Financial implications
A notice will need to be placed in the local newspaper describing the route. The route will also require signposting. Any route created under this section automatically becomes maintainable at the public expense.
These initial costs will be met out of existing budgets.
Once created, future maintenance of the surface of this route will lie with the Council as Highway Authority as required by statute. These costs will have to be met from future maintenance budgets.
Recommendations
I recommend:-
(1) That an agreement be entered into under Section 25 Highways Act 1980 between the Forestry Commission and the Merthyr Tydfil County Borough Council to create the bridleway described above and depicted in Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dedication of Bridleway leading from a gate and stile within Gethin Woodlands to a point to the west of Upper Abercanaid: Plymouth Electoral DivisionReport
72Dedication of Bridleway leading from a gate and stile within Gethin Woodlands to a point to the west of Upper Abercanaid - Plymouth Electoral DivisionThis decision
Dedication of Bridleway leading from a gate and stile within Gethin Woodlands to a point to the west of Upper Abercanaid - Plymouth Electoral DivisionThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.