Redevelopment of Miniature Railway site and paddling pool / play area at Cyfarthfa Park

Noted Executive 1 paper

Cabinet noted this item on Wednesday 22 December 2010. Below is the council's own wording, with the papers it was decided on.

Item602

Resolved

RESOLVED that Cabinet note the content of the report and approve the appointment of Flowline Civil Engineering Ltd to undertake the works to the redevelopment of the miniature railway site and paddling pool /play area in the sum of £261,215.00
Word for word from the decision Merthyr Tydfil published for this meeting. Source: democracy.merthyr.gov.uk

Follow this further

Built from Merthyr Tydfil's papers

What the report saysPro

Report to Cabinet, 3 pages

Purpose of the report

To seek approval of the appointment of a contractor to undertake the construction works for the redevelopment of Miniature Railway site and paddling pool / play area at Cyfarthfa Park.

1.0INTRODUCTION AND BACKGROUND

1.1A report was presented to Cabinet on 14th April 2010 informing members of the funding secured through the Heads of the Valley’s Programme to fund the Miniature Railway Project at Cyfarthfa Park and the appointment of Capita Symonds to design and manage the project.

2.0APPOINTMENT OF CONTRACTORS 2.1 Detailed designs and a cost model has been developed by Capita and due to the conditions imposed by CADW the cost estimate for the scheme has increased from the original £200k to £300k. Therefore additional funding has been approved by the Heads of the Valleys programme.

2.2Planning permission for the scheme was granted on 15th December. Tender documents were issued by Capita to five contractors on 19th November 2010, to be returned by 17th December 2010. The tender included all landscaping works associated with the redevelopment of the model railway and external refurbishment of the toilet block. The tender excluded the purchase and installation of the railway track as this will be undertaken by the model railway company once the contract is completed.

2.3The tenders were returned and opened as follows:

Tender 1 £ 261,215.00 Tender 2 £ 286,734.00 Tender 3 £ 419,411.00 Tender 4 £ 454,450.00

2.4The tenders received have been reviewed and assessed by Capita and the lowest tender received is from Flowline Civil Engineering Ltd in the sum of £261,215.00.

2.5Capita have confirmed the tender is considered very competitively priced and does not contain any specific qualifications. An arithmetical check of this tender was carried out and no errors were found. The contractor has confirmed that they are fully committed to the scheme in terms of time and quality.

2.6Construction works will commence in early January and will be completed by end March 2011.

2.7Quotations for the purchase of the track are currently being obtained by Capita which is expected to be in the region of £30,000. The railway track will then be handed over to the Model Railway Company for installation following completion of the main contract by end March 2011. Therefore, the new railway should be fully operational by the Model Railway Company by June 2011.

2.8The works will be managed by Capita Glamorgan who will be the contract administrators and overseen by Engineering Department who will provide the necessary technical advice and undertake site inspections.

3.0FINANCIAL IMPLICATIONS 3.1 The scheme is funded by the Heads of the Valleys Programme, £300k has been approved. There are no direct financial implications for MTCBC, other than the need for officer time in supporting and monitoring development of the project.

4.0RECOMMENDATION(S) that

4.1Cabinet notes the contents of this Report and approves the appointment of Flowline Civil Engineering Ltd to undertake the works to the redevelopment of the miniature railway site and paddling pool / play area in the sum of £261,215.00.

GARETH CHAPMAN CHIEF EXECUTIVE

BACKGROUND PAPERS Title of Document(s) Document(s) Date Document Location Project Initiation Document 2009 Physical Regeneration Design Brief 2009 Planning permission 2010 Design board 2010 Pavilion Extension Brief February 2010 Capita Tender Report December 2010

Consultation has been undertaken with Executive Board in respect of each proposal(s) and recommendation(s) set out in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Redevelopment of Miniature Railway site and paddling pool / play area at Cyfarthfa ParkReport 3 pages DownloadRead as text

At this meeting

Whole meeting

More from Merthyr Tydfil Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 The Tobacco and Vapes Act 2026 - Scheme of DelegationResolved that: 2.1 Approve the inclusion of the Tobacco and Vapes Act 2026 within the Council's Scheme of Delegation.... Approved Open
22 Oct 2026 Annual Equality Report 2025-2026Resolved that: 2.1 The Council’s Annual Equality Report for 2025-2026 be approved for publishing. Approved Open
22 Oct 2026 Bright Futures Education Strategy 2026 - 2030Resolved that: 2.1 The Bright Futures Education Strategy 2026-2030 (Appendix 1) be discussed and noted prior to Full ... Noted Open
22 Oct 2026 Greenfield Special School - Satellite ProvisionResolved that: 2.1 The use of the vacated former St Mary’s Primary School site as an interim solution for Greenfield ... Approved Open
22 Oct 2026 Provisional Capital Outturn Report 2025/26Resolved that: 2.1 The provisional Capital Outturn position for the 2025/26 financial year be noted. 2.2 The budget a... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies