CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Merthyr Tydfil County Borough Council
Cabinet, Wednesday 22 December 2010 at 2.30pm

Cyfarthfa Park Signage, Interpretation and Orientation Phase 1

Decided Executive 1 paper

Cabinet decided this item on Wednesday 22 December 2010. Below is the council's own wording, with the papers it was decided on.

Item601

Resolved

RESOLVED that Cabinet receive this report
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 3 pages

Purpose of the report

To inform Councillors of the contract award for Cyfarthfa Park signage, interpretation and orientation scheme and additional works/costs associated with the above project.

1.0INTRODUCTION AND BACKGROUND

1.1Members may recall a report on June 7th 2010 informing Councillors of a Cyfarthfa Park logo and to approve the Cyfarthfa Signage, Interpretation and Orientation Strategy.

1.2A budget of £70,000 was approved from the Heads of the Valleys Programme to implement an initial phase for the strategy.

2.0IMPLEMENTATION OF CYFARTHFA PARK SIGNAGE, INTERPRETATION & ORIENTATION PHASE 1

2.1The primary objective of the scheme is to encourage better presentation and linkages to attractions within the park as well as redevelop products to a corporate standard.

2.2Consultation has been undertaken with the Friends of Cyfarthfa Park and it was agreed to segment the scheme into two phases. Phase two will be dependent on securing future funding however it is expected that it could be delivered through the HLF proposal. 2.3 Phase one proposals include structural fingerpost signs, display cases, entrance signs and plaques and traffic and dog signs. All of which were designed to a corporate brand as approved by Cabinet with the Cyfarthfa Park logo in June 2010.

3.0CONTRACT AWARD

3.1The contract brief was registered on Buy4Wales and product quantities were configured based on a cost model exercise undertaken from the strategy.

3.2There were twenty eight expressions of interest received and eight tenders submitted. The tenders were returned by November 29th 2010 at 1pm.

3.3Arithmetical checks were carried out however some tender submissions did not adequately address the brief. MTCBC officers examined and assessed the submissions and unanimously agreed to award the contract to Fitzpatrick Woolmer at £39,154.42 for a quality submission and demonstrating best value.

4.0CONTRACT VARIATION

4.1The developed cost model highlighted that the budget restricted the desired scheme. Following a competitive tender return which was much lower than anticipated, there is now an opportunity to deliver the additional products that were previously omitted.

4.2Based on the product rates from the winning tender, a formal quote was received outlining the additional product quantities requested. The additional products were priced at £19,146.58 totalling a 48.9% increase on the original contract price. The variation request has been signed and approved under analytical process.

5.0FINANCIAL IMPLICATION(S)

3.1The strategy initial phase in being funded by the Heads of the Valleys Programme. There are no direct financial implications for MTCBC, other than the need for officer time in supporting and monitoring development of the project.

GARETH CHAPMAN CHIEF EXECUTIVE BACKGROUND PAPERS Title of Document(s) Document(s) Date Document Location Hyder Report September 2008 Physical Regeneration

Cyfarthfa Park September 2009 Physical Regeneration Conservation Management Plan

Cyfarthfa Park Signage August 2010 Physical Regeneration & Orientation Strategy

Consultation has been undertaken with Executive Board in respect of each proposal(s) and recommendation(s) set out in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cyfarthfa Park Signage, Interpretation and Orientation Phase 1Report 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Merthyr Tydfil

Search all
  1. Cyfarthfa Park Signage, Interpretation and Orientation Phase 1This decision
  2. Application for a variation of a premises licence - McDonalds Restaurant, Cyfarthfa Retail Park, Swansea Road, Merthyr TydfilDecided
  3. P/17/0327 - B & Q, Cyfarthfa Retail Park, Swansea Road, Merthyr TydfilRefused
  4. Cyfarthfa Parks for People 2: Heritage Lottery Fund Stage 1 ApprovalDecided
  5. P/15/0046 - Land between Merthyr College, Cyfarthfa Retail Park and Keir Hardie Health ParkApproved
  6. Cyfarthfa Park - Bothy Rural Heritage Centre Contract AwardApproved

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies