RESOLVED that Having considered the criteria laid down in section 257 of the Town and Country Planning Act and also Circular 5/93 (Welsh Office), it is felt that the public would be disadvantaged by the diverted route as the proposal fragments the current network and prohibits people using existing routes. The existing route allows the public to use further routes as shown on the plan in Appendix E of the report. The diverted route would run along the points of A-D-C as shown on the plan. It is known that there are routes which people use leading from Point E on the plan and these routes would not be able to be accessed as where the proposed diversion would end there is a retaining wall approximately 4 metre high. It is felt that the proposed diversion is not suitable for the above reasons. The Public Path Diversion Order be refused and the applicant advised accordingly. On the grounds of equity the applicant either: Receive a refund of £2,500 application fee, or Have the opportunity to submit a revised application. In view of the circumstances surrounding this application, a policy for dealing with the level of charges to be levied in respect of unsuccessful applications should be developed.
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
DATE WRITTEN 5th January 2010 REPORT AUTHOR Beth Jones HEAD OF SERVICE E Foley COMMITTEE DIVISION Strategic COMMITTEE Rights of Way COMMITTEE DATE 22nd February 2010
TO: Chairman, Ladies and Gentlemen
TREHARRIS 21 TOWN AND COUNTRY PLANNING ACT SECTION 257 APPLICATION FOR A PUBLIC PATH DIVERSION ORDER
PURPOSE OF REPORT: To inform Councillors of an application received to divert Footpath 21 Treharris.
1.0INTRODUCTION AND BACKGROUND
1.1An application has been made under Section 257 of the Town and Country Planning Act 1990 to divert a public right of way known as Treharris 21. The application is made to enable development to be carried out. Planning permission for the site was granted in September 2004.
1.2Section 257 of the Town and Country Planning Act 1990 states:
(1) Subject to Section 259, a competent authority may by order authorise the stopping up or diversion of any footpath or bridleway if they are satisfied it is necessary to do so in order to enable development to be carried out:
a) in accordance with planning permission granted under part III or under Section 293a; b) by a Government Department.
(2) An order under this section may, if the competent authority are satisfied that it should do so, provide –
(a) for the creation of an alternative highway for use as a replacement for the one authorised by the order to be stopped up or diverted, or for the improvement of an existing highway for such use; (b) for authorising or requiring works to be carried out in relation to any footpath or bridleway for whose stopping up or diversion, creation or improvement provision is made by the order;
(c) for the preservation of any rights of statutory undertakers in respect of any apparatus of theirs which immediately before the date of the order is under, in, on, over, along or across any such footpath or bridleway;
(d) for requiring any person named in the order to pay, or make contributions in respect of, the cost of carrying out any such works.
(3) An order may be made under this section authorising the stopping up or diversion of a footpath or bridleway which is temporarily stopped up or diverted under any other enactment.
(4) In this section “competent authority” means –
(a) in the case of development authorised by a planning permission, the local planning authority who granted the permission or, in the case of a permission granted by the Secretary of State, who would have had power to grant it; and
(b) in the case of development carried out by a government department, the local planning authority who would have had power to grant planning permission on an application in respect of the development in question if such an application had fallen to be made.
1.3Paragraph 23 of Annexe C of Circular 5/93 (Welsh Office) states that:
“While it is not open to question the merits of the planning permission when considering whether to make or confirm an Order, it should not be assumed that the Order should be made simply because planning permission has been granted. The disadvantages or loss likely to arise as a result of the stopping up or diversion, either to members of the public generally, or to persons whose properties adjoin, or are near the existing highway should be weighed against the advantages to be conferred by the proposed Order.
1.4However, having arrived at the conclusion that it was right for the planning permission to be granted, there must be good reasons for deciding that an Order, which would permit implementation of that permission, should not be made or confirmed.
2.0EXISTING FOOTPATH
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.