RESOLVED that Cabinet note the content of the report and approve the appointment of Flowline Civil Engineering Ltd to undertake the works to the redevelopment of the miniature railway site and paddling pool /play area in the sum of £261,215.00
Word for word from the decision Merthyr Tydfil published for this meeting.Source: democracy.merthyr.gov.uk
To seek approval of the appointment of a contractor to undertake the construction works for the redevelopment of Miniature Railway site and paddling pool / play area at Cyfarthfa Park.
1.0INTRODUCTION AND BACKGROUND
1.1A report was presented to Cabinet on 14th April 2010 informing members of the funding secured through the Heads of the Valley’s Programme to fund the Miniature Railway Project at Cyfarthfa Park and the appointment of Capita Symonds to design and manage the project.
2.0APPOINTMENT OF CONTRACTORS 2.1 Detailed designs and a cost model has been developed by Capita and due to the conditions imposed by CADW the cost estimate for the scheme has increased from the original £200k to £300k. Therefore additional funding has been approved by the Heads of the Valleys programme.
2.2Planning permission for the scheme was granted on 15th December. Tender documents were issued by Capita to five contractors on 19th November 2010, to be returned by 17th December 2010. The tender included all landscaping works associated with the redevelopment of the model railway and external refurbishment of the toilet block. The tender excluded the purchase and installation of the railway track as this will be undertaken by the model railway company once the contract is completed.
2.3The tenders were returned and opened as follows:
2.4The tenders received have been reviewed and assessed by Capita and the lowest tender received is from Flowline Civil Engineering Ltd in the sum of £261,215.00.
2.5Capita have confirmed the tender is considered very competitively priced and does not contain any specific qualifications. An arithmetical check of this tender was carried out and no errors were found. The contractor has confirmed that they are fully committed to the scheme in terms of time and quality.
2.6Construction works will commence in early January and will be completed by end March 2011.
2.7Quotations for the purchase of the track are currently being obtained by Capita which is expected to be in the region of £30,000. The railway track will then be handed over to the Model Railway Company for installation following completion of the main contract by end March 2011. Therefore, the new railway should be fully operational by the Model Railway Company by June 2011.
2.8The works will be managed by Capita Glamorgan who will be the contract administrators and overseen by Engineering Department who will provide the necessary technical advice and undertake site inspections.
3.0FINANCIAL IMPLICATIONS 3.1 The scheme is funded by the Heads of the Valleys Programme, £300k has been approved. There are no direct financial implications for MTCBC, other than the need for officer time in supporting and monitoring development of the project.
4.0RECOMMENDATION(S) that
4.1Cabinet notes the contents of this Report and approves the appointment of Flowline Civil Engineering Ltd to undertake the works to the redevelopment of the miniature railway site and paddling pool / play area in the sum of £261,215.00.
GARETH CHAPMAN CHIEF EXECUTIVE
BACKGROUND PAPERS Title of Document(s) Document(s) Date Document Location Project Initiation Document 2009 Physical Regeneration Design Brief 2009 Planning permission 2010 Design board 2010 Pavilion Extension Brief February 2010 Capita Tender Report December 2010
Consultation has been undertaken with Executive Board in respect of each proposal(s) and recommendation(s) set out in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.